MARK YOUNG CONSTRUCTION, INC. | B= | C | 03/10/2021 | Building final complete | ADAML | ADAML | | B= | C | 6894402 |
MARK YOUNG CONSTRUCTION, INC. | B= | P | 02/25/2021 | Building final complete pending other final inspections. No return trip needed | JEREMYA | JEREMYA | | B= | P | 6881540 |
MARK YOUNG CONSTRUCTION, INC. | BFR | P | 12/07/2020 | Main exterior sign frame OK - used contractor's copy of electronic RBD plans for inspection. | CHUCK | CHUCK | | BFR | P | 6798925 |
BIBLE ELECTRIC, INC. | E= | C | 11/19/2020 | 20 power drops , break room , vestibule lighting , produce lighting | TOMC | TOMC | | E= | C | 6782174 |
BIBLE ELECTRIC, INC. | ER | P | 10/21/2020 | ceiling in break room , buss gutter above electronics area | TOMC | TOMC | | ER | P | 6748673 |
HUSSMANN SERVICES CORPORATION | H= | C | 11/09/2020 | REFRIGERATION FINAL OK. | DUSTINS | DUSTINS | | H= | C | 6769740 |
HUSSMANN SERVICES CORPORATION | HRP | P | 10/30/2020 | 350 LB TEST OK ON LINE SET FOR C17. OK TO INSULATE. | DUSTINS | DUSTINS | | HRP | P | 6759435 |
FRONTIER MECHANICAL LLC | P= | C | 02/25/2021 | revised plans ok. | TAYLOR | TAYLOR | | P= | C | 6881295 |
FRONTIER MECHANICAL LLC | PTO | C | 02/25/2021 | | TAYLOR | TAYLOR | | PTO | C | 6881294 |
FRONTIER MECHANICAL LLC | P= | P | 02/01/2021 | lav at family restroom exceeds 34 inches in height. | TAYLOR | TAYLOR | | P= | P | 6855052 |
FRONTIER MECHANICAL LLC | P= | P | 01/19/2021 | complete lav at family restroom and revise plans. | TAYLOR | TAYLOR | | P= | P | 6840322 |
FRONTIER MECHANICAL LLC | PTO | P | 01/19/2021 | revise plans for new layout at family restroom, rest ok. | TAYLOR | TAYLOR | | PTO | P | 6840317 |
FRONTIER MECHANICAL LLC | P= | L | 01/15/2021 | cancelled at call ahead. | TAYLOR | TAYLOR | | P= | L | 6837774 |
FRONTIER MECHANICAL LLC | P= | P | 12/31/2020 | after corrections made ( need 15 inches from edge of wall to center of lav at family restroom ), rest ok. | TAYLOR | TAYLOR | | P= | P | 6823555 |
FRONTIER MECHANICAL LLC | P= | P | 12/03/2020 | lacks clear floor space at family restroom, lip of urinal exceeds 17 inches in height at front men's restroom, need 16 - 18 inches from partitions to center of toilets at rear men's and women's restrooms, rest ok. | TAYLOR | TAYLOR | | P= | P | 6795532 |
FRONTIER MECHANICAL LLC | PTO | P | 12/03/2020 | all existing plumbing, check toilet clearances at final, update: changed to partial on 1-12-2021 to allow PTO inspection for family restroom lav that was moved. | TAYLOR | TAYLOR | | PTO | P | 6795522 |
FRONTIER MECHANICAL LLC | XPS | T | 01/26/2021 | PAID (REC#1746429): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 3 revisions only: 1 sheet provided, P1.2 adjusted enlarged plumbing plans | SHANEN | SHANEN | | XPS | T | 6848539 |
BIBLE ELECTRIC, INC. | XES | T | 10/27/2020 | PAID (REC#1730671): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: As builts and added fabric table | SHELBY | SHELBY | | XES | T | 6755733 |
MARK YOUNG CONSTRUCTION, INC. | XBS | T | 10/27/2020 | PAID (REC#1730668): PLAN SPLICE FEE: $75 by: BPHILLIPS for Construction: Provided revised floor plan and details to reflect site conditions. | BPHILLIPS | BPHILLIPS | | XBS | T | 6754987 |
FRONTIER MECHANICAL LLC | XPS | T | 10/26/2020 | PAID (REC#1730672): PLAN SPLICE FEE: $50 by: TCRIPPEN for Plumbing: new splie adjusting floor drains | TCRIPPEN | TCRIPPEN | | XPS | T | 6754003 |
HUSSMANN SERVICES CORPORATION | XMS | P | 10/26/2020 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Added sheet notes | JUSTINC | JUSTINC | | XMS | P | 6753930 |