ROBINSON CONSTRUCTION, LLC. | B= | C | 03/08/2021 | Building final corrections complete. | CHUCK | CHUCK | | B= | C | 6892266 |
ROBINSON CONSTRUCTION, LLC. | BFR | C | 03/08/2021 | Frame verified. | CHUCK | CHUCK | | BFR | C | 6892265 |
ROBINSON CONSTRUCTION, LLC. | B= | R | 01/26/2021 | Cancelled by contractor (Fred R.) by phone prior to site visit. Additional Inspections Required (computer generated): EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet. | CHUCK | CHUCK | | B= | R | 6848672 |
ROBINSON CONSTRUCTION, LLC. | B= | R | 01/22/2021 | No BFR inspection results on file / Missing accessible restroom sign / Flush control not located on the open side of the water closet per 604.6 of the A117.1. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING CO Mechanical Final Inspection is not Completed yet. | CHUCK | CHUCK | | B= | R | 6846581 |
EL PASO ELECTRIC, LLC. | E= | C | 02/18/2021 | Electrical complete / | ROB | ROB | | E= | C | 6873409 |
EL PASO ELECTRIC, LLC. | E= | P | 02/11/2021 | Label should state the AIC of the fuse / | ROB | ROB | | E= | P | 6867555 |
EL PASO ELECTRIC, LLC. | E= | P | 02/10/2021 | Also need one for the Main Disconnect outside / | ROB | ROB | | E= | P | 6865705 |
EL PASO ELECTRIC, LLC. | E= | P | 02/09/2021 | Need labeling per 110.22 / | ROB | ROB | | E= | P | 6864270 |
EL PASO ELECTRIC, LLC. | E= | P | 01/29/2021 | New breakers installed need to be rated 22k / | ROB | ROB | | E= | P | 6852611 |
EL PASO ELECTRIC, LLC. | E= | P | 01/22/2021 | Need 20 amp breaker on HWH / Complete switch in bathroom / Pics ok, upload images with next inspection request. If you encounter problems uploading images, please contact IT at 799-2688 / Panel rated @ 22K, need to verify branch breakers / | ROB | ROB | | E= | P | 6845614 |
EL PASO ELECTRIC, LLC. | ER | C | 01/19/2021 | Rough ok / No FA going in per Fred / Need to check HWH at final / | ROB | ROB | | ER | C | 6840983 |
EL PASO ELECTRIC, LLC. | ER | P | 01/14/2021 | Still need to wire Water Heater above hard lid / Coil & tie up all low volt cables so nothing is laying on the grid. / Ceiling rough ok, FA not complete ---------do not close ceiling-------------- / Notes: Did see disconnect for one sign above drop ceiling. | JOSEPH | JOSEPH | | ER | P | 6836094 |
EL PASO ELECTRIC, LLC. | ER | P | 12/10/2020 | Wall rough ok / Bathroom walls and lid ok / Will need to look at ceiling when ready / | ROB | ROB | | ER | P | 6803981 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 03/02/2021 | REVISED TEST AND BALANCE REPORT RECEIVED - SEE IMAGES | MARKB | MARKB | | H= | C | 6884734 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 01/27/2021 | ENGINEER TO ADDRESS - Existing RTU schedule has outside air at 270 cfm but ventilation chart shows 340 cfm required. Balance report shows outside air adjustment at 284 cfm which is less than 10% of 340 cfm. | MARKB | MARKB | | H= | P | 6849681 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 01/21/2021 | Mechanical final ok pending receipt of test and balance report / | MARKB | MARKB | | H= | P | 6844421 |
OLSON PLUMBING & HEATING COMPANY | HD | C | 01/21/2021 | ABOVE CEILING DUCT - MAINS/BRANCHES/FLEX/DIFFUSERS COMPLETE PER PLAN SPLICE OK TO COVER. EXISTING THERMOSTAT | MARKB | MARKB | | HD | C | 6844407 |
OLSON PLUMBING & HEATING COMPANY | HD | R | 01/06/2021 | No approved mechanical splices found in computer. Duct matches unapproved plan on site provided by contractor - plan starts with two 14" round ducts off curb drop. Diffuser layout is the same as approved drawing. | MARKB | MARKB | | HD | R | 6827497 |
OLSON PLUMBING & HEATING COMPANY | HD | R | 12/31/2020 | Need correct suite number posted for where work is being performed. Duct sizes/shape does not match plan. | MARKB | MARKB | | HD | R | 6823543 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 01/21/2021 | | LEE | LEE | | P= | C | 6843739 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/31/2020 | OK PENDING FLOOR SINK REVISION | LEE | LEE | | PTO | P | 6823610 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 12/30/2020 | need to support pex in walls and ceiling to code, need to see water pipe insulation, still need plan revision from PB inspection, rest ok, note: water heater ok | JOSEPHD | JOSEPHD | | PTO | P | 6821993 |
OLSON PLUMBING & HEATING COMPANY | PB | C | 12/18/2020 | revise plan to show deleted floor sink | JOEL | JOEL | | PB | C | 6813296 |
OLSON PLUMBING & HEATING COMPANY | PB | P | 12/17/2020 | low test | JOEL | JOEL | | PB | P | 6811931 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 02/19/2021 | PAID (REC#1752980): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: new splice for outside air | TCRIPPEN | TCRIPPEN | | XMS | T | 6875103 |
EL PASO ELECTRIC, LLC. | XES | T | 02/04/2021 | PAID (REC#1748479): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Add series rating information for panel A | SHELBY | SHELBY | | XES | T | 6860409 |
OLSON PLUMBING & HEATING COMPANY | XMS | P | 01/20/2021 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Mechanical: okay see changes on plan pages | TCRIPPEN | TCRIPPEN | | XMS | P | 6842868 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 01/20/2021 | PAID (REC#1744366): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: okay see changes on plan pages | TCRIPPEN | TCRIPPEN | | XMS | T | 6842861 |