FOSTER ELECTRIC CORPORATION | E= | C | 10/01/2019 | Computer generated inspection complete / | ROB | ROB | | E= | C | 6353001 |
FOSTER ELECTRIC CORPORATION | E= | P | 04/05/2019 | Electrical complete /. Additional Inspections Required (computer generated): External Agency Inspection HD= by HEALTHDEPT is not Completed yet, , , -- Schedule a new final inspection after these are complete. | ROB | ROB | | E= | P | 6156246 |
FOSTER ELECTRIC CORPORATION | ER | C | 04/03/2019 | above ceiling okay | CHIPO | CHIPO | | ER | C | 6153602 |
FOSTER ELECTRIC CORPORATION | ER | P | 03/21/2019 | Oven wall rough ok / | ROB | ROB | | ER | P | 6139814 |
LANDMARK PLUMBING AND HEATING, INC. | H= | C | 06/06/2019 | Correction made | MARKB | MARKB | | H= | C | 6223036 |
HVAC SOLUTIONS, INC. | H= | C | 05/13/2019 | | MARKB | MARKB | | H= | C | 6196227 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 05/09/2019 | CAN FINAL ONCE REQUESTED BY CONTRACTOR | MARKB | MARKB | | H= | P | 6194253 |
HVAC SOLUTIONS, INC. | H= | P | 04/11/2019 | GOOD TEST AND BALANCE RECEIVED | MARKB | MARKB | | H= | P | 6162396 |
HVAC SOLUTIONS, INC. | H= | P | 04/08/2019 | Looks like Test And Balance was performed using demo page in plans? | MARKB | MARKB | | H= | P | 6158375 |
LANDMARK PLUMBING AND HEATING, INC. | H= | P | 04/05/2019 | FINAL PENDING - SEAL AROUND GAS STUBS IN HOOD WALL LIQUID TIGHT. TIFF TEST ON ALL CONNECTIONS COMPLETE, DISCONNECTS AND RESTRAINTS COMPLETE. | MARKB | MARKB | | H= | P | 6157194 |
HVAC SOLUTIONS, INC. | H= | P | 04/05/2019 | FINAL PENDING - Complete sealing hood wall seams and provide test and balance report.
UTILITY SET FAN GASKET, TRAY CLEAN OUT ACCESS ON ROOF COMPLETE. MAKEUP AIR DUCT CONNECTIONS COMPLETE. HOOD WALL CAPPED AND SEALED ABOVE HOOD. INTERLOCKS CONFIRMED, GREASE CUPS AND FILTERS IN PLACE. | MARKB | MARKB | | H= | P | 6157180 |
HVAC SOLUTIONS, INC. | HD | C | 04/04/2019 | 2 LAYERS OF GREASE DUCT WRAP WITH BANDS COMPLETE. | MARKB | MARKB | | HD | C | 6155724 |
LANDMARK PLUMBING AND HEATING, INC. | H= | R | 04/03/2019 | No gas piping on plans for dishwasher, is this for pizza oven, if so attached to wrong permit. Spoke with general contractor on site. | MARKB | MARKB | | H= | R | 6155398 |
HVAC SOLUTIONS, INC. | HD | P | 03/28/2019 | GREASE DUCT LIGHT TEST COMPLETE - OK TO WRAP DUCT WITH 2 LAYERS. | MARKB | MARKB | | HD | P | 6148396 |
HVAC SOLUTIONS, INC. | HD | P | 03/28/2019 | GREASE DUCT LIGHT TEST - LOOKED AT ALL SEAMS FOR COMPLETE DUCT SYSTEM INSIDE BUILDING FOR BOTH HOODS - FOUND 1 HOLE FOR CONTRACTOR TO ADDRESS. | MARKB | MARKB | | HD | P | 6148036 |
HVAC SOLUTIONS, INC. | HD | P | 03/25/2019 | HOOD WALL INSPECTION - HOOD WALL IS ALL NON-COMBUSTIBLE CONSTRUCTION. | MARKB | MARKB | | HD | P | 6143907 |