ELDER CONSTRUCTION, INC. | B= | C | 08/29/2019 | All other required Final inspections are complete. (This is a computer generated result) | DANE | DANE | | B= | C | 6319442 |
ELDER CONSTRUCTION, INC. | B= | P | 08/21/2019 | items corrected / final OK pending other finals. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FRONTIER MECHANICAL SYSTEMS INC Plumbing Final Inspection is not Completed yet, GREINER ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | P | 6308545 |
ELDER CONSTRUCTION, INC. | B= | R | 08/19/2019 | flush handle at women's restroom 131 needs to be on open side of toilet / need to complete both sides of the head of wall for the UL U465 rated corridor wall per the head of wall detail on page A1.1 in detail 6 on splice dated 5/21/19 / need to complete all other finals. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), FRONTIER MECHANICAL SYSTEMS INC Plumbing Final Inspection is not Completed yet, GREINER ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, NIELSEN MECHANICAL CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | DANE | DANE | | B= | R | 6306343 |
ELDER CONSTRUCTION, INC. | BFR | P | 05/24/2019 | Framing OK pending other Roughs / discussed UL U495 at the new doorway (Corridor 110F near Room 126) / discussed accessible elements including sink heights and door clearances | RICHB | RICHB | | BFR | P | 6209839 |
GREINER ELECTRIC, LLC. | E= | C | 08/27/2019 | | GARYL | GARYL | | E= | C | 6315308 |
GREINER ELECTRIC, LLC. | E= | R | 08/16/2019 | GFCI not changed out, canceled at call a head | GARYL | GARYL | | E= | R | 6303742 |
GREINER ELECTRIC, LLC. | E= | P | 08/15/2019 | 1) need up dated panel schedules, 2) gfci protection in clean room next to 4-wire 220v recept | GARYL | GARYL | | E= | P | 6302066 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 07/25/2019 | FIRE ALARM INSPECTION: signed F/A card | GARYL | GARYL | | E= | C | 6276648 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 07/25/2019 | FIRE ALARM INSPECTION: ALL CEILINGS | GARYL | GARYL | | ER | C | 6276624 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 07/25/2019 | FIRE ALARM INSPECTION: ALL CEILINGS | GARYL | GARYL | | E= | C | 6276625 |
GREINER ELECTRIC, LLC. | ER | P | 07/25/2019 | ALL ceilings, EXCEPT IN ROOM 114, REWORKING STEEL TO HOLD EXAM LIGHT | GARYL | GARYL | | ER | P | 6276622 |
GREINER ELECTRIC, LLC. | ER | P | 06/18/2019 | ALL hardlids, ALL kneewalls--nurses stations | GARYL | GARYL | | ER | P | 6235090 |
GREINER ELECTRIC, LLC. | ER | P | 06/05/2019 | 3 bath lids, 3 mill work walls | BRET | BRET | | ER | P | 6220845 |
GREINER ELECTRIC, LLC. | ER | P | 06/03/2019 | Rough ok for walls hi-lited blue on prints / | ROB | ROB | | ER | P | 6218596 |
GREINER ELECTRIC, LLC. | ER | L | 05/31/2019 | contractor cancelled | CRAIGS | CRAIGS | | ER | L | 6216294 |
GREINER ELECTRIC, LLC. | ER | P | 05/24/2019 | walls high lighted in pink OK | CRAIGS | CRAIGS | | ER | P | 6210355 |
GREINER ELECTRIC, LLC. | EUG | C | 04/24/2019 | floor boxes --- emt with anti corrosion tape OK | CRAIGS | CRAIGS | | EUG | C | 6176302 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | C | 08/29/2019 | HEAT FINAL OK. | LIDO | LIDO | | H= | C | 6319441 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 08/14/2019 | ((NOTE 4 AND NOTE 6 ARE TRANSVERSE )) PARTIAL PENDING - NEED HEAT FINAL INSPECTION, NEED TEST AND BALANCE REPORT. | LIDO | LIDO | | H= | P | 6299860 |
NIELSEN MECHANICAL CONTRACTORS, INC. | H= | P | 07/19/2019 | ((NEED REVISED / APPROVED PLANS FOR THE FOLLOWING- NOTE 4 WHICH REFERENCES TRANSFER AIR IS SHOWN ON THE DRYER VENT AND IS NOT CORRECT . THIS SHOULD SHOW NOTE 6 TO REFERENCE THE DRYER VENT.)) ABOVE CEILING FINAL OK , INCLUDING DRYER VENT. | LIDO | LIDO | | H= | P | 6270606 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 06/26/2019 | NEED REVISED AND APPROVED PLANS FOR MEDIUM PRESSURE SUPPLY TO VAV-139 IS NO LONGER PENETRATING THE RATED WALL IN THE CORRIDOR / REVISED PLANS WILL NEED TO REFLECT NO FIRE/SMOKE DAMPER TO BE INSTALLED. EXHAUST DUCT FROM LAB-134 IS INSTALLED PER SPLICE THAT IS BEING REVIEWED BY PLANS AND REVIEW / 6" EXHAUST DUCT DOES NOT PENETRATE THE RATED SHAFT WHEN EXITING THE BUILDING/ EXHAUST ROUGH AND REGISTER OK. ((ABOVE CEILING FINAL FOR CORRIDOR THAT VAV-139 / DUCT ROUGH / SUPPLY FINAL TIE-INS INSTALLED OK .)) | LIDO | LIDO | | HD | P | 6245580 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 05/29/2019 | NEED REVISED/APPROVED PRINTS FOR CHANGES TO EXHAUST DUCT IN LAB 134. EXHAUST DUCTS ABOVE HARD LIDS OK. | DUSTINS | DUSTINS | | HD | P | 6213572 |
NIELSEN MECHANICAL CONTRACTORS, INC. | HD | P | 04/23/2019 | ABOVE CEILING DUCT ROUGH FOR SUPPLY,RETURN AND EXHAUST OK / OK TO WRAP. STILL NEED EXHAUST AND TRANSFER FANS AND DUCT ROUGH COMPLETED . NEED TEST AND BALANCE REPORT BY FINAL. | LIDO | LIDO | | HD | P | 6175691 |
FRONTIER MECHANICAL SYSTEMS INC | PB | C | 08/21/2019 | Ice maker drain tie in at break room sink. | SAMH | SAMH | | PB | C | 6309090 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 08/21/2019 | Vent POC ok. | SAMH | SAMH | | PTO | C | 6308792 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 08/21/2019 | | SAMH | SAMH | | P= | C | 6308791 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 06/03/2019 | All in wall plumbing, and hall vents OK. Need to check 3" vent to POC with existing system. | SAMH | SAMH | | PTO | P | 6218601 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 05/28/2019 | In walls OK at rooms 118, 119, 120, 121, 122, 130, 131, 132, 134. Vents tested in ceiling through hall. | SAMH | SAMH | | PTO | P | 6211927 |
FRONTIER MECHANICAL SYSTEMS INC | PB | P | 04/22/2019 | Delete hub drain at room #122. Rest OK. | SAMH | SAMH | | PB | P | 6174265 |
NIELSEN MECHANICAL CONTRACTORS, INC. | XMS | P | 08/27/2019 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Mechanical: delta 4 only revised keyed note | TCRIPPEN | TCRIPPEN | | XMS | P | 6316113 |
NIELSEN MECHANICAL CONTRACTORS, INC. | XMS | T | 06/27/2019 | PAID (REC#1609886) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised layout | JUSTINC | JUSTINC | | XMS | T | 6245883 |
GREINER ELECTRIC, LLC. | XES | P | 05/21/2019 | PLAN SPLICE FEE: $0 by: SHELBY for Electrical: Lighting as builts | SHELBY | SHELBY | | XES | P | 6205838 |
NIELSEN MECHANICAL CONTRACTORS, INC. | XMS | P | 05/21/2019 | PLAN SPLICE FEE: $0 by: DALEH for Mechanical: clouded revisions only | DALEH | DALEH | | XMS | P | 6205811 |
ELDER CONSTRUCTION, INC. | XBS | T | 05/21/2019 | PAID (REC#1600201) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revise wall type ti 1-hr. | MICHAELA | MICHAELA | | XBS | T | 6205578 |