RAINE BUILDING LLC. | B= | C | 09/11/2020 | All other required Final inspections are complete. (This is a computer generated result) | BOBF | BOBF | | B= | C | 6702580 |
RAINE BUILDING LLC. | B= | P | 09/10/2020 | pending completion of elec final, building okay. Additional Inspections Required (computer generated): PROCOM ELECTRICAL SERVICES, INC. Electrical Final Inspection is not Completed yet. | BOBF | BOBF | | B= | P | 6701115 |
RAINE BUILDING LLC. | B= | P | 03/16/2020 | Knee protection added, image uploaded. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2). | NATHAN | NATHAN | | B= | P | 6511258 |
RAINE BUILDING LLC. | B= | P | 03/10/2020 | missing knee protection under break room sink. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2). | NATHAN | NATHAN | | B= | P | 6505706 |
RAINE BUILDING LLC. | BSP | P | 03/06/2020 | spoke with superintendent about exterior patio door for egress, design professional will need to address patio design and enclosure details for combined egress of 1st floor and exit enclosure Exit Discharge to public way using the same space. | NATHAN | NATHAN | | BSP | P | 6502630 |
RAINE BUILDING LLC. | BSP | P | 01/29/2020 | SFRM observation report on file | NATHAN | NATHAN | | BSP | P | 6467400 |
RAINE BUILDING LLC. | BSP | P | 01/22/2020 | engineering for steel lintel support at new window openings on file | NATHAN | NATHAN | | BSP | P | 6459915 |
RAINE BUILDING LLC. | BFR | P | 01/17/2020 | partial frame at NW exterior wall beam needs protection per 1A building type. | NATHAN | NATHAN | | BFR | P | 6456485 |
RAINE BUILDING LLC. | BSP | P | 01/02/2020 | discussed issues of sink, dishwasher, clear floor space and reach ranges for Coffee Bar area. | NATHAN | NATHAN | | BSP | P | 6441772 |
RAINE BUILDING LLC. | BFR | P | 12/26/2019 | remaining wall framing with completed required inspections okay, HARD LID frame needed | NATHAN | NATHAN | | BFR | P | 6436675 |
RAINE BUILDING LLC. | BFR | P | 12/11/2019 | With attached MEP permits and completed required inspections frame of 122-127, open office framing between 121,120, and screen wall in front of restrooms 118,119, rooms 112-114, Reviewed Accessible Elements / Observation letter for column and beam protection needed by final | NATHAN | NATHAN | | BFR | P | 6423819 |
PROCOM ELECTRICAL SERVICES, INC. | E= | C | 09/11/2020 | | LOGANP | LOGANP | | E= | C | 6702579 |
PROCOM ELECTRICAL SERVICES, INC. | E= | P | 05/26/2020 | corrections made / need the plans to reflect the 32 circuit panels installed instead of 42 circuits ---ok to final after plans shoe 32 circuits / | BRIAN | BRIAN | | E= | P | 6583224 |
PROCOM ELECTRICAL SERVICES, INC. | E= | C | 03/09/2020 | FIRE ALARM INSPECTION: | LOGANP | LOGANP | | E= | C | 6504447 |
PROCOM ELECTRICAL SERVICES, INC. | E= | P | 03/09/2020 | Need to trim out floor box in common area / no power to floor boxes in meeting room / plan splice to show 32 circuit panels not changed / missing 2 panel fillers and permanent panel schedules / need j-box for puck lights in break room / | LOGANP | LOGANP | | E= | P | 6504446 |
PROCOM ELECTRICAL SERVICES, INC. | E= | R | 03/03/2020 | not ready | BRIAN | BRIAN | | E= | R | 6498319 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 03/03/2020 | FIRE ALARM INSPECTION: offices in phase 2 --ok | BRIAN | BRIAN | | ER | P | 6498318 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 03/03/2020 | rest of the drop ceilings in phase 2 --ok / | BRIAN | BRIAN | | ER | P | 6498314 |
PROCOM ELECTRICAL SERVICES, INC. | E= | P | 02/28/2020 | PHASE 1 ----except the bathroom group , need handle ties for mod furniture , test gfci on the keg cooler / rest in phase 1 is ok / | BRIAN | BRIAN | | E= | P | 6495937 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 02/28/2020 | FIRE ALARM INSPECTION: lobby | BRIAN | BRIAN | | ER | P | 6495922 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 02/28/2020 | lobby---ok see plans | BRIAN | BRIAN | | ER | P | 6495919 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 02/14/2020 | entry siffit / hard lid--ok | BRIAN | BRIAN | | ER | P | 6482709 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 02/06/2020 | walls in phase 2--ok / see plans / | BRIAN | BRIAN | | ER | P | 6475542 |
PROCOM ELECTRICAL SERVICES, INC. | ESL | C | 01/23/2020 | floor boxes in phase 2--ok / | BRIAN | BRIAN | | ESL | C | 6461679 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 01/17/2020 | all phase 1 walls, complete, | JOHNN | JOHNN | | ER | P | 6456317 |
PROCOM ELECTRICAL SERVICES, INC. | EUG | P | 12/19/2019 | floor boxes in phase 1 --ok / | BRIAN | BRIAN | | EUG | P | 6432062 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 12/13/2019 | partial walls in phase 1 / see plans | BRIAN | BRIAN | | ER | P | 6427071 |
PROCOM ELECTRICAL SERVICES, INC. | ER | R | 12/12/2019 | not ready / | BRIAN | BRIAN | | ER | R | 6425244 |
PROCOM ELECTRICAL SERVICES, INC. | ER | R | 12/12/2019 | not ready / | BRIAN | BRIAN | | ER | R | 6425245 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | C | 03/10/2020 | TAB REPORT RECEIVED | JERRYF | JERRYF | | H= | C | 6505344 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HSP | L | 03/10/2020 | NO TAB REPORT ATTACHED | JERRYF | JERRYF | | HSP | L | 6505126 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | P | 03/09/2020 | PARTIAL PENDING TAB REPORT NOTES: ALL SA / RA / EXHAUST GRILLES / FINAL CONNECTIONS AND CONTROLS ARE COMPLETE | JERRYF | JERRYF | | H= | P | 6504762 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | H= | P | 03/09/2020 | ENGINEER LETTER FOR DUCT INSULATION RECEIVED | JERRYF | JERRYF | | H= | P | 6503623 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | P | 02/18/2020 | MECHANICAL SPECIFICATIONS SO INSULATED DUCT ON SA / RA / VENTILATION AIR NEED LETTER FROM ENGINEER DELETING INSULATION OR INSULATE ALL DUCT NOTES: ABOVE CEILING SA / RA / OSA AND EXHAUST DUCT MAINS AND RUN OUTS OK | JERRYF | JERRYF | | HD | P | 6484562 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | HD | P | 02/07/2020 | ABOVE CEILING SA / RA MAINS / RUN OUTS / BOXES OK TO INCLUDE FROM GRID LINES 9 THROUGH 11 / BREAK AREA / CONFERENCE ROOM FCU 7 | JERRYF | JERRYF | | HD | P | 6476644 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | P= | C | 03/09/2020 | | SAMH | SAMH | | P= | C | 6504754 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | C | 03/09/2020 | | SAMH | SAMH | | PTO | C | 6504737 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PB | C | 12/27/2019 | Engineers letter received and sent to scanning | JOHNS | JOHNS | | PB | C | 6437940 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | P | 12/27/2019 | need to insulate all new waters per plan, need vertical support @ shwr hot and cold lines, inspector to verify bfp @ trap primers @ next inspection, rest ok. NOTE: aav @ both sinks, vtr (existing) @ shwr, check middle area water htr @ final, above ceiling water htr looked @ on PTO, engineers letter received for pex and sent to scanning, has (2) trap primers | JOHNS | JOHNS | | PTO | P | 6437930 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PB | P | 12/18/2019 | need engineers letter allowing pex under ground for trap primers (plans call out copper), cover @ own risk,
Partial status pending E letter
rest ok | JOHNS | JOHNS | | PB | P | 6430613 |
PROCOM ELECTRICAL SERVICES, INC. | XES | T | 08/31/2020 | PAID (REC#1711611): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised panel schedules. | BERTHA | BERTHA | | XES | T | 6690571 |
RAINE BUILDING LLC. | XBS | T | 03/04/2020 | PAID (REC#1666198) PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revised doors to include card readers and mag locks. | SHELLEY | SHELLEY | | XBS | T | 6500034 |