TRI-STAR MASONRY, INC. | B= | C | 11/06/2019 | | BRIANB | BRIANB | | B= | C | 6389854 |
TRI-STAR MASONRY, INC. | B= | P | 11/04/2019 | restroom signage at men's and uni-sex restroom are not installed at latch side of door -- Schedule a new Building Final when above items are complete. | BRIANB | BRIANB | | B= | P | 6386886 |
TRI-STAR MASONRY, INC. | B= | P | 07/01/2019 | missing all restroom signage / need to complete other final inspections and shell final inspection -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), AIR TECH MECHANICAL INC Mechanical Final Inspection is not Completed yet, GRANT DRUMMOND II Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 6249603 |
TRI-STAR MASONRY, INC. | BFR | P | 05/21/2019 | need to revise design to reflect as built condition - to reflect 42" high knee wall installed for cabinets at reception area in lieu of 7' high curved wall on design / observed light gauge non-load bearing wall framing and hard lid framing / discussed accessible elements with the site rep and discussed completing inspections for structure (permit L49233) / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 6205671 |
ELECTRIC TECH INC. | E= | C | 06/27/2019 | | CRAIG | CRAIG | | E= | C | 6247340 |
ELECTRIC TECH INC. | ER | C | 06/25/2019 | All rough in completed | CHIPO | CHIPO | | ER | C | 6243359 |
ELECTRIC TECH INC. | ER | P | 06/24/2019 | above ceiling ok | CRAIG | CRAIG | | ER | P | 6241558 |
ELECTRIC TECH INC. | ER | P | 05/28/2019 | Remainder of rocked walls rough in okay | CHIPO | CHIPO | | ER | P | 6211557 |
ELECTRIC TECH INC. | ER | P | 05/22/2019 | walls only marked on plans | CRAIG | CRAIG | | ER | P | 6207224 |
ELECTRIC TECH INC. | ESL | P | 05/03/2019 | Floor box in Conference room | JOSEPH | JOSEPH | | ESL | P | 6186126 |
AIRTECH MECHANICAL, INC. | H= | C | 07/02/2019 | CORRECTION MADE | BILLS | BILLS | | H= | C | 6251697 |
AIRTECH MECHANICAL, INC. | H= | P | 07/02/2019 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. STILL NEED TO VERIFY CAPPED FUTURE USE WATER HEATER BVENT | BILLS | BILLS | | H= | P | 6250844 |
AIRTECH MECHANICAL, INC. | H= | P | 06/27/2019 | NEED TEST AND BALANCE REPORT, CAP FUTURE USE WATER HEATER BVENT (ELECTRIC WATER HEATER INSTALLED), | BILLS | BILLS | | H= | P | 6246806 |
AIRTECH MECHANICAL, INC. | HD | P | 04/15/2019 | ----NEED ELECTRICAL CONTRACTOR ATTACHED TO PERMIT---- ABOVE CEILING DUCT - SUPPLY/RETURN MAINS/BRANCHES INSTALLED PER PLAN OK TO WRAP. No exhaust/flex/diffusers this inspection. Walls not installed at this time. | MARKB | MARKB | | HD | P | 6166215 |
DRUMMOND PLUMBING LLC | P= | C | 07/02/2019 | | JOEL | JOEL | | P= | C | 6251219 |
DRUMMOND PLUMBING LLC | P= | P | 07/01/2019 | need plan splice for water heater change from gas to electric, still need water piping insulation at water heater, note: R.P. irrigation backflow in water meter room | TED | TED | | P= | P | 6249457 |
DRUMMOND PLUMBING LLC | P= | P | 06/28/2019 | need insulation at water heater on hot and return piping, need electric outlet for return pump, (not plugged in), no hot water temp. to fixtures, note: rest ok | TED | TED | | P= | P | 6247730 |
DRUMMOND PLUMBING LLC | PTO | P | 05/22/2019 | Need room 119 toilet flange glued and anchored, 2 vtr penetrations, rest ok. Note: at final check water heater, and over head hot / recirc insulation, room 104 toilet 19" off framing by final need 16"-18" off finish wall, discussed accessible elements. | DANR | DANR | | PTO | P | 6207133 |
DRUMMOND PLUMBING LLC | PTO | P | 05/21/2019 | field cancel | TED | TED | | PTO | P | 6205674 |
DRUMMOND PLUMBING LLC | PB | C | 04/16/2019 | Ok. | DANR | DANR | | PB | C | 6166492 |
DRUMMOND PLUMBING LLC | PB | P | 04/15/2019 | No drawings on site, drawings not uploading on computer, will revise notes from office in the morning, cover at own risk. | DANR | DANR | | PB | P | 6166107 |
DRUMMOND PLUMBING LLC | XPS | T | 07/02/2019 | PAID (REC#1611098): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Plumbing splice 7/2/19: Delta 2 revision adjust fixture schedule for electric WH-1. | SHANEN | SHANEN | | XPS | T | 6251120 |
TRI-STAR MASONRY, INC. | XBS | P | 06/28/2019 | PLAN SPLICE: (No Fee) by: MICHAELA for Construction: casework reconfigured | MICHAELA | MICHAELA | | XBS | P | 6247504 |
AIRTECH MECHANICAL, INC. | XMS | T | 04/18/2019 | PAID (REC#1609819): PLAN SPLICE FEE: $50 by: SHANEN for Mechanical: Revised schedule and gas | SHANEN | SHANEN | | XMS | T | 6170635 |