ELDER CONSTRUCTION, INC. | B= | C | 09/03/2019 | All other required Final inspections are complete. (This is a computer generated result) | NATHAN | NATHAN | | B= | C | 6321390 |
ELDER CONSTRUCTION, INC. | B= | P | 08/07/2019 | penetrations, hardware and frame and final mall okay. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), PEAK HEATING & AIR COND, INC. Mechanical Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 6291889 |
ELDER CONSTRUCTION, INC. | BFR | P | 07/16/2019 | hard lid framing okay / elevator lobby sealed for smoke | NATHAN | NATHAN | | BFR | P | 6264806 |
ELDER CONSTRUCTION, INC. | BFR | P | 05/08/2019 | complete all required inspections, Reviewed Accessible Elements / will need inspection of any floor penetrations and elevator lobby walls before ceilings installed. | NATHAN | NATHAN | | BFR | P | 6192381 |
EL PASO ELECTRIC, LLC. | E= | C | 07/25/2019 | | BRIAN | BRIAN | | E= | C | 6276469 |
EL PASO ELECTRIC, LLC. | ER | P | 07/16/2019 | grid: spliced area/north of elevator hallway and elevator lobby, | JOHNN | JOHNN | | ER | P | 6265257 |
EL PASO ELECTRIC, LLC. | ER | C | 07/03/2019 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | ER | C | 6252618 |
EL PASO ELECTRIC, LLC. | E= | C | 07/03/2019 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 6252619 |
EL PASO ELECTRIC, LLC. | ER | C | 07/03/2019 | rest of the ceilings inside the suit only / common area is under separate permit / | BRIAN | BRIAN | | ER | C | 6252617 |
EL PASO ELECTRIC, LLC. | ER | R | 06/27/2019 | FIRE ALARM INSPECTION: need support wires on the fire alarm boxes / | BRIAN | BRIAN | | ER | R | 6246104 |
EL PASO ELECTRIC, LLC. | ER | P | 06/27/2019 | partial ceiling- - see plans / 1 j box missing cover and 1 light box not made up / | BRIAN | BRIAN | | ER | P | 6246093 |
EL PASO ELECTRIC, LLC. | ER | P | 05/14/2019 | rest ow walls with switches --ok | BRIAN | BRIAN | | ER | P | 6198022 |
EL PASO ELECTRIC, LLC. | ER | P | 05/13/2019 | walls -- except for the switches need plenum rated low volt wiring with 300 volt rating | BRIAN | BRIAN | | ER | P | 6196587 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 09/03/2019 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 6321389 |
FRONTIER MECHANICAL SYSTEMS INC | H= | C | 07/30/2019 | WATER PIPE TO VAV COMPLETE AND CONDENSATES COMPLETE | BENH | BENH | | H= | C | 6281598 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | C | 07/22/2019 | ABOVE CEILING FLEX AND DIFFUSER OK, MECHANICAL FINAL OK PENDING TAB REPORT | BENH | BENH | | HD | C | 6271360 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 07/16/2019 | NOT READY NEED TO ADDRESS ITEMS FROM PREVIOUS INSPECTION AND TILE LEFT OUT IN ROOM 107 | BENH | BENH | | HD | P | 6264514 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 07/01/2019 | STILL NEED TO ADRESS ITEMS IN OFFICE 107, 109 AND 101 FROM PREVIOUS INSPECTION, SEAL MEDIUM PRESSURE DUCT IN OFFICE 124, MISSING SUPPLY DIFFUSER IN 120 BY NORTHWEST WINDOW, IN OPEN OFFICE 128 MISSING SUPPLY AIR AND RETURN AIR FLEX AND DIFFUSERS, MISSING RETURN GRILLE OUTSIDE OFFICE 126 IN CORRIDOR, ALL TRUNK LINES AND LATERALS ABOVE CEILING OK NORTH OF OFFICE 120 | BENH | BENH | | HD | P | 6249514 |
FRONTIER MECHANICAL SYSTEMS INC | H= | P | 07/01/2019 | INSULATE AND LABEL HOT WATER PIPE TO NEW VAV IN OFFICE 129 | BENH | BENH | | H= | P | 6249492 |
FRONTIER MECHANICAL SYSTEMS INC | HWP | P | 06/25/2019 | STILL NEED TO SEE CONDENSATE TERMINATION, NEED PROPER SLOPE FOR CONDENSATE IN CORRIDOR NEXT TO MENS BATHROOM, NEED TO SEE HYDRONIC PIPING CONNECTION TO NEW VAV, WATER PIPING SUPPLY/ RETURN TO HEAT PUMP OK TO INSULATE AND LABEL | BENH | BENH | | HWP | P | 6242899 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 06/25/2019 | SEAL MEDIUM PRESSURE DUCT IN ROOM 107, FYI: CONFERENCE ROOM 109 MISSING RETURN GRILLE, MISSING RETURN GRILLE IN RECEPTION 101, ABOVE CEILING OK STILL NEED TO SEE EVERYTHING NORTH OF OFFICE 120 | BENH | BENH | | H= | P | 6242884 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 06/06/2019 | NEED SOMEONE TO CLAIM ALL NEW HWP PIPING AND CALL INSPECTION WHEN READY - NEED THE FOLLOWING TO COMPLETE HD INSPECTION - CAP OPEN HOLES AT VAV DUCTS IN THE FOLLOWING ROOMS SERVER 103 / 122 - QUESTION VAV ACCESS AT SERVER ROOM 103 - COMPLETE ALL MEDIUM PRESSURE DUCT TIE INS - SEAL LOW PRESSURE DUCT AT VAV 1 OK TO SHOW INSPECTOR PICTURES TO VERIFY NOTES: THIS INSPECTION WAS FOR THE FOLLOWING ALL LOW PRESSURE SA MAINS / RUN OUTS AND BOXES ALL OK | JERRYF | JERRYF | | HD | P | 6222581 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 07/31/2019 | correction made | JOSEPHD | JOSEPHD | | P= | C | 6282859 |
FRONTIER MECHANICAL SYSTEMS INC | P= | P | 07/30/2019 | no hot water, need to see vent connection in ceiling | JOSEPHD | JOSEPHD | | P= | P | 6281316 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | C | 05/14/2019 | note: check water heater at final, check connection at vent at final | JOSEPHD | JOSEPHD | | PTO | C | 6198051 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | L | 05/13/2019 | field canceled | JOSEPHD | JOSEPHD | | PTO | L | 6196421 |
EL PASO ELECTRIC, LLC. | XES | P | 07/15/2019 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised lighting. | BERTHA | BERTHA | | XES | P | 6263143 |
ELDER CONSTRUCTION, INC. | XBS | P | 07/11/2019 | PLAN SPLICE: (No Fee) by: DANM for Construction: Add hallway ceiling and flooring to scope of work | DANM | DANM | | XBS | P | 6260854 |
PEAK HEATING & AIR CONDITIONING, INC. | XMS | T | 07/11/2019 | PAID (REC#1614004) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: new splice added supplys for corridors | TCRIPPEN | TCRIPPEN | | XMS | T | 6260767 |