T-BONE CONSTRUCTION, INC. | B= | C | 11/05/2019 | final OK pending other finals | DANE | DANE | | B= | C | 6388420 |
T-BONE CONSTRUCTION, INC. | BFR | P | 11/05/2019 | stamped letter for CMU wall construction on file / this completes the BFR inspections pending other roughs | DANE | DANE | | BFR | P | 6388101 |
T-BONE CONSTRUCTION, INC. | B= | L | 10/31/2019 | no access to site at loading docks / could not make contact with the contractor on site / call ahead was sent and failed 4 times and made physical call ahead to number provided and it would not go through before arrival on site / will need engineer observation for CMU wall when final is recalled / wall is called out as 1hr fire barrier (UL U906) for other than IBC | DANE | DANE | | B= | L | 6385020 |
T-BONE CONSTRUCTION, INC. | BFN | P | 07/02/2019 | forms and reinforcement for electrical vault at rear of dock area OK pending other roughs / need to attach mechanical and plumbing permits and have inspections | DANE | DANE | | BFN | P | 6251059 |
T-BONE CONSTRUCTION, INC. | BFT | P | 04/01/2019 | pier and footing reinforcement for CMU wall at exterior electrical yard now OK | DANE | DANE | | BFT | P | 6150585 |
T-BONE CONSTRUCTION, INC. | BFT | P | 03/29/2019 | transformer pad at northwest corner of building by loading docks is OK but the pier and footing for the CMU wall extension is not ready as it needs to be dug out and remainder of bars set and hung / OK to use engineer for wall footing if desired / contractor noted that depth of hole is to change - if depth of pier is to change from what the approved plan states a stamped design is required to either be uploaded on an online inspection request or will need to pick up hard copy at next inspection | DANE | DANE | | BFT | P | 6148742 |
STURGEON ELECTRIC CO INC | E= | C | 09/12/2019 | | GARYL | GARYL | | E= | C | 6333220 |
STURGEON ELECTRIC CO INC | EP | P | 08/09/2019 | Panel MS-1 DP H1A | GARYL | GARYL | | EP | P | 6295132 |
STURGEON ELECTRIC CO INC | ES | C | 07/19/2019 | Commercial Service: DOWN SIZING EXISTING SERVICE TO 2000 AMPS, NEED TO COORDINATE WITH ELECTRICAL CONTRACTOR FOR OUTAGE AND RESTORING POWER | GARYL | GARYL | | ES | C | 6269886 |
STURGEON ELECTRIC CO INC | EP | P | 05/31/2019 | panels and transformer OK | CRAIGS | CRAIGS | | EP | P | 6216333 |
STURGEON ELECTRIC CO INC | EUG | P | 03/28/2019 | CT pipe ok / Contractor will contact CSU Quality control for transformer pad /All stub up in pad are existing / | ROB | ROB | | EUG | P | 6148119 |
HEATING & PLUMBING ENGINEERS, INC | H= | C | 08/19/2019 | HEAT FINAL OK. | LIDO | LIDO | | H= | C | 6305312 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 08/14/2019 | HEAT WATER PIPING INSULATED AND LABELED ( SEE IMAGES) PARTIAL PENDING : PLUMBING TO ATTACH TO PERMIT. | LIDO | LIDO | | H= | P | 6299512 |
HEATING & PLUMBING ENGINEERS, INC | H= | P | 08/12/2019 | PARTIAL PENDING: ATTACH PLUMBING TO PERMIT. LABEL HEAT WATER SUPPLY AND RETURN / OK TO ATTACH PICTURES TO NEXT INSPECTION REQUEST.(( HEAT WATER SUPPLY AND RETURN UNDER OPERATING PRESSURE NO VISIBLE LEAKS)) | LIDO | LIDO | | H= | P | 6297588 |
HEATING & PLUMBING ENGINEERS, INC | P= | C | 08/20/2019 | Demo of Hose bib, Trap primer and Floor drain over lower level water entry. | SAMH | SAMH | | P= | C | 6308009 |
STURGEON ELECTRIC CO INC | XES | T | 06/26/2019 | PAID (REC#1609509) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised utility vault. | BERTHA | BERTHA | | XES | T | 6244319 |
T-BONE CONSTRUCTION, INC. | XBS | P | 06/26/2019 | PLAN SPLICE: (No Fee) by: DANM for Construction: Revision to Utility Vault detail | DANM | DANM | | XBS | P | 6244277 |