CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | C | 10/02/2020 | All other required Final inspections are complete. (This is a computer generated result) | BOBF | BOBF | | B= | C | 6728005 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | B= | P | 06/29/2020 | pending completion of other required inspections, building okay. Additional Inspections Required (computer generated): THYSSENKRUPP ELEVATOR CORP. Mechanical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6621310 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFR | P | 05/05/2020 | framing under escalator 4 okay | BOBF | BOBF | | BFR | P | 6561041 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BE | P | 04/10/2020 | | MATTHEWM | MATTHEWM | | BE | P | 6537538 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BSP | P | 11/08/2019 | screw inspection not required at non rated walls | BOBF | BOBF | | BSP | P | 6393412 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFR | P | 11/08/2019 | pending other required inspections, framing each side of east escalator okay | BOBF | BOBF | | BFR | P | 6393409 |
CONSTRUCTION CONSULTING SOLUTIONS, INC. | BFR | P | 11/04/2019 | light metal framing for escalator 5 okay | BOBF | BOBF | | BFR | P | 6386901 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | C | 05/22/2020 | | CRAIG | CRAIG | | E= | C | 6581214 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | P | 05/13/2020 | waiting for lights / switch / plug under escalator 4 | CRAIG | CRAIG | | E= | P | 6569912 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | C | 05/13/2020 | 480v and 120v to top of escalator pit for escalator1, 2 and 4 ok | CRAIG | CRAIG | | ER | C | 6569910 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 05/04/2020 | need to coordinate with elevator inspector on final for escalators 1, 2, and 4 | CRAIG | CRAIG | | ER | P | 6559667 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | EE | L | 05/01/2020 | Renewed for No Fee at 5/1/2020 11:32:55 AM | DEAN | DEAN | | EE | L | 6558247 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 10/31/2019 | 480 v and 120 v to top of escalator pit for escalator 3 and 5 ok | CRAIG | CRAIG | | ER | P | 6384801 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 10/31/2019 | above ceiling under escalator 5 only ok note verify 3 access panels on final | CRAIG | CRAIG | | ER | P | 6384794 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 10/25/2019 | wall rough under escalator for 3 gang switch and lights and single switch and plug only ok | CRAIG | CRAIG | | ER | P | 6380345 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | C | 10/02/2020 | ALL FIVE ESCALATORS COMPLETE AND REGISTERED WITH THE STATE OF COLORADO | ROBERTV | ROBERTV | | HE= | C | 6728003 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 05/13/2020 | NEED CODE DATA STICKERS AFFIXED TO TOP OF CONTROLLER ON ESCALATORS #1,2,3,5. NEED TO INSTALL PERMANENT GLASS DECK BARRICADES AT TOP AND BOTTOM ENDS OF #4. NEED TO APPLY PERMANENT IDENTIFICATION FOR STARTING SWITCHES ON ALL ESCALATORS TO REFLECT "DOWN" - "RUN" - "UP", PRESENT MEANS STILL LIST PREVIOUS DIRECTIONS. NEED CONVEYANCE REGISTRATION PAPERWORK WITH NEW JOB/CONTRACT/SERIAL NUMBERS AND ESCALATOR SPECIFICATIONS SENT TO STATE OF COLORADO. (CANNOT CLOSE PERMIT UNTIL EITHER EXISTING REGISTRATION NUMBERS ARE ADEQUATE OR IF NEW REGISTRATIONS NUMBERS ARE TO BE ISSUED - CONTACT STATE OF COLORADO CONVEYANCE DEPARTMENT) | ROBERTV | ROBERTV | | HE= | P | 6570824 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 04/08/2020 | (ESCALATOR #1 AND #2) - NEED CODE DATA TAGS ATTACHED TO THE CONTROLLERS. NEED PERMANENT BARRICADE GLASS INSTALLATION COMPLETED BETWEEN UNITS. NEED REGISTRATION FOR BOTH UNITS UPDATED OR RE-REGISTERED WITH THE STATE OF COLORADO OPS. .............. OK FOR PUBLIC USE (SEE IMAGES FOR ACCEPTANCE TEST FORMS) | ROBERTV | ROBERTV | | HE= | P | 6534467 |
THYSSENKRUPP ELEVATOR CORPORATION | HE= | P | 11/18/2019 | (ESCALATOR #3 AND #5) - NEED UPDATED OR NEW REGISTRATION WITH COLORADO OPS. ESCALATORS #3 AND #5 OK FOR PUBLIC USE. (SEE IMAGES FOR ACCEPTANCE TEST FORMS) | ROBERTV | ROBERTV | | HE= | P | 6402139 |