RAINE BUILDING LLC. | B= | C | 03/01/2022 | Final items OK | ADAML | ADAML | | B= | C | 7285362 |
RAINE BUILDING LLC. | B= | P | 01/10/2022 | Final items OK pending all other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), HARRIS ELECTRIC GROUP Electrical Final Inspection is not Completed yet, MECH ONE, INC. Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7233673 |
RAINE BUILDING LLC. | B16 | P | 12/16/2021 | Provided on site consultation and discussed restroom accessibility and other final items | ADAML | ADAML | | B16 | P | 7212342 |
RAINE BUILDING LLC. | BFR | P | 12/09/2021 | Engineer letter on file for structural steel bolting and welding | ADAML | ADAML | | BFR | P | 7202747 |
RAINE BUILDING LLC. | BSP | P | 10/11/2021 | Met with superintendent to discuss accessibility requirements for break room and classroom cabinetry | TIMOTHYS | TIMOTHYS | | BSP | P | 7137682 |
RAINE BUILDING LLC. | BFR | P | 10/04/2021 | Box header above window to Resource Room OK | ADAML | ADAML | | BFR | P | 7128990 |
RAINE BUILDING LLC. | BFR | P | 09/10/2021 | Box headers OK except over knee wall for Resource Center which isn't installed yet / Knee wall framing OK on South wall of Resource Center | ADAML | ADAML | | BFR | P | 7103873 |
RAINE BUILDING LLC. | BFR | P | 09/02/2021 | Still need to inspect box headers at glass wall locations and knee wall at library / All other light gauge steel stud framing ok | TIMOTHYS | TIMOTHYS | | BFR | P | 7095848 |
RAINE BUILDING LLC. | BFR | P | 08/20/2021 | Light gauge steel framing for partition type C03A ok Grid lines K-M 1-9 / Still need to inspect full height partition type B03 / Fur out framing in vestibule ok | TIMOTHYS | TIMOTHYS | | BFR | P | 7080681 |
RAINE BUILDING LLC. | BFR | P | 08/11/2021 | PARTIAL FRAME- Pending all other required inspections / East side- Light gauge metal framing OK for both restrooms, break room and 15 offices grid line 8 to 9 / West side- Light gauge metal framing OK including hard lid framing for both restrooms at grid line 3 to 4 H to G / Reviewed accessible elements | ADAML | ADAML | | BFR | P | 7068968 |
HARRIS ELECTRIC GROUP | E= | C | 01/28/2022 | | JOHNN | JOHNN | | E= | C | 7253304 |
HARRIS ELECTRIC GROUP | EP | C | 01/28/2022 | transformers,panels,ok | JOHNN | JOHNN | | EP | C | 7253302 |
HARRIS ELECTRIC GROUP | EP | P | 01/20/2022 | both 150 KVA transformers,ok/ except need common grd bar in each/ label primary cb's feeding transformers/ Photo upload requested. If unfamiliar with uploading photos for an inspection, please click the following link: https://youtu.be/QS0hdGSBA6o / | JOHNN | JOHNN | | EP | P | 7245259 |
HARRIS ELECTRIC GROUP | EP | P | 01/18/2022 | I need to talk with Bret C about this. | JOHNN | JOHNN | | EP | P | 7241919 |
HARRIS ELECTRIC GROUP | E= | P | 01/04/2022 | Need to inspect panels & one-line area /Need to splice drawings new AHU 13 & 14 new loads to panel HMA1 / East side - 157 / West side - 135, 145 & 147 - 2 - 60 amp AHU's - ok / Splice required, please submit splice for changes in scope. If unfamiliar in submitting electronic splice, please click the following link: https://youtu.be/dG3kHpgDP0w / | BRETC | BRETC | | E= | P | 7227865 |
HARRIS ELECTRIC GROUP | E= | P | 12/29/2021 | East side except - 157 / West side except - 135, 145 & 147 - 2-AHU's, panels & one-line area / Water heater 35 amp - Ok | BRETC | BRETC | | E= | P | 7223500 |
HARRIS ELECTRIC GROUP | E= | R | 12/20/2021 | East side, except rooms: 157,158,164. | JOHNN | JOHNN | | E= | R | 7215325 |
HARRIS ELECTRIC GROUP | ER | C | 12/16/2021 | all ceiling complete. | JOHNN | JOHNN | | ER | C | 7211059 |
HARRIS ELECTRIC GROUP | EP | P | 12/10/2021 | looked at P and H panels/ P panels,ok/ H panels missing a few branch cb's/don't need to open panels up again. | JOHNN | JOHNN | | EP | P | 7205554 |
HARRIS ELECTRIC GROUP | ER | P | 12/10/2021 | 2 clouds at foyer: need nm connectors at each light for LV controls/1 j box is open/ conferance rm cloud,ok. | JOHNN | JOHNN | | ER | P | 7205549 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 11/30/2021 | FIRE ALARM INSPECTION: | JOHNN | JOHNN | | E= | C | 7192117 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 11/30/2021 | FIRE ALARM INSPECTION: | JOHNN | JOHNN | | E= | C | 7192111 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 11/30/2021 | FIRE ALARM INSPECTION: | JOHNN | JOHNN | | ER | C | 7192110 |
HARRIS ELECTRIC GROUP | ER | P | 11/23/2021 | Area's marked on drawings 11/23 / VAV's 13-4, 13-5, 13-6 & 14-16 - Ok | BRETC | BRETC | | ER | P | 7187475 |
HARRIS ELECTRIC GROUP | ER | P | 11/18/2021 | Ceiling areas marked on drawings / VAV's - 13-1, 14-5.1, 14-5.2 & 14-7 | BRETC | BRETC | | ER | P | 7182073 |
HARRIS ELECTRIC GROUP | ER | P | 11/17/2021 | Ceiling areas marked on drawings 11/17 / VAV's 13-2, 13-12, 13-13, 13-14, 13-17 & 14-15 | BRETC | BRETC | | ER | P | 7179840 |
HARRIS ELECTRIC GROUP | ER | P | 11/15/2021 | grid, see plans, | JOHNN | JOHNN | | ER | P | 7177125 |
HARRIS ELECTRIC GROUP | ER | P | 11/08/2021 | grid, see plans. | JOHNN | JOHNN | | ER | P | 7169118 |
HARRIS ELECTRIC GROUP | ER | P | 11/04/2021 | rough inside foyer reception millwork/ no ceilings today. | JOHNN | JOHNN | | ER | P | 7165968 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 11/02/2021 | FIRE ALARM INSPECTION: grid, see plans. | JOHNN | JOHNN | | ER | P | 7162706 |
HARRIS ELECTRIC GROUP | ER | P | 11/02/2021 | grid, see plans. | JOHNN | JOHNN | | ER | P | 7162701 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 10/27/2021 | FIRE ALARM INSPECTION: 95% of all ceilings - Ok | BRETC | BRETC | | ER | P | 7156126 |
HARRIS ELECTRIC GROUP | ER | P | 10/27/2021 | Ceilings marked on drawings 10/27 | BRETC | BRETC | | ER | P | 7156125 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 10/18/2021 | FIRE ALARM INSPECTION: grid, see plans | JOHNN | JOHNN | | ER | P | 7144945 |
HARRIS ELECTRIC GROUP | ER | P | 10/18/2021 | grid, see plans/ | JOHNN | JOHNN | | ER | P | 7144905 |
HARRIS ELECTRIC GROUP | ER | P | 10/11/2021 | vestibule hard lid/ see plans, | JOHNN | JOHNN | | ER | P | 7137371 |
HARRIS ELECTRIC GROUP | ER | P | 10/07/2021 | vestibule hard lid not complete: wire in heater/ CHECK access LATER for 4 boxes closed/ | JOHNN | JOHNN | | ER | P | 7133916 |
HARRIS ELECTRIC GROUP | ER | P | 10/04/2021 | walls, see plans/ | JOHNN | JOHNN | | ER | P | 7128830 |
HARRIS ELECTRIC GROUP | ER | P | 09/29/2021 | walls, see plans. | JOHNN | JOHNN | | ER | P | 7124240 |
HARRIS ELECTRIC GROUP | ER | P | 09/27/2021 | Walls marked on drawings only - Ok - 9/27 | BRETC | BRETC | | ER | P | 7120691 |
HARRIS ELECTRIC GROUP | ESL | C | 09/27/2021 | 2 floor boxes in conference room - Ok | BRETC | BRETC | | ESL | C | 7120689 |
HARRIS ELECTRIC GROUP | ER | P | 09/22/2021 | Walls only marked on drawings 9/22 | BRETC | BRETC | | ER | P | 7116222 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 09/20/2021 | FIRE ALARM INSPECTION: see plans, walls, | JOHNN | JOHNN | | ER | P | 7112957 |
HARRIS ELECTRIC GROUP | ER | P | 09/20/2021 | walls, see plans, | JOHNN | JOHNN | | ER | P | 7112956 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 09/15/2021 | FIRE ALARM INSPECTION: walls, see plans, | JOHNN | JOHNN | | ER | P | 7107837 |
HARRIS ELECTRIC GROUP | ER | P | 09/15/2021 | walls, see plans, | JOHNN | JOHNN | | ER | P | 7107835 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 09/10/2021 | FIRE ALARM INSPECTION: walls, see plans, | JOHNN | JOHNN | | ER | P | 7103638 |
HARRIS ELECTRIC GROUP | ER | P | 09/10/2021 | walls, see plans. | JOHNN | JOHNN | | ER | P | 7103627 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 09/07/2021 | FIRE ALARM INSPECTION: walls, see plans, | JOHNN | JOHNN | | ER | P | 7098471 |
HARRIS ELECTRIC GROUP | ER | P | 09/07/2021 | walls, see plans. | JOHNN | JOHNN | | ER | P | 7098470 |
HARRIS ELECTRIC GROUP | ER | P | 09/01/2021 | Walls only marked on drawings - Ok, 9/1 | BRETC | BRETC | | ER | P | 7093087 |
SPECIAL SYSTEMS DESIGN,LLC | ER | P | 08/26/2021 | FIRE ALARM INSPECTION: Walls only marked on drawings 8-26 / 3 wall pipe - only | BRETC | BRETC | | ER | P | 7086269 |
HARRIS ELECTRIC GROUP | ER | P | 08/26/2021 | Walls only marked on drawings 8-26 / Breakroom and Restrooms | BRETC | BRETC | | ER | P | 7086266 |
HARRIS ELECTRIC GROUP | ER | P | 08/20/2021 | walls, see plans, FA permit is pulled/ Discussed accessibility requirements with contractor / | JOHNN | JOHNN | | ER | P | 7080433 |
MECHONE, INC. | H= | C | 02/28/2022 | ENGINEER APPROVED TEST AND BALANCE REPORT RECEIVED | MARKB | MARKB | | H= | C | 7283558 |
MECHONE, INC. | H= | P | 02/04/2022 | FINAL ENDING - Address test and balance report. SLOT DIFFUSERS IN ROOM 165 AND DUCT SMOKE DETECTORS COMPLETE FOR AHU'S 13 & 14 | MARKB | MARKB | | H= | P | 7259967 |
MECHONE, INC. | H= | P | 02/03/2022 | ----ENGINEER TO ADDRESS: Test and balance report has a note that zoned portion of system for upstairs could not be balanced---- | MARKB | MARKB | | H= | P | 7258286 |
MECHONE, INC. | H= | P | 11/16/2021 | FINAL PENDING - Install smoke duct detectors on AHU'S 13 & 14. Complete condensate piping for AHU'S 13, 14 & I.t. room. Complete 2 slot diffusers in conference room 165. Provide test and balance report. ALL OTHER DIFFUSERS AND FAN POWERED BOXES ARE COMPLETE. | MARKB | MARKB | | H= | P | 7179250 |
MECHONE, INC. | HD | P | 11/09/2021 | ABOVE CEILING DUCT - PFPB 14-7 COMPLETE, PFPB 14-17 AND DIFFUSERS COMPLETE. FLEX AND DIFFUSERS COMPLETE IN ROOMS 165A, 157, 159, 161, 160, 196, 210, 207, 208, 163, 162, 144, 143, 139, 142, 141, 138, 137, 134, 132, 133, 110, 111, 237, 103, 104, 105 & 106. FLEX & DIFFUSERS COMPLETE IN HALLWAYS AT GRID LINES 7.5 (NORTH TO SOUTH), K (EAST TO WEST), 5.5 (NORTH TO SOUTH) & J.2 (EAST TO WEST) | MARKB | MARKB | | HD | P | 7171056 |
MECHONE, INC. | HD | P | 11/04/2021 | REVIEWING 6" ROUND EXHAUST DUCTS FOR BATHROOMS AND ROOM #210 (PLANS CALL FOR 8"X8"). Inspection for flex grills and diffusers-- all supply flex ducts and return complete for PFPB 14-17 (room 209), all supply air flex ducts complete for VAV #14-2 and return air grills and boots complete (rooms #201/202/203/204/205/206) and East (N.S.) hallway, all supply air flex ducts complete for VAV #14-1 and return grills and boots for room #210, PFPB 14-5.1 & 14-5.2 installed/sealed and supported. | PAULO | PAULO | | HD | P | 7166364 |
MECHONE, INC. | HD | P | 10/27/2021 | ABOVE CEILING DUCT - DUCT, FLEX AND DIFFUSERS COMPLETE IN ROOM 151. FLEX AND DIFFUSERS COMPLETE IN ROOMS: LOBBY AREA, 101, 102, 158, 164, 204, 205 & 206. | MARKB | MARKB | | HD | P | 7156277 |
MECHONE, INC. | HD | P | 10/12/2021 | ----ENGINEER TO ADDRESS: Duct for PFPB 14-5.1, VAV14-14 and AC-1 not installed per plan---- --ADD VAV'S and FAN POWERED BOXES to permit scope. ABOVE CEILING DUCT - SUPPLY MEDIUM/LOW PRESSURE DUCT AND VAV'S INSTALLED PER PLAN FROM NORTH ENTRANCE BACK SOUTH TO GRID LINE "H" EAST OF GRID LINE "7" AND WEST OF GRID LINE "7" BACK TO GRID LINE "G". FLEX AND DIFFUSERS ARE COMPLETE IN AREA BETWEEN GRID LINES 7.5 - 9 AND GRID LINES M - J. SEE SHARED PLAN SHEET M1.1 SPLICE (blue beam page 58). Duct past grid lines "h" & "g" to the south have been covered prior to inspection. No fan powered boxes installed at time of inspection. | MARKB | MARKB | | HD | P | 7138583 |
MECHONE, INC. | HD | P | 09/10/2021 | ABOVE CEILING DUCT - Contractor has a splice going through plan review at this time and will call for an inspection once that splice is approved. DUCT IS OK FOR SEALING AND SUPPORT - CONTINUE AT OWN RISK. SUPPLY/RETURN DUCT AT BOTH EXISTING AHU'S OK TO COVER. | MARKB | MARKB | | HD | P | 7103694 |
MECHONE, INC. | HD | R | 08/13/2021 | INSPECTION WAS FOR LOW PRESSURE DUCT BETWEEN GRID LINES 6 & 2 - CONTRACTOR WORKING OFF OTHER THAN APPROVED PLAN AND WHAT IS INSTALLED DOES NOT MATCH APPROVED PLAN. | MARKB | MARKB | | HD | R | 7072528 |
MECHONE, INC. | HD | P | 07/30/2021 | 1ST FLOOR: ABOVE CEILING DUCT - 46X32 & 42X32 MEDIUM PRESSURE DUCT FOR AHU-13 & 14 INSTALLED PER PLAN OK TO WRAP. Still needs to be completed through wall to AHU'S | MARKB | MARKB | | HD | P | 7056349 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | P= | C | 01/07/2022 | ALL ITEMS CORRECTED | LEE | LEE | | P= | C | 7232884 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | C | 12/22/2021 | men's restroom ok. | TAYLOR | TAYLOR | | PTO | C | 7218932 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | P= | P | 12/15/2021 | Need inspection men's rest room / need trap guards all floor drain / GGE 127 toilet wall to edge of sink lacking clearance ( at 59-1/8") / drinking fountains not working / Need PTO completed / rest ok. | DANR | DANR | | P= | P | 7209664 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | P | 12/15/2021 | Left PTO open for men's restroom / Tie in and splice ok / | DANR | DANR | | PTO | P | 7209660 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | P | 09/20/2021 | PIPE SUPPORT OK -- INSULATION OK -- STILL NEED REVISIONS AND TIE-IN INSPECTION ( POSSIBLE GRADE ISSUE ) | LEE | LEE | | PTO | P | 7113291 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | P | 08/27/2021 | NEED TO SUPPORT OVERHEAD COPPER TO CODE -- ((( NEED PLANS REVISED TO SHOW RELOCATED SINKS X-2 ))) -- NEED DOMESTIC WATER INSULATED PER PLANS -- CHECK GRADE AT TWO RESTROOM / BREAK ROOM TIE-IN WHEN COMPLETE -- REST OK -- NOTE: NO WATER HEATER AT THIS TIME | LEE | LEE | | PTO | P | 7089209 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | PTO | P | 08/20/2021 | ( MAIN RESTROOMS, BREAK SINK AND MOP SINK ) -- 3" VENT BACK-GRADED, MENS LAV DRAIN BACK-GRADED -- NOTES FOR RBD - 2" BALL VALVE ACCESS WITH TAG UNDER LAV AT FINAL | LEE | LEE | | PTO | P | 7080622 |
SPECIAL SYSTEMS DESIGN,LLC | XES | T | 01/26/2022 | PAID (REC#1839265) PLAN SPLICE FEE: $50 by: DANIELG for Electrical: Revised plans to address inspectors comment. | DANIELG | DANIELG | | XES | T | 7251248 |
SPECIAL SYSTEMS DESIGN,LLC | XES | T | 10/27/2021 | PAID (REC#1818320) PLAN SPLICE FEE: $50 by: DANIELG for Electrical: Revised one-line. | DANIELG | DANIELG | | XES | T | 7157136 |
MECHONE, INC. | XMS | T | 10/21/2021 | PAID (REC#1816745) PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: Approved new splice revised ducts see clouds. | TCRIPPEN | TCRIPPEN | | XMS | T | 7149783 |
RAINE BUILDING LLC. | XBS | T | 10/13/2021 | PAID (REC#1814548) PLAN SPLICE FEE: $50 by: GITA for Construction: relocate 2 sinks to different locations | GITA | GITA | | XBS | T | 7140742 |
MECHONE, INC. | XMS | P | 10/07/2021 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Multiple layout revisions | JUSTINC | JUSTINC | | XMS | P | 7134370 |
SPECIAL SYSTEMS DESIGN,LLC | XES | T | 10/07/2021 | PAID (REC#1814549) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revise load summary. | SHELBY | SHELBY | | XES | T | 7134364 |
JOHNSON BROTHER'S PLUMBING & HEATING LLC | XPS | T | 10/07/2021 | PAID (REC#1814550) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing Delta 4 revisions: adjusted sheet P1.1 and P2.1. | SHANEN | SHANEN | | XPS | T | 7134334 |