GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 12/20/2019 | All other required Final inspections are complete. (This is a computer generated result) | SCOTTS | SCOTTS | | B= | C | 6433399 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 06/24/2019 | pending other finals/rest ok. Additional Inspections Required (computer generated): COLORADO SHEET METAL CO., INC. Mechanical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, STURGEON ELECTRIC CO INC Electrical Final Inspection is not Completed yet. | SCOTTS | SCOTTS | | B= | P | 6241153 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 04/23/2019 | training with PPRBD Inspector Brian B/reviewed 1A construction per 2009 IBC table 601/ reviewed code study/plan sticker/plan review notes | SCOTTS | SCOTTS | | BSP | P | 6175849 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 04/23/2019 | observed light gauge non-load bearing wall framing / pending other rough inspections / Training with PPRBD inspector Scott - reviewed 1A construction type per table 601 / reviewed plan sticker - code study and plan review notes | BRIANB | BRIANB | | BFR | P | 6175840 |
STURGEON ELECTRIC CO INC | E= | C | 07/01/2019 | | RANDY | RANDY | | E= | C | 6250291 |
STURGEON ELECTRIC CO INC | ER | C | 07/01/2019 | | RANDY | RANDY | | ER | C | 6250274 |
STURGEON ELECTRIC CO INC | ER | P | 06/24/2019 | please have jeremy in the morning thanks. | RANDY | RANDY | | ER | P | 6242061 |
STURGEON ELECTRIC CO INC | EP | P | 06/21/2019 | panel NL1F and transformer TNL1F | RANDY | RANDY | | EP | P | 6238947 |
STURGEON ELECTRIC CO INC | ER | P | 05/17/2019 | electric in slab ok | RANDY | RANDY | | ER | P | 6203535 |
STURGEON ELECTRIC CO INC | ER | P | 04/16/2019 | walls for CT room | RANDY | RANDY | | ER | P | 6167870 |
COLORADO SHEET METAL CO., INC. | H= | C | 12/20/2019 | RECEIVED STAMPED ENGINEER LETTER APPROVING THE TEST AND BALANCE REPORT READING. ( SEE IMAGES ) | LIDO | LIDO | | H= | C | 6433398 |
COLORADO SHEET METAL CO., INC. | H= | P | 11/15/2019 | TEST AND BALANCE REPORT : SLOT # 10 IS STILL OUTSIDE THE 10 % PLUS OR MINUS ALLOWED . NEED REVISED TEST AND BALANCE REPORT OR STAMPED ENGINEER LETTER APPROVING THE READINGS. | LIDO | LIDO | | H= | P | 6400188 |
COLORADO SHEET METAL CO., INC. | H= | P | 11/04/2019 | PARTIAL PENDING: TEST AND BALANCE REPORT REVIEW: T-B-1-87 GRILL 1 AND 2 - THE CORRECT DESIGN CFM'S NOT USED. FCU-1330 - SLOT 10 IS OUTSIDE THE ALLOWED 10%. NEED REVISED TEST AND BALANCE REPORT OR STAMPED ENGINEER LETTER APPROVING THE READINGS. | LIDO | LIDO | | H= | P | 6386753 |
COLORADO SHEET METAL CO., INC. | H= | P | 10/31/2019 | FIELD CANCELED BY CONTRACTOR. | LIDO | LIDO | | H= | P | 6384756 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 07/01/2019 | CONFIRMED BY CONTRACTOR PIPE IS INSULATED AND LABELED ((HEAT FINAL OK .)) | LIDO | LIDO | | H= | C | 6250094 |
COLORADO SHEET METAL CO., INC. | H= | P | 06/24/2019 | PARTIAL PENDING : LABEL FCU-1330 / TOP OF THERMOSTAT FOR FCU-1330 / TB-1330 SHALL NOT BE MORE THAN 48" OFF FINISHED FLOOR. (( EXISTING THERMOSTAT FOR TB-187 WAS NOT RELOCATED ))NEED TEST AND BALANCE REPORT.
| LIDO | LIDO | | H= | P | 6242195 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 06/24/2019 | LOW PRESSURE STEAM UNDER OPERATING PRESSURE OK/ NO VISIBLE LEAKS. PARTIAL PENDING : INSULATE AND LABEL HEAT WATER SUPPLY AND RETURN/ CHILLED WATER SUPPLY AND RETURN / LOW PRESSURE STEAM . SIZES FOR THE CHILLED WATER SUPPLY AND RETURN FOR FCU-1330 ARE NOT SHOWN ON PLANS / 1-1/4" INSTALLED ,NEED REVISED AND APPROVED PLANS TO MATCH INSTALL. | LIDO | LIDO | | H= | P | 6242194 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 06/21/2019 | H-1330 : STILL NEED TEST FOR LOW PRESSURE STEAM / INSTALLED PER PLAN . LOW PRESSURE CONDENSATE INSTALLED PER PLAN/ OK TO INSULATE AND LABEL. SIZES FOR THE CHILLED WATER SUPPLY AND RETURN FOR FCU-1330 ARE NOT SHOWN ON PLANS / 1-1/4" INSTALLED ,NEED REVISED AND APPROVED PLANS TO MATCH INSTALL. FCU -1330 : CHILLED WATER SUPPLY AND RETURN UNDER OPERATING PRESSURE - NO VISIBLE LEAKS / OK TO INSULATE AND LABEL. CONDENSATE DISPOSAL OK . TB-1330 : HEAT WATER SUPPLY AND RETURN UNDER OPERATING PRESSURE - NO VISIBLE LEAKS/ INSTALLED PER PLAN / OK TO INSULATE AND LABEL. OK TO ATTACH PICTURES OF INSULATION AND LABELS ON NEXT INSPECTION REQUEST.
| LIDO | LIDO | | H= | P | 6240407 |
COLORADO SHEET METAL CO., INC. | HD | P | 06/07/2019 | STILL NEED SUPPLY DUCT ROUGH FOR CONTROL ROOM. NEED FCU-1330 INSTALLED. REST OF ABOVE CEILING SUPPLY, RETURN AND EXHAUST DUCT ROUGH INCLUDING VAV -1330 AND HUMIDIFIER OK / OK TO WRAP. | LIDO | LIDO | | HD | P | 6224536 |
COLORADO SHEET METAL CO., INC. | HD | P | 05/08/2019 | 6 X 6 SUPPLY AIR DUCT IN WALL ONLY OK . | LIDO | LIDO | | HD | P | 6192816 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 06/21/2019 | pet-ct sink | TED | TED | | P= | C | 6239827 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 06/21/2019 | over head dwv rerouted lines, | TED | TED | | PTO | C | 6239821 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 04/05/2019 | DWV and water lines OK to sink, and hub drain. F line P101 | SAMH | SAMH | | PTO | P | 6156747 |
OLSON PLUMBING & HEATING COMPANY | XMS | P | 06/28/2019 | PLAN SPLICE FEE: $0 by: JUSTINC for Mechanical: Revised chilled water pipe size | JUSTINC | JUSTINC | | XMS | P | 6248387 |