T.N. PARKER CONSTRUCTION, LLC | B= | C | 06/01/2022 | All other required Final inspections are complete. (This is a computer generated result) | ADAML | ADAML | | B= | C | 7394706 |
T.N. PARKER CONSTRUCTION, LLC | B= | P | 05/27/2022 | Engineer letter on file for structural steel for RTU's / Complete mechanical final. Additional Inspections Required (computer generated): PEAK HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7391526 |
T.N. PARKER CONSTRUCTION, LLC | B= | P | 05/13/2022 | Pending all other required finals / Provide an observation letter from a 3rd party licensed design professional for structural steel welding at RTU angle iron -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), ELECTRIC SERVICE OF COLORADO, LLC Electrical Final Inspection is not Completed yet, PEAK HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7375719 |
T.N. PARKER CONSTRUCTION, LLC | B= | P | 05/13/2022 | Pending all other required finals / Provide an observation letter from a 3rd party licensed design professional for structural steel welding at RTU angle iron -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), ELECTRIC SERVICE OF COLORADO, LLC Electrical Final Inspection is not Completed yet, PEAK HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7375720 |
ELECTRIC SERVICE OF COLORADO, LLC | E= | C | 05/19/2022 | 45a RTU RK5 fused ok. / | LOGANP | LOGANP | | E= | C | 7381626 |
ELECTRIC SERVICE OF COLORADO, LLC | EP | C | 05/19/2022 | Panel A1 ok. / | LOGANP | LOGANP | | EP | C | 7381619 |
ELECTRIC SERVICE OF COLORADO, LLC | ER | R | 05/12/2022 | Need a complete raceway from bell box in RTU to disconnect and from disconnect to control panel. --- Need to label disconnect. --- No power at service receptacle. --- MCA 31a MOP 45a RK5 fused ok. --- 100-amp 4/w panel A1 ok. --- | LOGANP | LOGANP | | ER | R | 7373545 |
ELECTRIC SERVICE OF COLORADO, LLC | ER | L | 05/11/2022 | Need ladder set up for RTU. --- Need Panels A & A1 accessible for inspection. --- | LOGANP | LOGANP | | ER | L | 7372264 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 06/01/2022 | NOTE / TAB REPORT RECEIVED / | JERRYF | JERRYF | | H= | C | 7394705 |
PEAK HEATING & AIR CONDITIONING, INC. | HSP | C | 05/13/2022 | ENGINEERS LETTER FOR THE CARRIER RTU RECEIVED, SEE IMAGES | BILLS | BILLS | | HSP | C | 7376262 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 05/13/2022 | FINAL PENDING TEST AND BALANCE REPORT. ENGINEERS LETTER FOR THE CARRIER EQUIPMENT RECEIVED UNDER AN HSP INSPECTION REQUEST, SEE IMAGES | BILLS | BILLS | | H= | P | 7376165 |
PEAK HEATING & AIR CONDITIONING, INC. | HSP | C | 05/13/2022 | ENGINEERS LETTER FOR THE CARRIER EQUIPMENT RECEIVED, SEE IMAGES | BILLS | BILLS | | HSP | C | 7376158 |
PEAK HEATING & AIR CONDITIONING, INC. | HSP | P | 01/06/2022 | NEED ENGINEER APPROVED EQUIPMENT SUBMITTAL FOR CARRIER RTU | JERRYF | JERRYF | | HSP | P | 7231161 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 01/05/2022 | AT FINAL VERIFY GRILLES / SECONDARY DRAIN PROTECTION / ECONOMIZER NOTE / ALL SA / RA MAINS AND RUN OUTS / THERMOSTAT ARE COMPLETE / | JERRYF | JERRYF | | HD | P | 7229571 |
PEAK HEATING & AIR CONDITIONING, INC. | HC | C | 01/05/2022 | RELEASE ELEVATED PRESSURE METER FOR ADDED LOAD | JERRYF | JERRYF | | HC | C | 7229561 |
PEAK HEATING & AIR CONDITIONING, INC. | HI | C | 01/05/2022 | VERIFY FINAL CONNECTION AT FINAL NOTE / PRESSURE TEST OK / PIPING PER PLAN | JERRYF | JERRYF | | HI | C | 7229559 |