HAMMERS CONSTRUCTION, INC | B= | C | 04/01/2022 | | BOBF | BOBF | | B= | C | 7322510 |
HAMMERS CONSTRUCTION, INC | B= | P | 02/23/2022 | Still need to attach mechanical contractor and have inspection -- Splice for floor plan changes not in permit plan image, Need splice in plan image, reviewed approved splice on site -- Rest of building final OK pending other finals -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): ELECTRIC SERVICE OF COLORADO, LLC Electrical Final Inspection is not Completed yet, MARTINSON MECHANICAL, INC Plumbing Final Inspection is not Completed yet. | DAKOTAB | DAKOTAB | | B= | P | 7279832 |
HAMMERS CONSTRUCTION, INC | BFR | P | 12/28/2021 | Need to attach mechanical to permit and complete associated inspections / Need to revise design to reflect as-built conditions: 1. At laundry area - New 2.5" wall framing installed in front of existing fire-rated assembly not in approved design 2. In west-most office - Observed framing around existing exterior door - Door not in approved design / Observed interior light gauge metal framing / Pending other rough inspections | JEREMYD | JEREMYD | | BFR | P | 7222326 |
ELECTRIC SERVICE OF COLORADO, LLC | EP | C | 02/24/2022 | 50 amp 4/w to panel D sub panel ok | CRAIG | CRAIG | | EP | C | 7281960 |
ELECTRIC SERVICE OF COLORADO, LLC | E= | C | 02/24/2022 | | CRAIG | CRAIG | | E= | C | 7281957 |
ELECTRIC SERVICE OF COLORADO, LLC | ER | P | 12/28/2021 | all walls ok | MATTHEW | MATTHEW | | ER | P | 7222414 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 03/30/2022 | TEST AND BALANCE REPORT RECEIVED. SEE IMAGES. | LIDO | LIDO | | H= | C | 7319342 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 03/29/2022 | TEST AND BALANCE REPORT IS BEING REVIEWED./ | LIDO | LIDO | | H= | P | 7317884 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 03/22/2022 | EF-1 AND EC-1 INTERLOCKS NOT REQUIRED PER SPLICE / ALL CORRECTIONS MADE. SEE IMAGES . FINAL PENDING : NEED TEST AND BALANCE REPORT /
| LIDO | LIDO | | H= | P | 7309814 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 03/07/2022 | SUPPORT 6" FLEX DUCT TO ROOM # 102 / CONTROLS FOR RELOCATED THERMOSTAT IN ROOM # 109 ARE OVER 48" ABOVE THE FLOOR. LOWER THERMOSTAT FOR OK TO INSTALL A LOCK BOX / MULTIPLE ROOMS ARE LACKING 1" UNDERCUT DOORS (for return air path) PER NOTE #3 / NEED TEST AND BALANCE REPORT / 20" X 20" INTAKE ELIMINATED ON SPLICE DATED 3/2/22 / EC-1 / EF-1 AND DUCT INSTALLED PER SPLICE DATED 3/2/22 /. MISSING ALL 12" X 12" TRANSFER AIR / NEED TO INSTALL RELOCATED THERMOSTATS / NEED EF-1 AND EC-1 INTERLOCK VERIFIED WITH INTAKE / RELIEF MOTORIZED DAMPER PER KEY NOTE # 4 BY FINAL / ALL SUPPLY GRILLS INSTALLED / | LIDO | LIDO | | H= | P | 7292855 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 02/24/2022 | NEED TO RESEARCH EQUIPMENT IN ATTIC ACCESS. WILL UPDATED NOTES AFTER / NEED REVISED AND APPROVED PLANS FOR THE FOLLOWING : EC-1 INSTALLED ON THE NORTH WALL OF BUILDING. PLAN SPLICE MUST INCLUDE DUCT SIZES AND ROUTING. ALSO NEED EF-1 DUCT SIZES AND ROUTING . NEED LOCATION OF RELOCATED THERMOSTATS ON SPLICE / UNABLE TO ACCESS EF-1 EXHAUST FAN IN ATTIC SPACE. CONTRACTOR TO PROVIDE SAFE ACCESS FOR INSPECTION. MISSING 20" X 20" INTAKE / RELIEF DUCT INCLUDING MOTORIZED DAMPER. SEE KEY NOTE #4 / PLAN SHOWS NEW RIGID 6" SUPPLY TO ROOM 102, 6" FLEX DUCT WAS INSTALLED / MISSING ALL 12" X 12" TRANSFER AIR / NEED TO INSTALL RELOCATED THERMOSTATS / NEED EF-1 AND EC-1 INTERLOCK VERIFIED WITH INTAKE / RELIEF MOTORIZED DAMPER PER KEY NOTE # 4 BY FINAL / ALL SUPPLY GRILLS INSTALLED / | LIDO | LIDO | | HD | P | 7281423 |
MARTINSON MECHANICAL, INC | P= | C | 03/23/2022 | | TREBORB | TREBORB | | P= | C | 7311268 |
MARTINSON MECHANICAL, INC | P= | P | 03/23/2022 | STILL NEED ENGINEER LETTER FOR DELETION OF HOSE BIBBS; REST OK | TREBORB | TREBORB | | P= | P | 7311023 |
MARTINSON MECHANICAL, INC | P= | P | 03/01/2022 | WILL ACCEPT ENGINEER LETTER OR PLAN SPLICE FOR DELETION OF HOSE BIBBS IN LOOKING AT ATTIC, STILL NEED FREEZE PROTECTION, CAN WE ADD HEAT/VENT IN ATTIC? Photo upload requested. If unfamiliar with uploading photos for an inspection, please click the following link: https://youtu.be/QS0hdGSBA6o / | TREBORB | TREBORB | | P= | P | 7285575 |
MARTINSON MECHANICAL, INC | P= | R | 02/22/2022 | NEED TO SEE HOOK UP OF WATER TO EVAP.COOLER; NEED TRAP GUARD AT HUB DRAIN FOR WATER HEATER; NEED ELECTRIC TO HOT WATER CIRC PUMP; NEED TO COMPLETE INSULATION ON PEX PIPING IN ATTIC; NEED TO SECURE PEX PIPING IN ATTIC; FREEZE PROTECTION FOR WATER PIPING IN ATTIC? NO HOSE BIBBS AS PER PLANS? HOSE BIBBS ARE NOT INSTALLED. REST OK | TREBORB | TREBORB | | P= | R | 7277830 |
MARTINSON MECHANICAL, INC | PTO | C | 12/23/2021 | | TREBORB | TREBORB | | PTO | C | 7219702 |
MARTINSON MECHANICAL, INC | PB | C | 12/01/2021 | DWV OK, WATER OVERHEAD | TREBORB | TREBORB | | PB | C | 7193255 |
PEAK HEATING & AIR CONDITIONING, INC. | XMS | T | 03/17/2022 | PAID (REC#1851859): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Layout revised - Tstat, transfer grills | JUSTINC | JUSTINC | | XMS | T | 7305344 |
PEAK HEATING & AIR CONDITIONING, INC. | XMS | T | 03/02/2022 | PAID (REC#1847838): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Relocated exhaust fan, and Evap cooler locations | JUSTINC | JUSTINC | | XMS | T | 7287541 |
MARTINSON MECHANICAL, INC | XPS | T | 03/01/2022 | PAID (REC#1847469) PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 1 revisions: Adjusted sheet P-2 and P-3. | SHANEN | SHANEN | | XPS | T | 7286121 |
HAMMERS CONSTRUCTION, INC | XBS | T | 01/13/2022 | PAID (REC#1836457): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Revised floor plan | MICHAELA | MICHAELA | | XBS | T | 7237792 |