MARK YOUNG CONSTRUCTION, LLC | B= | C | 10/04/2022 | welding observation letter on file | BRIANB | BRIANB | | B= | C | 7538274 |
MARK YOUNG CONSTRUCTION, LLC | B= | P | 09/30/2022 | Building final complete pending welding/bolting letter uploaded -- Schedule a new Building Final when above items are complete. | JEREMYA | JEREMYA | | B= | P | 7536253 |
MARK YOUNG CONSTRUCTION, LLC | B= | R | 07/14/2022 | call ahead confirmed 11:11 - no answer at call ahead number provided with inspection request and left v.m onsite / unable to gain access to perform inspection / no inspection performed. Additional Inspections Required (computer generated): HUSSMANN SERVICES CORPORATION Mechanical Final Inspection is not Completed yet, TDR CONTRACTORS, INC. Mechanical Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | R | 7446251 |
MARK YOUNG CONSTRUCTION, LLC | BSP | R | 02/23/2022 | documents uploaded to need to go to electric permit | LONNYS | LONNYS | | BSP | R | 7279540 |
MARK YOUNG CONSTRUCTION, INC. | BFR | P | 10/15/2021 | pending other required inspections // need to splice in wall extension at pick up freezer / provide welding and bolting obs. for RTUs / interior light gauge steel framing in meat utility room OK | LONNYS | LONNYS | | BFR | P | 7143120 |
BIBLE ELECTRIC, INC. | E= | C | 09/21/2022 | E= OK ----- | GREGM | GREGM | | E= | C | 7524166 |
BIBLE ELECTRIC, INC. | EE | C | 09/19/2022 | | MATTHEW | MATTHEW | | EE | C | 7522025 |
BIBLE ELECTRIC, INC. | E= | P | 04/21/2022 | E= OK -------- CLEARANCE FOR CONTROLS BOX AT AIR CURTAIN ----- CHANGED TO PARTIAL 7-26-22 ---- | GREGM | GREGM | | E= | P | 7346606 |
BIBLE ELECTRIC, INC. | E= | R | 01/25/2022 | PLAN SPLICE NEEDS TO BE APPROVED BEFORE FINAL INSP ------- | GREGM | GREGM | | E= | R | 7249105 |
BIBLE ELECTRIC, INC. | E= | R | 11/10/2021 | NOT READY FOR FINAL --- COMPLETE PLAN SPLICE ----- | GREGM | GREGM | | E= | R | 7171844 |
BIBLE ELECTRIC, INC. | ER | P | 11/10/2021 | ER OK ---- 4 WALK-IN COOLERS ---- | GREGM | GREGM | | ER | P | 7171830 |
BIBLE ELECTRIC, INC. | ER | R | 10/08/2021 | NEED REVISED PLANS SPICED ----- | GREGM | GREGM | | ER | R | 7135091 |
BIBLE ELECTRIC, INC. | E= | R | 09/21/2021 | Two new coolers on exterior wall okay - need splice on prints eliminating the moving of managers station from scope of work | CHIPO | CHIPO | | E= | R | 7114249 |
BIBLE ELECTRIC, INC. | ER | P | 09/21/2021 | rough in for two new coolers on exterior wall okay | CHIPO | CHIPO | | ER | P | 7114247 |
TDR CONTRACTORS, INC. | H= | C | 09/21/2022 | AIR CURTAIN OK / | LIDO | LIDO | | H= | C | 7524807 |
HUSSMANN SERVICES CORPORATION | H= | C | 09/06/2022 | ALARM PROBE FOR WALK IN PICKUP FREEZER AND PICKUP COOLER OK / CONDENSERS ON ROOF LABELED. SEE IMAGES / REFRIGERATION CONTRACTOR FINAL OK / | LIDO | LIDO | | H= | C | 7506430 |
HUSSMANN SERVICES CORPORATION | H= | P | 08/02/2022 | FINAL PENDING : ALARM PROBE FOR WALK IN PICKUP FREEZER AND PICKUP COOLER #1 ARE BROKEN / LABEL CONDENSERS ON ROOF FOR WALK IN PICKUP FREEZER, PICKUP COOLER 1 AND 2, MEAT UTILITY / OK TO ATTACH PICTURE OF CORRECTION TO AN INSPECTION REQUEST / | LIDO | LIDO | | H= | P | 7468102 |
TDR CONTRACTORS, INC. | H= | P | 07/22/2022 | PLAN PAGE M1 (BDA 67) AIR CURTAIN (AC#) EAST SIDE OF BUILDING PICK UP AREA : FINAL PENDING : LACKING 36" SERVICE CLEARANCE TO HIGH VOLTAGE CONTROL BOX / | LIDO | LIDO | | H= | P | 7456813 |
TDR CONTRACTORS, INC. | HRP | C | 07/22/2022 | PLAN PAGE M1 (BDA 67) AIR CURTAIN (AC#) EAST SIDE OF BUILDING PICK UP AREA : LACKING 36" SERVICE CLEARANCE TO HIGH VOLTAGE CONTROL BOX (correct for final)/ | LIDO | LIDO | | HRP | C | 7456808 |
HUSSMANN SERVICES CORPORATION | HE | L | 07/20/2022 | Renewed online for Half Fee at Jul 20 2022 12:16PM (RECEIPT #: 1884646) | WEBSITE | WEBSITE | | HE | L | 7453280 |
TDR CONTRACTORS, INC. | HE | L | 07/15/2022 | Renewed for $50.00 at 7/15/2022 11:23:07 AM (Receipt#1883435) | JACKIEP | JACKIEP | | HE | L | 7448012 |
HUSSMANN SERVICES CORPORATION | HRP | P | 10/08/2021 | 4 - 310LB TESTS OK / REFRIGERATION PIPING FROM WALK IN 1-PICKUP FREEZER, 2-PICKUP COOLERS AND 1- MEAT UTILITY TO ROOF OK. NEED FINAL CONNECTIONS TO EVAP COILS AND RCU ROOF TOP UNITS. | LIDO | LIDO | | HRP | P | 7135812 |
INTERSTATE MECHANICAL, INC. | P= | C | 06/28/2022 | | LEE | LEE | | P= | C | 7427242 |
INTERSTATE MECHANICAL, INC. | PE | L | 05/25/2022 | Renewed online for Half Fee at May 25 2022 8:02AM (RECEIPT #: 1869563) | WEBSITE | WEBSITE | | PE | L | 7388173 |
INTERSTATE MECHANICAL, INC. | P= | P | 11/12/2021 | NEED SPLICE / LETTER FOR USE OF EXISTING DRAINS IN FRONT OF PICKUP COOLER AND PICKUP FREEZER INSTEAD OF ADDING NEW DRAINS PER PLANS -- REST OK | LEE | LEE | | P= | P | 7175850 |
INTERSTATE MECHANICAL, INC. | PTO | P | 10/14/2021 | MEAT PREP -- IN WALLS DWV AND H20 OK -- VENTING COMPLETE THRU ROOF -- CHECK FLOW CONTROL ON RE-CIRC NEXT INSPECTION | LEE | LEE | | PTO | P | 7142100 |
INTERSTATE MECHANICAL, INC. | PB | P | 09/10/2021 | Underground meat area ok. | DANR | DANR | | PB | P | 7103432 |
INTERSTATE MECHANICAL, INC. | XPS | T | 04/26/2022 | PAID (REC#1869563): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 1 revisions: Adjusted sheet P1.1 and P2. | SHANEN | SHANEN | | XPS | T | 7351802 |
BIBLE ELECTRIC, INC. | XES | T | 03/09/2022 | PAID (REC#1849736): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revise one line. | SHELBY | SHELBY | | XES | T | 7296047 |
TDR CONTRACTORS, INC. | XMS | P | 10/25/2021 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Revised refrigeration drawings and added air curtain | JUSTINC | JUSTINC | | XMS | P | 7152709 |
MARK YOUNG CONSTRUCTION, INC. | XBS | T | 10/22/2021 | PAID (REC#1838657): PLAN SPLICE FEE: $50 by: DANM for Construction: Various revisions throughout architectural and structural | DANM | DANM | | XBS | T | 7152532 |