SNYDER BUILDING CONSTRUCTION, LLC | B= | C | 05/05/2021 | observation letter for perogla on file | BRIANB | BRIANB | | B= | C | 6957325 |
SNYDER BUILDING CONSTRUCTION, LLC | B= | P | 04/26/2021 | missing design professional stamp on observation letter for perogla - pending stamped copies / no return trip required after stamp copy of observation letter received / need to complete other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): AMEN PLUMBING AND HEATING Mechanical Final Inspection is not Completed yet, EL PASO GREEN ENERGIES LLC DBA PEAK VIEW Electrical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 6947519 |
SNYDER BUILDING CONSTRUCTION, LLC | BIN | P | 03/25/2021 | Insulation install at removed bulkhead above entry okay | BOBF | BOBF | | BIN | P | 6911272 |
SNYDER BUILDING CONSTRUCTION, LLC | BFR | P | 03/03/2021 | pending completion of other required inspections, interior wall and pony walls okay / still need all exterior inspections for pergola / Reviewed Accessible Elements / | BOBF | BOBF | | BFR | P | 6886531 |
EL PASO GREEN ENERGIES LLC | E= | C | 05/04/2021 | Electrical complete / | ROB | ROB | | E= | C | 6955847 |
EL PASO GREEN ENERGIES LLC | E= | P | 04/29/2021 | (2) 4-250 KCMIL AL installed / Splice shows 4/0 / Pic ok for Revised fault current when feeders are spliced / | ROB | ROB | | E= | P | 6952088 |
EL PASO GREEN ENERGIES LLC | E= | P | 04/28/2021 | Need to verify revised feeder size and fault current labeling / Nobody on site / | ROB | ROB | | E= | P | 6949775 |
EL PASO GREEN ENERGIES LLC | E= | P | 04/23/2021 | Still needing splice to prints reflecting feeder changes / rest of items were corrected. | AARONR | AARONR | | E= | P | 6945950 |
EL PASO GREEN ENERGIES LLC | E= | P | 04/16/2021 | Need to splice prints for feeders-do not match one line / GFCI's cannot be blocked / Need GFCI for bar receptacles within 6' of sink / Need to check o/s area / Need to repair GFCI on east wall kitchen / GFCI behind equipment next to cash register / Need Fault Current Labels for panels and main / Need control for patio heat / Need to check Cooler and Freezer / | ROB | ROB | | E= | P | 6937204 |
EL PASO GREEN ENERGIES LLC | ER | P | 03/25/2021 | Rough ok for framed ceiling over bar / NOTE: Check at final: Access in sheetrock ceiling for j-box over garage door and relocated j-boxes that were mounted to joist above cloud ceiling / | ROB | ROB | | ER | P | 6911134 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 03/22/2021 | FIRE ALARM INSPECTION: Complete / | ROB | ROB | | E= | C | 6905985 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 03/22/2021 | FIRE ALARM INSPECTION: Rough ok / | ROB | ROB | | ER | C | 6905982 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 03/22/2021 | FIRE ALARM INSPECTION: Rough ok / | ROB | ROB | | E= | C | 6905983 |
EL PASO GREEN ENERGIES LLC | ER | P | 03/19/2021 | above ceilings rough in okay except in hall over electrical panels | CHIPO | CHIPO | | ER | P | 6905019 |
EL PASO GREEN ENERGIES LLC | ER | P | 03/05/2021 | Rough ok for walls / | ROB | ROB | | ER | P | 6889708 |
EL PASO GREEN ENERGIES LLC | ER | P | 03/03/2021 | Rough ok for dining ceiling / Rough ok for walls except where mc cable is fed thru conduits under slab / | ROB | ROB | | ER | P | 6887501 |
EL PASO GREEN ENERGIES LLC | ESL | C | 02/22/2021 | 3/4 inch PVC stub ups and 5 inch chase for MC okay | CHIPO | CHIPO | | ESL | C | 6877335 |
AMEN PLUMBING- HEATING, LLC | H= | C | 05/04/2021 | CORRECTION MADE SEE IMAGES | JERRYF | JERRYF | | H= | C | 6955864 |
AMEN PLUMBING- HEATING, LLC | H= | R | 04/30/2021 | PER PREVIOUS FROM INSPECTION ENTRY GAS FLEX CONNECTOR IS INSTALLED INCORRECTLY - STOPPED INSPECTION | JERRYF | JERRYF | | H= | R | 6953735 |
AMEN PLUMBING- HEATING, LLC | H= | R | 04/30/2021 | GAS FLEX CONNECTOR AT TUBE HEATER IS INSTALLED INCORRECTLY NOTES: PICTURES RECEIVED FOR PIPE SUPPORT AND FLEX CONNECTOR | JERRYF | JERRYF | | H= | R | 6952820 |
AMEN PLUMBING- HEATING, LLC | HI | P | 04/21/2021 | NEED ADDITIONAL SUPPORT AT 2" LINE IN KITCHEN AREA ( CONTRACTOR CAN ATTACH PICTURES TO NEXT INSPECTION REQUEST NOTES: PRESSURE TEST OK AND PIPING AT INTERIOR PER REVISED PLAN | JERRYF | JERRYF | | HI | P | 6942539 |
AMEN PLUMBING- HEATING, LLC | HO | P | 04/21/2021 | NEED REVISED PLAN SHOWING 2" GAS LINE AS INSTALLED INCLUDING ROUTING UNDER GROUND AT SIDE OF BUILDING - NEED ADDITIONAL SUPPORT AT 2" LINE ABOVE KITCHEN AREA IN CEILING BEFORE METER RELEASE - CONTRACTOR PROCEEDING AT OWN RISK - NEED FINAL CONNECTION AT HEATER (CONTRACTOR TO SUPPLY PICTURES OF CONNECTION TO NEXT REQUEST NOTES: PRESSURE TEST OK | JERRYF | JERRYF | | HO | P | 6942536 |
REEVES SPECIALTY SERVICES, INC. | H= | C | 04/19/2021 | TAB REPORT RECEIVED AND EXHAUST FAN TAG IS COMPLETE | JERRYF | JERRYF | | H= | C | 6937644 |
REEVES SPECIALTY SERVICES, INC. | H= | P | 04/16/2021 | PARTIAL PENDING THE FOLLOWING - TAB REPORT AND PICTURE OF UNIT TAG AT EXHAUST FAN FOR TYPE 2 HOODS (ATTACH PICTURE OF UNIT TAG TO TAB REPORT NOTES: ALL SA / RA EXHAUST GRILLES / ALL CONTROLS ARE COMPLETE / | JERRYF | JERRYF | | H= | P | 6937276 |
AMEN PLUMBING- HEATING, LLC | HSP | R | 04/09/2021 | CHANGED INSPECTION TO HSP - IT IS NOT THE INSPECTORS JOB TO INSTRUCT CONTRACTOR ON WHAT TYPE OF MATERIAL NEEDS TO BE USED FOR UNDER GROUND PIPING - CALLED AND TALKED TO DAVE AT AMEN AND TOLD HIM HE NEEDS TO BE ON SITE FOR ALL INSPECTIONS | JERRYF | JERRYF | | HSP | R | 6928920 |
REEVES SPECIALTY SERVICES, INC. | HD | P | 04/05/2021 | DUCTS TO PLANS FOR 2 TYPE TWO HOODS AND HVAC MODIFICATIONS AT FRONT AND BACK KITCHEN AREA. NEED ROOF INSPECTION AND FRONT HEATERS INSTALLED WHEN READY AND CALL INSPECTION. | JON | JON | | HD | P | 6922930 |
A & H PLUMBING LLC | P= | C | 04/16/2021 | Ok. | DANR | DANR | | P= | C | 6936888 |
A & H PLUMBING LLC | PTO | C | 03/18/2021 | See images for pictures of nail protection and pipe support. Note: Need engineers approval letter for CWV all floor sinks / AAV at bar / check overhead insulation at final. | DANR | DANR | | PTO | C | 6902433 |
A & H PLUMBING LLC | PTO | P | 03/03/2021 | Need nail protection at bar sink baseplate / need pipe support for overhead vent on hand sink, pictures ok / ok to insulate domestic water / rest ok. Note: Need engineers approval letter for CWV all floor sinks / AAV at bar. | DANR | DANR | | PTO | P | 6887219 |
A & H PLUMBING LLC | PB | C | 03/03/2021 | See plans splice. | DANR | DANR | | PB | C | 6887213 |
A & H PLUMBING LLC | PB | P | 02/23/2021 | Need plan splice for added floor sink by soda table / need engineer approval for CWV at all floor sinks / Images of water under floor to bar area received from contractor. | DANR | DANR | | PB | P | 6878469 |
A & H PLUMBING LLC | PB | P | 02/22/2021 | Need plan splice for added floor sink by soda table / need to run all waters to bar area and insulate through concrete / need engineer approval for CWV at all floor sinks. | DANR | DANR | | PB | P | 6876816 |
EL PASO GREEN ENERGIES LLC | XES | T | 04/30/2021 | PAID (REC#1769509): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised one-line | BERTHA | BERTHA | | XES | T | 6952964 |
AMEN PLUMBING- HEATING, LLC | XMS | T | 04/28/2021 | PAID (REC#1769032) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised for underground gas line | JUSTINC | JUSTINC | | XMS | T | 6950389 |
EL PASO GREEN ENERGIES LLC | XES | P | 04/26/2021 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised schedules, load summary, revised circuit numbers on power plan, added festoon lighting. | BERTHA | BERTHA | | XES | P | 6947654 |
AMEN PLUMBING- HEATING, LLC | XMS | T | 04/09/2021 | PAID (REC#1766386) PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised to show existing return air locations | JUSTINC | JUSTINC | | XMS | T | 6928822 |
A & H PLUMBING LLC | XPS | T | 02/26/2021 | PAID (REC#1753661): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 3 revisions: P1.02 adjusted plumbing waste plan, P2.01 adjusted waste & vent isometric drawing | SHANEN | SHANEN | | XPS | T | 6882231 |