HENSEL PHELPS CONSTRUCTION CO | B= | C | 03/24/2022 | patch at removed 10" duct OK / building final OK | LONNYS | LONNYS | | B= | C | 7313732 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 11/30/2021 | pending other required inspections / still need to splice in design change for wall heights not continuing to deck / provide fire stop detail for steel plate covering removed 10 duct penetration in temp male locker lobby / rest of above ceiling fire stop OK per Hilti listings on site | LONNYS | LONNYS | | BFR | P | 7191944 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 11/10/2021 | pending other required inspections / attach electric permit / need to splice in changed wall heights / pending splice entire scope of interior light gauge steel framing OK / reviewed rated assemblies and accessibility with site rep // NOTE: will need above ceiling inspection prior to grid ceiling | LONNYS | LONNYS | | BFR | P | 7171966 |
ENCORE ELECTRIC, INC. | E= | C | 12/03/2021 | | RANDY | RANDY | | E= | C | 7197538 |
MECHONE, INC. | H= | C | 02/17/2022 | (TEMP LOCKERS) MECHANICAL FINAL COMPLETE | TREVORH | TREVORH | | H= | C | 7274158 |
MECHONE, INC. | H= | P | 02/17/2022 | TEST AND BALANCE REPORT RECEIVED SEE IMAGES. MECHANICAL FINAL PENDING-------------ON SITE INSPECTION | TREVORH | TREVORH | | H= | P | 7273825 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 12/10/2021 | HEATING WATER FINAL COMPLETE PLAN PAGE M301 (BDA 25) HWS / HWR PIPING : 3/4" HEAT WATER SUPPLY AND RETURN PIPING TO VAV -TB-0-6, TB-0-7 AND TB-0-8 - CIRCUIT SETTERS AND STRAINERS INSTALLED AT VAV'S ./ ALL NEW PIPE UNDER OPERATING PRESSURE NO VISIBLE LEAKS./ NEW PIPING TIE INS TO EXISTING HWS AND HWR PIPING OK / PIPE INSTALLED PER PLAN. | TREVORH | TREVORH | | H= | C | 7205728 |
MECHONE, INC. | H= | P | 12/09/2021 | TEMP LOCKER AREA : VAV-TB-07 AND VAV- TB-08 - SUPPLY GRILLS DUCTED,THEY HAVE BEEN HARD PIPED. PER KEY NOTE M-44 PICTURES HAVE BEEN SENT TO INSPECTOR, ( 2015 IMC code section 607.5.2 (3). 6" EXHAUST DUCT IS NOT PENETRATING THE RATED WALL LIKE IT IS SHOWN ON PLANS. REVISED AND APPROVED PLANS ARE REQUIRED. MEDIUM PRESSURE DUCT TIE INS INTO VAV'S OK / RETURN AND EXHAUST HARD PIPE CONNECTION TO REGISTERS OK / TEMP OFFICE AREA : | TREVORH | TREVORH | | H= | P | 7204080 |
MECHONE, INC. | H= | P | 12/01/2021 | TEMP LOCKER AREA : VAV-TB-07 AND VAV- TB-08 - SUPPLY GRILLS FLEX DUCTED,THEY MUST BE HARD PIPED. SEE KEY NOTE M-44 ( 2015 IMC code section 607.5.2 (3). 6" EXHAUST DUCT IS NOT PENETRATING THE RATED WALL LIKE IT IS SHOWN ON PLANS. REVISED AND APPROVED PLANS ARE REQUIRED. MEDIUM PRESSURE DUCT TIE INS INTO VAV'S OK / RETURN AND EXHAUST HARD PIPE CONNECTION TO REGISTERS OK / TEMP OFFICE AREA : MEDIUM PRESSURE DUCT TIE INS INTO VAV'S OK . SUPPLY GRILLS AND EXHAUST REGISTERS OK /
| LIDO | LIDO | | H= | P | 7194340 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 11/22/2021 | PLAN PAGE M301 (BDA 25) HWS / HWR PIPING : 3/4" HEAT WATER SUPPLY AND RETURN PIPING TO VAV -TB-0-6, TB-0-7 AND TB-0-8 - STILL NEED ISOLATION VALVES AND STRAINERS AT VAV'S ./ ALL NEW PIPE UNDER OPERATING PRESSURE NO VISIBLE LEAKS./ NEW PIPING TIE INS TO EXISTING HWS AND HWR PIPING OK / PIPE INSTALLED PER PLAN. OK TO INSULATE /
| LIDO | LIDO | | HWP | P | 7186243 |
MECHONE, INC. | HD | P | 11/15/2021 | (DUCT ROUGH) SHEET M201 BDA PAGE 24 VAV'S MAIN TRUNK AND LATERAL RUNS OK OK TO WRAP, WILL VERIFY MEDIUM PRESSURE TIE IN AND RETURN AIR AT NEXT INPECTION | TREVORH | TREVORH | | HD | P | 7177040 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 12/23/2021 | PAID (REC#1848049): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised duct routing | JUSTINC | JUSTINC | | XMS | T | 7219771 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 12/07/2021 | PAID (REC#1827675): PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised room numbers | LBENNETT | LBENNETT | | XBS | T | 7199638 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 12/06/2021 | PAID (REC#1827280): PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised non-rated wall types | LBENNETT | LBENNETT | | XBS | T | 7197778 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 12/02/2021 | PAID (REC#1826696): PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised temp office and locker room layouts | LBENNETT | LBENNETT | | XBS | T | 7194747 |
ENCORE ELECTRIC, INC. | XES | T | 11/22/2021 | PAID (REC#1826056): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Minor power revisions. Relocated one receptacle. | BERTHA | BERTHA | | XES | T | 7185898 |
ENCORE ELECTRIC, INC. | XES | T | 11/22/2021 | PAID (REC#1826057): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Minor power revisions. Relocated one receptacle. | BERTHA | BERTHA | | XES | T | 7185500 |