THE COPESTONE COMPANY | B= | C | 09/01/2020 | All other required Final inspections are complete. (This is a computer generated result) | JEREMYA | JEREMYA | | B= | C | 6692135 |
THE COPESTONE COMPANY | B= | P | 08/19/2020 | Building final complete pending other final inspections. Additional Inspections Required (computer generated): INTERMOUNTAIN POWER SERVICES INC Electrical Final Inspection is not Completed yet, PEAK HEATING & AIR COND, INC. Mechanical Final Inspection is not Completed yet. | JEREMYA | JEREMYA | | B= | P | 6678453 |
THE COPESTONE COMPANY | BFR | P | 07/31/2020 | Horizontal assembly above entry vestibule OK | JEREMYA | JEREMYA | | BFR | P | 6657817 |
THE COPESTONE COMPANY | BFR | P | 07/09/2020 | Corrections from previous inspection complete // East entry walls OK per approved UL listing // Need to splice in UL used for horizontal assembly above the walls. Listing used is not on the approved plans. U415 is what is being used, which is a USG listing.Went through components of listing with contractor to ensure they are using the correct products. | JEREMYA | JEREMYA | | BFR | P | 6632693 |
THE COPESTONE COMPANY | BFR | R | 07/02/2020 | not ready/discussed previous inspection with Pete/still need to attach plumbing permit | SCOTTS | SCOTTS | | BFR | R | 6625504 |
THE COPESTONE COMPANY | BFR | R | 06/18/2020 | need to attach all MEP permits and have inspections / all W01 and W03 walls are missing the braces at the top of walls to structure 4' on center per plan / still need to build all UL U465 walls at east entry / all other framing OK pending other roughs / discussed accessible elements including need for forward approach at break room sink or 4' clear floor space centered on sink for horizontal approach and dishwasher and refrigerator are both in the horizontal approach on the drawing. | DANE | DANE | | BFR | R | 6609967 |
THE COPESTONE COMPANY | BSP | P | 06/09/2020 | Contractor OK to one-side while finishing the framing. Still need full frame inspection once ready | JEREMYA | JEREMYA | | BSP | P | 6598033 |
INTERMOUNTAIN POWER SERVICES INC | E= | C | 08/20/2020 | | RANDY | RANDY | | E= | C | 6679344 |
INTERMOUNTAIN POWER SERVICES INC | E= | R | 08/18/2020 | need outlet under front desk trimmed out and TR outlets for waiting rm | RANDY | RANDY | | E= | R | 6677311 |
STILSON ELECTRIC SYSTEMS, INC. | E= | C | 08/04/2020 | FIRE ALARM INSPECTION: | RANDY | RANDY | | E= | C | 6660018 |
STILSON ELECTRIC SYSTEMS, INC. | ER | P | 07/30/2020 | FIRE ALARM INSPECTION: FA ceilings ok | RANDY | RANDY | | ER | P | 6655922 |
INTERMOUNTAIN POWER SERVICES INC | ER | P | 07/30/2020 | ceilings ok | RANDY | RANDY | | ER | P | 6655921 |
INTERMOUNTAIN POWER SERVICES INC | ER | P | 06/24/2020 | walls ok | RANDY | RANDY | | ER | P | 6616454 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 09/01/2020 | TEST AND BALANCE REPORT RECEIVED, SEE IMAGES. MECHANICAL FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6692134 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 08/21/2020 | MECHANICAL FINAL PENDING TEST AND BALANCE REPORT. | DUSTINS | DUSTINS | | H= | P | 6681711 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 07/30/2020 | ALL ABOVE CEILING DUCTS, FLEX AND DIFFUSERS INSTALLED EXCEPT MISSING RETURN AIR GRILLE IN FILES/CHARTS 108. STILL NEED TO SEE MINI SPLIT COMPLETED. PROVIDE TEST AND BALANCE REPORT FOR FINAL. | DUSTINS | DUSTINS | | HD | P | 6656621 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 07/22/2020 | ALL NEW MEDIUM/LOW PRESSURE SUPPLY AIR DUCTS ABOVE CEILING OK, OK TO WRAP EXCEPT MISSING 6" SUPPLY AIR IN HALLWAY 129 FROM VAV-4. | DUSTINS | DUSTINS | | HD | P | 6646059 |
FRONTIER MECHANICAL SYSTEMS INC | P= | C | 08/13/2020 | | JOSEPHD | JOSEPHD | | P= | C | 6670941 |
FRONTIER MECHANICAL SYSTEMS INC | P= | P | 08/12/2020 | will need to conduct more research into breakroom sink will update notes in morning, rest ok | JOSEPHD | JOSEPHD | | P= | P | 6670067 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 07/14/2020 | need to see water pipe insulation, water pipe over head ok, sink in 120 ok | JOSEPHD | JOSEPHD | | PTO | P | 6636952 |
FRONTIER MECHANICAL SYSTEMS INC | PTO | P | 07/07/2020 | need to see over head water piping completed, need engineer letter for aav @ breakroom sink, still need to see sink in room 120 completed, in wall water pipe and dwv ok, under floor dwv ok | JOSEPHD | JOSEPHD | | PTO | P | 6628541 |
THE COPESTONE COMPANY | XBS | P | 07/17/2020 | PLAN SPLICE: (No Fee) by: BPHILLIPS for Construction: Provided 1-hr soffit detail, engineering letter. | BPHILLIPS | BPHILLIPS | | XBS | P | 6641769 |
INTERMOUNTAIN POWER SERVICES INC | XES | P | 07/15/2020 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised Exam 01 and Exam 02. | BERTHA | BERTHA | | XES | P | 6638718 |
FRONTIER MECHANICAL SYSTEMS INC | XPS | T | 07/10/2020 | PAID (REC#1695409): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 1 revisions: P1.1 adjusted plumbing demolition plan, P1.2 adjusted plumbing water and waste & vent plans | SHANEN | SHANEN | | XPS | T | 6633305 |
PEAK HEATING & AIR CONDITIONING, INC. | XMS | T | 07/10/2020 | PAID (REC#1695407): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: cloud | DALEH | DALEH | | XMS | T | 6633117 |