HENSEL PHELPS CONSTRUCTION CO | B= | C | 06/24/2022 | All other required Final inspections are complete. (This is a computer generated result) | LONNYS | LONNYS | | B= | C | 7425051 |
HENSEL PHELPS CONSTRUCTION CO | B= | P | 04/05/2022 | final OK pending other required inspections. Additional Inspections Required (computer generated): MECH ONE, INC. Mechanical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 7326600 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 03/02/2022 | ABOVE CEILING FIRE STOP // fire stop okay in all areas | LONNYS | LONNYS | | BSP | P | 7287220 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 02/16/2022 | pending other required inspections / still need to inspect above ceiling penetrations at existing 2 hr. fire barrier above ceiling / scope of interior light gauge steel framing OK | LONNYS | LONNYS | | BFR | P | 7272920 |
ENCORE ELECTRIC, INC. | E= | C | 03/23/2022 | | AARONR | AARONR | | E= | C | 7311490 |
ENCORE ELECTRIC, INC. | ER | C | 03/10/2022 | Above ceilings OK. | AARONR | AARONR | | ER | C | 7297137 |
ENCORE ELECTRIC, INC. | ER | P | 02/11/2022 | All walls only - Ok | BRETC | BRETC | | ER | P | 7268452 |
MECHONE, INC. | H= | C | 06/24/2022 | MECHANICAL FINAL COMPLETE | TREVORH | TREVORH | | H= | C | 7425050 |
MECHONE, INC. | H= | P | 04/11/2022 | TEST AND BALANCE REPORT RECEIVED SEE IMAGES MECHANICAL FINAL PENDING----------VERIFY OF THERMOSTAT LOCATION | TREVORH | TREVORH | | H= | P | 7332941 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 03/01/2022 | WATER SOURCE VAV'S COMPLETE. | TREVORH | TREVORH | | H= | C | 7285817 |
OLSON PLUMBING & HEATING COMPANY | HWP | C | 03/01/2022 | PLAN SHEET M202 (BDA) PAGE 31 VAV CIRCUIT SETTERS AND FINAL CONNECTIONS ON OPERATING PRESSURE OK, OK TO INSULATE. | TREVORH | TREVORH | | HWP | C | 7285810 |
MECHONE, INC. | HD | P | 02/25/2022 | VAV 1139 OK 10'' ROUND SUPPLY OK, OK TO WRAP , OK FOR PICTURES OF HIGH SIDE WRAP, AT FINAL TEST AND BALANCE. | TREVORH | TREVORH | | HD | P | 7282751 |
MECHONE, INC. | HD | P | 02/22/2022 | PLAN SHEET M1O2 (BDA) PAGE 30 VAV INSTALL OK, SUPPLY AND RETURN MAINS AND LATERAL RUNS OK,OK TO WRAP . STILL NEED TO SEE COMPLETED 10'' ROUND RETURN AIR TO OFFICE 1130 AND 1131 , NO REGISTERS AT THIS TIME ALL CONNECTIONS MUST BE HARD PIPED . | TREVORH | TREVORH | | HD | P | 7278148 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 03/31/2022 | MATERIAL LETTER ON FILE | LEE | LEE | | P= | C | 7321139 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 03/16/2022 | NEED LETTER -- REST OK | LEE | LEE | | P= | P | 7304536 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 02/22/2022 | under floor dwv ok, water tie in ok, water pipe insulation ok | JOSEPHD | JOSEPHD | | PTO | P | 7277687 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 02/15/2022 | above ceiling and in wall 4 sinks o.k dwv and h2o, need engineers approval for cast iron vent material. still need under floor piping and h2o tie- in. | JOEL | JOEL | | PTO | P | 7271582 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 02/17/2022 | PAID (REC#1844429): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Floor plan clarifications and wall types | SHELLEY | SHELLEY | | XBS | T | 7273905 |
HENSEL PHELPS CONSTRUCTION CO | XMS | P | 02/03/2022 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Added test and balance note | JUSTINC | JUSTINC | | XMS | P | 7258627 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 02/03/2022 | PAID (REC#1841367): PLAN SPLICE FEE: $50 by: MICHAELA for Construction: Additional scope of work. | MICHAELA | MICHAELA | | XBS | T | 7258433 |