GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 05/26/2020 | | DAKOTAB | DAKOTAB | | B= | C | 6582516 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 12/20/2019 | Building final OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, U.S.ENGINEERING CONSTRUCTION, LLC Mechanical Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 6433859 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 12/20/2019 | Items from previous inspection corrected | DAKOTAB | DAKOTAB | | BFR | P | 6433853 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 12/02/2019 | ABOVE LID -- Pack of 4 electrical conduits not firecaulked at corridor 1701 -- Rest of above lid at corridor and observation rooms OK | DAKOTAB | DAKOTAB | | BFR | P | 6412648 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 11/05/2019 | Remainder of light gauge framing at corridor 1701 up to door way OK, this completes light gauge framing inspections on this permit -- Above lid at staff station 1705 OK | DAKOTAB | DAKOTAB | | BFR | P | 6388862 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 10/25/2019 | Above lid framing and head of wall detail above door at corridor 1701 OK -- Reviewed upcoming framing inspections at this area | DAKOTAB | DAKOTAB | | BFR | P | 6381137 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 09/25/2019 | soffit framing/remainder of wall framing is complete and per plan | SCOTTS | SCOTTS | | BFR | P | 6347755 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/30/2019 | wall framing for observation rooms 1740 and 1750 thru 1756 framed per plan | SCOTTS | SCOTTS | | BFR | P | 6320942 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/23/2019 | field cancelled by Dale w/ SpaceCon/not ready | SCOTTS | SCOTTS | | BFR | P | 6312873 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/22/2019 | partial frame inspection for observation rooms 1741-1744/soiled work/clean supplies -- frame is per plan and listings | SCOTTS | SCOTTS | | BFR | P | 6311355 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 08/20/2019 | ADDITIONAL PLAN REVIEW TIME: (No Fee) From: MICHAELA Revise wall types | MICHAELA | MICHAELA | | BSP | P | 6306890 |
ENCORE ELECTRIC, INC. | ER | C | 03/27/2020 | FIRE ALARM INSPECTION: | RANDY | RANDY | | ER | C | 6523385 |
ENCORE ELECTRIC, INC. | E= | C | 03/27/2020 | FIRE ALARM INSPECTION: | RANDY | RANDY | | E= | C | 6523384 |
ENCORE ELECTRIC, INC. | E= | C | 12/19/2019 | | RANDY | RANDY | | E= | C | 6432826 |
ENCORE ELECTRIC, INC. | ER | P | 12/03/2019 | FIRE ALARM INSPECTION: FA with electric | RANDY | RANDY | | ER | P | 6414612 |
ENCORE ELECTRIC, INC. | ER | P | 12/03/2019 | observation rooms ceilings marked on plans | RANDY | RANDY | | ER | P | 6414605 |
ENCORE ELECTRIC, INC. | ER | P | 11/11/2019 | walls and ceiling in observation marked on plans | RANDY | RANDY | | ER | P | 6395391 |
ENCORE ELECTRIC, INC. | ER | P | 11/05/2019 | corridor marked on the plans OK | CRAIGS | CRAIGS | | ER | P | 6388318 |
ENCORE ELECTRIC, INC. | ER | P | 09/04/2019 | observation area walls and 2 equipment rm drop ceilings all marked on plans | RANDY | RANDY | | ER | P | 6324261 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | C | 03/25/2020 | ENGINEER STAMPED TEST AND BALANCE REPORT RECEIVED ( SEE IMAGES ) | LIDO | LIDO | | H= | C | 6520627 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 03/24/2020 | HYDRONIC ( HEAT WATER ) / HEAT FINAL OK | LIDO | LIDO | | H= | C | 6519049 |
U.S. ENGINEERING CONSTRUCTION, LLC | H= | P | 12/03/2019 | PARTIAL PENDING : NEED TEST AND BALANCE REPORT. | LIDO | LIDO | | H= | P | 6414646 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | C | 11/13/2019 | 1ST FLOOR ALL SUPPLY, RETURN, EXHAUST GRILLS AND REGISTERS OK / STILL NEED FINAL WALK. NEED TEST AND BALANCE REPORT. | LIDO | LIDO | | HD | C | 6398442 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/11/2019 | 1ST FLOOR MH110 ( BDA 66) SUPPLY, RETURN, EXHAUST GRILLS AND REGISTERS OK / STILL NEED GRILL DOWN CORRIDOR. | LIDO | LIDO | | HD | P | 6395296 |
U.S. ENGINEERING CONSTRUCTION, LLC | HD | P | 11/06/2019 | 1st FLOOR MH-110 ( BDA 66) 5- ADDED SMOKE DAMPERS INSTALLED PER SPLICE OK . SUPPLY, RETURN, EXHAUST GRILLS AND REGISTERS INSTALLED IN ROOM SOUTH OF CORRIDOR OK. | LIDO | LIDO | | HD | P | 6390270 |
OLSON PLUMBING & HEATING COMPANY | HSP | P | 10/09/2019 | 1ST FLOOR REVISED AND APPROVED PLANS FOR HEAT WATER SUPPLY AND RETURN HYDRONIC PIPING FOR VAV'S IS COMPLETED. SEE ( BDA 83) | LIDO | LIDO | | HSP | P | 6363948 |
OLSON PLUMBING & HEATING COMPANY | HWP | C | 10/09/2019 | ALL HEAT WATER PIPING AND VAV FINAL CONNECTIONS COMPLETE. | LIDO | LIDO | | HWP | C | 6363167 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 10/02/2019 | 1ST FLOOR . SPLICE MH110 ( BDA 66) : 3 - DAMPERS COMPLETE. ALL ABOVE CEILING SUPPLY, RETURN AND EXHAUST DUCT ROUGH OK / OK TO WRAP. | LIDO | LIDO | | HD | P | 6355919 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 09/17/2019 | 1ST FLOOR . MH110 ( BDA 66) 1- FIRE DAMPER COMPLETE. VAV1-264 MEDIUM PRESSURE DUCT ROUGH OK/ OK TO WRAP. VAV 1-262 AND 263 LOW PRESSURE DUCT ROUGH OK / OK TO WRAP. | LIDO | LIDO | | HD | P | 6338181 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 09/11/2019 | 1ST MH-110 ( BDA 66) LOW PRESSURE ONLY FOR VAV-1-264 AND VAV 1-265 OK / OK TO WRAP / STILL NEED VAV'S . 4- FIRE DAMPERS COMPLETE. RETURN AND EXHAUST AIR DUCT ROUGH OK / OK TO WRAP. | LIDO | LIDO | | HD | P | 6331801 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 09/10/2019 | 1ST FLOOR : NEED REVISED AND APPROVED PLANS FOR HEAT WATER SUPPLY AND RETURN TO MATCH INSTALL FOR THE LISTED VAV'S. HEAT WATER SUPPLY AND RETURN UNDER OPERATING PRESSURE OK / NO VISIBLE LEAKS FOR VAV # 1-259, 260, 261, 263, 264, 265 / OK TO INSULATE AND LABEL. NEED TO SEE FINAL CONNECTION TO VAV'S. (( NEED TO HIGHLIGHT PLANS AT NEXT INSPECTION. )) | LIDO | LIDO | | HWP | P | 6330489 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 09/05/2019 | 1ST FLOOR MH-110 ( BDA 66) 4- DAMPER FRAMES OK. | LIDO | LIDO | | HD | P | 6325544 |
OLSON PLUMBING & HEATING COMPANY | HD | P | 08/26/2019 | 1ST FLOOR ( BDA 66) MH-110 : 4 - DAMPER FRAMES OK. | LIDO | LIDO | | HD | P | 6314187 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 12/19/2019 | Corrections made. | SAMH | SAMH | | P= | C | 6433115 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 12/18/2019 | Sink height exceeds 34" at restroom 7502. Need 5" side clearance at lav, Trap guard in floor drain, and Non positive shower wand at Restroom 7501. Rest OK. | SAMH | SAMH | | P= | P | 6430953 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 10/02/2019 | dwv and water in walls and ceiling rooms 1702, 1703, 1740, 1741, 1742, 1743, 1744, 1745 | TED | TED | | PTO | C | 6355165 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 09/23/2019 | dwv and water in walls and ceilings, rooms 1705, 1750, 1751, 1752, 1753, 1754, 1755, 1756, over head water main lines ok , | TED | TED | | PTO | P | 6344441 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 09/11/2019 | 1st floor base piping in garage ceiling | TED | TED | | PB | C | 6331491 |
OLSON PLUMBING & HEATING COMPANY | PB | P | 09/10/2019 | dwv in garage ceiling for rooms 1739, 1740, 1750, 1751, 1756, men's and woman's locker room area | TED | TED | | PB | P | 6330093 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 09/10/2019 | in walls and ceiling dwv and water room 1745 for sink only | TED | TED | | PTO | P | 6330061 |
OLSON PLUMBING & HEATING COMPANY | PB | P | 09/03/2019 | 6'' relocation in garage ceiling, 1st floor rooms 1744, 1745, 1754, 1755, through floor into garage ceiling | TED | TED | | PB | P | 6322255 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 08/28/2019 | 1st floor observation relocating 6 inch main, ceiling / walls ok | TED | TED | | PTO | P | 6317226 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 09/30/2019 | PAID (REC#1634101) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revision is for replacing fsd to smoke dampers | JUSTINC | JUSTINC | | XMS | T | 6352340 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 09/17/2019 | PAID (REC#1630770) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds only | DALEH | DALEH | | XMS | T | 6337643 |
ENCORE ELECTRIC, INC. | XES | T | 09/17/2019 | PAID (REC#1634394) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Relocated switches. | BERTHA | BERTHA | | XES | T | 6337396 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | P | 09/16/2019 | PLAN SPLICE: (No Fee) by: DANM for Construction: Minor door and interior elevation revisions | DANM | DANM | | XBS | P | 6336238 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 08/20/2019 | PAID (REC#1623619) PLAN SPLICE FEE: $50 by: DALEH for Mechanical: clouds only | DALEH | DALEH | | XMS | T | 6306871 |
OLSON PLUMBING & HEATING COMPANY | XPS | P | 08/20/2019 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Plumbing splice 8/20/19: Delta ASI-08 revisions added L-6 to fixture schedule | SHANEN | SHANEN | | XPS | P | 6306667 |