MASTER BILT HOMES, INC. | B= | C | 07/08/2022 | unfinished basement | BRIANB | BRIANB | | B= | C | 7440058 |
MASTER BILT HOMES, INC. | BSP | P | 07/01/2022 | Air Leakage Testing report (Blower Door) Per 2015 IECC Section R402.4.1 on file / | JASONL | JASONL | | BSP | P | 7432509 |
MASTER BILT HOMES, INC. | BLA | C | 05/17/2022 | | MATTHEWA | MATTHEWA | | BLA | C | 7379348 |
MASTER BILT HOMES, INC. | BIN | C | 05/05/2022 | Still need to verify attic insulation and basement insulation at final / Observed insulation at protection wall in attic spaces / Reviewed Air Leakage Testing Requirements Per 2015 IECC Section R402.4.1.2 to be Provided by Final Inspection / | JASONL | JASONL | | BIN | C | 7365959 |
MASTER BILT HOMES, INC. | BFR | C | 05/05/2022 | Observed front porch post and lid framing | JASONL | JASONL | | BFR | C | 7365954 |
MASTER BILT HOMES, INC. | BFR | P | 05/03/2022 | Need to glue shims in beam pockets basement / Unfinished basement | JASONL | JASONL | | BFR | P | 7361754 |
MASTER BILT HOMES, INC. | BSP | P | 04/22/2022 | Final approved certificates and test report for materials used in fire protection of floor per IRC 302.13 EX #4 on file / | JASONL | JASONL | | BSP | P | 7348271 |
MASTER BILT HOMES, INC. | BFD | C | 02/10/2022 | Drain is entire to sump pit -- Damp proofing okay | BRIANB | BRIANB | | BFD | C | 7266500 |
MASTER BILT HOMES, INC. | BFN | C | 02/10/2022 | Soils report on file / Open hole on file / Drilled pier observation on file / Foundation wall observation on file, UFER noted / Foundation design on file / Drain required around entire structure per open hole on file -- 5% | JASONL | JASONL | | BFN | C | 7265825 |
MASTER BILT HOMES, INC. | BFT | C | 02/10/2022 | Soils report on file / Open hole on file / Drilled pier observation on file / Foundation wall observation on file, UFER noted / Foundation design on file / Drain required around entire structure per open hole on file -- 5% | JASONL | JASONL | | BFT | C | 7265824 |
MASTER BILT HOMES, INC. | BFT | P | 12/09/2021 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFT | P | 7203536 |
MASTER BILT HOMES, INC. | BFN | P | 12/09/2021 | AUTHORIZED INSPECTION BY ENGINEER | JANE | JANE | JANE | BFN | P | 7203535 |
FIRST RATE ELECTRICAL SERVICES, INC. | E= | C | 06/22/2022 | Correction complete from 6.21.2022 inspection / | ROB | ROB | | E= | C | 7421242 |
FIRST RATE ELECTRICAL SERVICES, INC. | E= | P | 06/21/2022 | Need GFCI protection receptacle with-in 6' from mstr bath sink in mstr bed rm / No A/C pre wire / No appliances at time of inspection | BRETC | BRETC | | E= | P | 7418679 |
FIRST RATE ELECTRICAL SERVICES, INC. | ES | C | 05/02/2022 | Residential Underground: 200-amp 3 Wire New Residence ok to set meter. / | ROB | ROB | | ES | C | 7359861 |
FIRST RATE ELECTRICAL SERVICES, INC. | ER | C | 05/02/2022 | #14 CU to Refer / Irreversible UFER connection / Unfinished Basement / | ROB | ROB | | ER | C | 7359855 |
OAK VIEW INVESTMENTS, LLC | H= | C | 06/21/2022 | Whole house ventilation being achieved with dampered outside air duct to furnace return. / Whole house ventilation switch located at furnace / Note / Unfinished basement with two supplies and one return / Direct vent furnace / Outside air with damper to furnace return / No A/C / | JOSHH | JOSHH | | H= | C | 7418583 |
OAK VIEW INVESTMENTS, LLC | HC | C | 05/02/2022 | RELEASE METER | JONH | JONH | | HC | C | 7359233 |
OAK VIEW INVESTMENTS, LLC | HRR | C | 05/02/2022 | WHOLE HOUSE VENTILATION BEING ACHIEVED WITH DAMPERED OUTSIDE AIR DUCT TO FURNACE RETURN. / VERIFY WHOLE HOUSE VENTILATION SWITCH LOCATION AT FINAL / NOTE /UNFINISHED BASEMENT / / DIRECT VENT FURNACE / OUTSIDE AIR WITH DAMPER TO FURNACE RETURN / | JONH | JONH | | HRR | C | 7359227 |
SPRINGS GAS, INC. | HI | C | 04/22/2022 | 10 LB TEST OK / 1 INCH MAIN / 1 FURNACE / 1 WATER HEATER / 1 RANGE / | JONH | JONH | | HI | C | 7349378 |
JOLLY PLUMBING & HEATING INC. | P= | C | 06/21/2022 | Ok. | DANR | DANR | | P= | C | 7419001 |
JOLLY PLUMBING & HEATING INC. | PTO | C | 04/18/2022 | ok note: 1 vtr / aav at both masters ,powder and up hall lav, aav at fd in basement / unfinished basement | ANTHONYT | ANTHONYT | | PTO | C | 7342090 |
JOLLY PLUMBING & HEATING INC. | PB | C | 03/01/2022 | CORRECTIONS MADE; AAV AT FLOOR DRAIN | TREBORB | TREBORB | | PB | C | 7286725 |
JOLLY PLUMBING & HEATING INC. | PB | R | 02/28/2022 | NEED VENT FOR FLOOR DRAIN; REST OK EXPLAINED VENTING REQUIREMENT TO INSTALLER AT PREVIOUS BASE INSPECTIONS, NONE OF THE FLOOR DRAINS HAVE PROPER VENTING | TREBORB | TREBORB | | PB | R | 7284159 |