GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 05/27/2020 | | DAKOTAB | DAKOTAB | | B= | C | 6583588 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BE | L | 05/26/2020 | Renewed for No Fee at 5/26/2020 11:30:40 AM | MATTHEWM | MATTHEWM | | BE | L | 6582543 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 11/22/2019 | Building final OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 6408616 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 11/12/2019 | Items from previous inspection corrected -- Above lid OK at employee breakroom | DAKOTAB | DAKOTAB | | BSP | P | 6396211 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 10/30/2019 | ABOVE LID -- Need to firecaulk blue conduit penetrations at both ends of fire barrier in employee break room -- Above lid penetrations at corridor, mens and womens locker room, and mens and womens bathrooms OK | DAKOTAB | DAKOTAB | | BSP | P | 6383665 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/19/2019 | hard lid framing in front of break room/male locker room/front of break room/female locker room per plan -- hard framings in both bathrooms/front of break room/ corridor 1580 per plan -- penetrations and head of wall above hard lids complete -- gypsum fastening per U419 and gypsum is per listing at break room walls | SCOTTS | SCOTTS | | BFR | P | 6341321 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/10/2019 | wall framing for locker/bathrooms/and corridor per plan and listing U419 | SCOTTS | SCOTTS | | BFR | P | 6330653 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 08/20/2019 | ADDITIONAL PLAN REVIEW TIME: (No Fee) From: MICHAELA Revise wall types | MICHAELA | MICHAELA | | BSP | P | 6306893 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/14/2019 | wall framing for break room and locker rooms is per plan -- Reviewed Accessible Elements / | SCOTTS | SCOTTS | | BFR | P | 6300777 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/02/2019 | corridor wall framing is per UL U419 and plan -- will review accessibility at wall framing for locker rooms/break room | SCOTTS | SCOTTS | | BFR | P | 6287304 |
ENCORE ELECTRIC, INC. | E= | C | 05/04/2020 | FIRE ALARM INSPECTION: | RANDY | RANDY | | E= | C | 6560424 |
ENCORE ELECTRIC, INC. | ER | P | 12/02/2019 | FIRE ALARM INSPECTION: wrong permit called in | RANDY | RANDY | | ER | P | 6413562 |
ENCORE ELECTRIC, INC. | ER | P | 12/02/2019 | wrong permit called in | RANDY | RANDY | | ER | P | 6413561 |
ENCORE ELECTRIC, INC. | ER | P | 11/22/2019 | no rough | RANDY | RANDY | | ER | P | 6409122 |
ENCORE ELECTRIC, INC. | E= | C | 11/22/2019 | | RANDY | RANDY | | E= | C | 6408746 |
ENCORE ELECTRIC, INC. | ER | P | 11/07/2019 | hunter douglas ceiling marked on plans | RANDY | RANDY | | ER | P | 6392150 |
ENCORE ELECTRIC, INC. | ER | P | 11/07/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6392135 |
ENCORE ELECTRIC, INC. | ER | P | 10/30/2019 | FA with electric | RANDY | RANDY | | ER | P | 6383787 |
ENCORE ELECTRIC, INC. | ER | P | 10/30/2019 | staff locker ceilings | RANDY | RANDY | | ER | P | 6383785 |
ENCORE ELECTRIC, INC. | ER | P | 10/25/2019 | staff locker casework | RANDY | RANDY | | ER | P | 6381305 |
ENCORE ELECTRIC, INC. | ER | P | 09/26/2019 | walls, 1701.1702,1703 1739,1740,1750 stubs to ceiling, side and door walls only | BRET | BRET | | ER | P | 6348600 |
ENCORE ELECTRIC, INC. | ER | P | 09/26/2019 | FIRE ALARM INSPECTION: walls 1701,1702,1703 1739,1740 ,1750 all stubs to ceiling side walls and door walls only | BRET | BRET | | ER | P | 6348595 |
ENCORE ELECTRIC, INC. | ER | P | 09/12/2019 | staff lockers walls and hard lids----marked on plans | RANDY | RANDY | | ER | P | 6333586 |
ENCORE ELECTRIC, INC. | ER | P | 08/23/2019 | staff locker rooms 1st fl walls marked on plans | RANDY | RANDY | | ER | P | 6312253 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | C | 03/25/2020 | ENGINEER STAMPED TEST AND BALANCE REPORT RECEIVED ( SEE IMAGES ) | LIDO | LIDO | | H= | C | 6520620 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 03/25/2020 | TEST AND BALANCE REPORT PROVIDED TO THE INSPECTOR BY THE CONTRACTOR IS THE SAME REPORT THAT WAS PROVIDED ON 12/17/19 THAT WAS NOT APPROVED / CONTRACTOR WILL NEED TO REVIEW NOTES FROM 12/17/19, AND REVIEW TEST AND BALANCE REPORT AT ITS ENTIRETY PRIOR TO ATTACHING TO AN INSPECTION REQUEST. A REVISED TEST AND BALANCE REPORT OR A STAMPED ENGINEER LETTER APPROVING THE READINGS IS REQUIRED . ( MULTIPLE GEF-2 READINGS ARE ALSO OUTSIDE THE 10% +/- ALLOWED) | LIDO | LIDO | | H= | P | 6520424 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 03/24/2020 | HYDRONIC ( HEAT WATER ) HEAT FINAL OK | LIDO | LIDO | | H= | C | 6519009 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 12/17/2019 | PARTIAL PENDING : TEST AND BALANCE REPORT REVIEW : ALL RETURN AIR READING ARE OUTSIDE THE 10% +/- ALLOWED. VAV 1-255 IS NOT THE VAV FOR ROOM # 1801 AND 1802 / SUPPLY GRILL #1,#2 / THE VAV FOR THE TWO GRILLS LISTED IS VAV-1-258. PROVIDE REVISED TEST AND BALANCE REPORT OR STAMPED ENGINEER LETTER APPROVING THE READINGS. | LIDO | LIDO | | H= | P | 6430355 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 12/17/2019 | RECEIVED TEST AND BALANCE REPORT IS BEING REVIEWED. | LIDO | LIDO | | H= | P | 6429180 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 11/06/2019 | PARTIAL PENDING : TEST AND BALANCE REPORT. | LIDO | LIDO | | H= | P | 6390274 |
OLSON PLUMBING & HEATING COMPANY | HD | C | 10/21/2019 | changed to complete 10/21/19 (LM). 1ST FLOOR MH-111 ( BDA 39) ALL SUPPLY , RETURN AND EXHAUST GRILLS AND REGISTERS COMPLETE. | LIDO | LIDO | | HD | C | 6375645 |
OLSON PLUMBING & HEATING COMPANY | HD | C | 10/16/2019 | 1ST FLOOR MH-111 ( BDA 39 ) ABOVE CEILING FINAL IN ROOMS 1803, 1804, 1805,1806, 1807 OK. | LIDO | LIDO | | HD | C | 6370580 |
OLSON PLUMBING & HEATING COMPANY | HWP | C | 10/09/2019 | 1ST FLOOR : ALL HEAT WATER PIPING,VAV FINAL CONNECTIONS, INSULATION AND LABELS COMPLETE. | LIDO | LIDO | | HWP | C | 6363166 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 10/02/2019 | 1ST FLOOR MH-111 ( SPLICE BDA 36) ALL ABOVE CEILING DUCT ROUGH OK / OK TO WRAP. | LIDO | LIDO | | HD | P | 6355918 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 09/11/2019 | 1ST FLOOR MH-111 ( BDA 15 & SPLICE BDA 38) 3- FIRE/ SMOKE DAMPERS COMPLETE. | LIDO | LIDO | | HD | P | 6331789 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 09/06/2019 | FIRE / SMOKE DAMPERS REMOVED FROM THE NORTH SIDE OF CORRIDOR PER SPLICE DATED 8/20/19 PLAN PAGE MH-111 ( BDA 48.) 1ST FLOOR MH-111 ( BDA15) ABOVE CEILING MEDIUM PRESSURE AND LOW PRESSURE DUCT ROUGH OK / OK TO WRAP. | LIDO | LIDO | | HD | P | 6326597 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 08/23/2019 | 1ST FLOOR (BDA 15) MH-111 - SUPPLY, RETURN AND EXHAUST ABOVE CEILING DUCT ROUGH FOR ROOM # 1806, 1803, 1849 AND CORRIDOR OK / OK TO INSULATE. | LIDO | LIDO | | HD | P | 6312909 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 08/23/2019 | 1ST FLOOR ( BDA 16) MP-111 : HEAT WATER SUPPLY AND RETURN FOR VAV-1-258, 259, 256, 255, 254 UNDER OPERATING PRESSURE OK / NO VISIBLE LEAKS / INSTALLED PER PLAN / OK TO INSULATE AND LABEL.NEED FINAL TIE-IN TO VAV'S. | LIDO | LIDO | | HWP | P | 6312889 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 08/08/2019 | 1ST FLOOR ( BDA15) MH-111 : THREE DAMPER FRAMES OK. | LIDO | LIDO | | HD | P | 6293610 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 11/15/2019 | locker rooms, break room, drinking fountain | TED | TED | | P= | C | 6401044 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 09/03/2019 | over head water mains in hallway for locker rooms and break room | TED | TED | | PTO | P | 6322213 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 08/27/2019 | 1st floor woman,s locker room and break room water and dwv in walls and ceiling ok | TED | TED | | PTO | P | 6315557 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 08/21/2019 | 1st floor men's locker room and hall drinking fountain, dwv and water in walls and ceilings ok | TED | TED | | PTO | P | 6309200 |
ENCORE ELECTRIC, INC. | XES | P | 09/16/2019 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: Intercom changes | SHELBY | SHELBY | | XES | P | 6335809 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 09/13/2019 | PAID (REC#1630768) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised location of VAV 1-256 and associated duct and damper | JUSTINC | JUSTINC | | XMS | T | 6335339 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 08/20/2019 | PAID (REC#1623616) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds only | DALEH | DALEH | | XMS | T | 6306827 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XES | P | 08/20/2019 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised lighting for background change. | BERTHA | BERTHA | | XES | P | 6306677 |
OLSON PLUMBING & HEATING COMPANY | XPS | P | 08/20/2019 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Plumbing splice 8/20/19: Delta ASI-07 revised piping | SHANEN | SHANEN | | XPS | P | 6306661 |