GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 04/20/2020 | All other required Final inspections are complete. (This is a computer generated result) | CHUCK | CHUCK | | B= | C | 6545536 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 03/12/2020 | Building final OK for Rooms AG300 and AG303 pending completion of electrical and mechanical final inspections. Additional Inspections Required (computer generated): ENCORE ELECTRIC, INC. Electrical Final Inspection is not Completed yet, MECH ONE, INC. Mechanical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Plumbing Final Inspection is not Completed yet. | CHUCK | CHUCK | | B= | P | 6508654 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 02/21/2020 | above dropped lid penetrations ok | SCOTTS | SCOTTS | | BSP | P | 6488708 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 02/11/2020 | Light gauge metal stud framing for MF3U walls OK / Need to inspect fire stopping at penetrations and head of wall. | CHUCK | CHUCK | | BFR | P | 6478857 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 01/23/2020 | observed light gauge wall framing / need to attach electrical to permit and complete other rough inspections / reviewed details for 1hr fire barrier assembly UL U419 with site foreman Felix / also discussed needing fire stop details for all through penetrations at fire barrier and needing letter - details for maintaining gyp continuity where insulated pipes are installed parallel with the wall and will interrupt gyp continuity for fire barrier | BRIANB | BRIANB | | BFR | P | 6461976 |
ENCORE ELECTRIC, INC. | E= | C | 03/12/2020 | | RANDY | RANDY | | E= | C | 6509046 |
ENCORE ELECTRIC, INC. | ER | P | 02/13/2020 | scope processing ceilings ok | RANDY | RANDY | | ER | P | 6481676 |
ENCORE ELECTRIC, INC. | E= | P | 01/29/2020 | scope processing and storage walls ok | RANDY | RANDY | | E= | P | 6468038 |
MECHONE, INC. | H= | C | 04/20/2020 | MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6545535 |
MECHONE, INC. | H= | P | 04/20/2020 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. STILL NEED TO SEE EXHAUST DUCT FROM FIRE DAMPER TO TIE IN AT CORRIDOR. FLEX AND DIFFUSERS IN AG301. STILL NEED TO SEE FIRE DAMPER ACCESS DOORS AND LABELS INSTALLED. | DUSTINS | DUSTINS | | H= | P | 6544729 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 03/13/2020 | PIPING FINAL OK. INSULATION AND LABELS INSTALLED, SEE IMAGES. | NANCY | NANCY | | H= | C | 6510302 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 03/13/2020 | IMAGE OF MANUAL AIR VENT INSTALLED, SEE IMAGES. STILL NEED TO SEE INSULATION AND LABELING | DUSTINS | DUSTINS | | H= | P | 6509866 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 03/12/2020 | NEED MANUAL AIR VENT PER PLAN. SYSTEM OPERATING AT OPERATION PRESSURE, NO VISIBLE LEAKS. OK TO INSULATE AND LABEL. | DUSTINS | DUSTINS | | H= | P | 6509000 |
MECHONE, INC. | HD | P | 02/20/2020 | MECHANICAL FINAL OK IN ROOMS AG 300 AND AG 303 ONLY. | DUSTINS | DUSTINS | | HD | P | 6487532 |
MECHONE, INC. | HD | P | 02/11/2020 | ABOVE CEILING SUPPLY/RETURN/EXHAUST DUCTS OK, OK TO WRAP. STILL NEED TO SEE EXHAUST DUCT FROM FIRE DAMPER TO TIE IN AT CORRIDOR. NO FLEX AND DIFFUSERS YET. STILL NEED TO SEE FIRE DAMPER ACCESS DOORS AND LABELS INSTALLED. | DUSTINS | DUSTINS | | HD | P | 6479023 |
MECHONE, INC. | HD | P | 02/05/2020 | ALL FOUR FIRE DAMPERS RETAINING ANGLES OK. STILL NEED TO SEE ACCESS DOORS AND LABELS. | DUSTINS | DUSTINS | | HD | P | 6474504 |
MECHONE, INC. | HD | P | 01/30/2020 | FOUR FIRE DAMPER FRAMING OK. EXHAUST DAMPER IS MOVING TO CORNER OF WALL? 22X10 RETURN AIR DAMPER STILL NEEDS RETAINING ANGLES INSTALLED PER INSTALLATION INSTRUCTIONS. MISSING SCREWS TO WALL, NO MORE THAN 12" SPACING. SUPPLY DAMPER RETAINING ANGLES OK, NEED TO SEE ACCESS DOOR AND LABEL. STILL NEED TO SEE DAMPER AND RETAINING ANGLES ON EXHAUST AND TB143. | DUSTINS | DUSTINS | | HD | P | 6469996 |
MECHONE, INC. | HD | P | 01/27/2020 | INSTALL FIRE DAMPER RETAINING ANGLES PER INSTALLATION INSTRUCTIONS, SCREW SPACING TO BE NO MORE THAN 12" AT WALL AND 6" AT DAMPER. FIRE DAMPER FRAMING NEEDS TO HAVE FULL LENGTH STUDS FROM BOTTOM TO TOP TRACK. DISCUSSED NEED FOR VERIFYING FULL LENGTH STUDS AT NEW FIRE DAMPER FOR TB 143 AND TO VERIFY DUCT PENETRATION IS COMPLETED PER NOTE 9 WITH FIRE CAULKING. | DUSTINS | DUSTINS | | HD | P | 6464501 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 03/13/2020 | | TAYLOR | TAYLOR | | P= | C | 6509991 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 03/12/2020 | need proper drainage fittings for wall box, complete sink at decontam room and still need to revise plans as previously noted, rest ok. | TAYLOR | TAYLOR | | P= | P | 6508562 |
OLSON PLUMBING & HEATING COMPANY | PTO | C | 01/24/2020 | check backflow at final. | TAYLOR | TAYLOR | | PTO | C | 6462965 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 01/16/2020 | revise plans for existing 3 inch drain tie in by final. | TAYLOR | TAYLOR | | PB | C | 6454746 |
OLSON PLUMBING & HEATING COMPANY | PB | P | 01/15/2020 | complete tie in, rest ok. | TAYLOR | TAYLOR | | PB | P | 6453808 |
OLSON PLUMBING & HEATING COMPANY | XPS | P | 03/13/2020 | PLAN SPLICE: (No Fee) by: DALEH for Plumbing: delta 4 revised sheet note | DALEH | DALEH | | XPS | P | 6509959 |
ENCORE ELECTRIC, INC. | XES | P | 03/05/2020 | PLAN SPLICE: (No Fee) by: SHELBY for Electrical: As builts | SHELBY | SHELBY | | XES | P | 6501904 |
OLSON PLUMBING & HEATING COMPANY | XPS | T | 03/05/2020 | PAID (REC#1666529) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: 3/5/20: Delta 3 revisions: P000 adjusted fixture schedule, P100 revised basement DWV and domestic plumbing plan. | SHANEN | SHANEN | | XPS | T | 6501818 |
ENCORE ELECTRIC, INC. | XES | T | 03/03/2020 | PAID (REC#1666204) PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Removed new panel and transformer from scope. | BERTHA | BERTHA | | XES | T | 6498663 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 02/05/2020 | PAID (REC#1661115) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Fire barrier modification | SHELLEY | SHELLEY | | XBS | T | 6474390 |
OLSON PLUMBING & HEATING COMPANY | XPS | T | 01/29/2020 | PAID (REC#1659098) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: 1/29/20: Delta 2 revisions P000 removed medical gas diagrams and details, P100 removed medical gas piping and revised keynotes 9 & 10. | SHANEN | SHANEN | | XPS | T | 6467863 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XBS | T | 12/30/2019 | PAID (REC#1655606) PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Clarify door ratings and hardware | MICHAELA | MICHAELA | | XBS | T | 6439867 |