SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | C | 12/13/2022 | All other required Final inspections are complete. (This is a computer generated result) | NATHAN | NATHAN | | B= | C | 7609214 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 08/30/2022 | . Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), HVAC SOLUTIONS, INC. Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING AND HEATING, INC. Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 7500005 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 06/24/2022 | Items corrected. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), HVAC SOLUTIONS, INC. Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING AND HEATING, INC. Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 7424778 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 06/17/2022 | Provide signage per 2009 ICC A117.1, controls and hand shower at transfer showers not at center line or forward of back wall / complete all final inspections. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), MARQUARDT ELECTRIC, INC Electrical Final Inspection is not Completed yet, HVAC SOLUTIONS, INC. Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 7416316 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 05/23/2022 | 2ND FLOOR RESTROOMS ONLY OKAY with completed required inspections. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), MARQUARDT ELECTRIC, INC Electrical Final Inspection is not Completed yet, CLIMATE SYSTEMS, INC Mechanical Final Inspection is not Completed yet, HVAC SOLUTIONS, INC. Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 7385385 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | B= | P | 05/16/2022 | Final 2nd floor restroom only, need all required MEP inspections completed, locker rooms and remaining areas not ready. -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), MARQUARDT ELECTRIC, INC Electrical Final Inspection is not Completed yet, CLIMATE SYSTEMS, INC Mechanical Final Inspection is not Completed yet, HVAC SOLUTIONS, INC. Mechanical Final Inspection is not Completed yet, NEWCOMER'S PLUMBING & HEATING Plumbing Final Inspection is not Completed yet. | NATHAN | NATHAN | | B= | P | 7377559 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 04/13/2022 | Remaining wall and ceiling framing at 2nd floor with completed required inspections okay / reviewed accessible elements. | NATHAN | NATHAN | | BFR | P | 7336895 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 03/15/2022 | Pending all other required inspections / Level 1 - Ceiling wires OK in Fitness Room / Level 2 - Metal framing OK in Womens restroom / Reviewed accessible clearances at showers | ADAML | ADAML | | BFR | P | 7301514 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BSP | P | 03/11/2022 | Pending all other required inspections - PARTIAL FINAL / Level 1 Restrooms OK on all final items | ADAML | ADAML | | BSP | P | 7298383 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BSP | P | 03/09/2022 | Pending all other required inspections / PARTIAL Final Walk through 1st Level Restrooms ONLY / Restroom 103 Missing braille on restroom sign / Missing pipe protection / Still need to install counter tops / Mirror exceeds 40" max height from finished floor / Restroom 104 - Missing pipe protection and counter tops | ADAML | ADAML | | BSP | P | 7295342 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 02/23/2022 | 2nd Floor framing around electric room 211, beam wrap framing, men's room corridor wall, ceiling framing virtual training room and 1st floor restroom okay with completed required inspections. | NATHAN | NATHAN | | BFR | P | 7280141 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | BFR | P | 02/03/2022 | 1st Framing under and around stairs storage 102, restroom at 1st floor and 2nd floor virtual training structural framing okay with obtained, attached and completed MEP's / Lockers and upper restroom framing remaining. | NATHAN | NATHAN | | BFR | P | 7259291 |
MARQUARDT ELECTRIC, INC | E= | C | 06/20/2022 | ok per pics | BRIAN | BRIAN | | E= | C | 7416639 |
MARQUARDT ELECTRIC, INC | E= | P | 06/16/2022 | need labels on panel / pic upload / rest ok / | BRIAN | BRIAN | | E= | P | 7414689 |
MARQUARDT ELECTRIC, INC | E= | P | 05/17/2022 | 2nd floor bath rooms only,ok/ | JOHNN | JOHNN | | E= | P | 7378742 |
STILSON ELECTRIC SYSTEMS, INC. | E= | C | 04/20/2022 | FIRE ALARM INSPECTION: 2nd floor --ok / | BRIAN | BRIAN | | E= | C | 7346019 |
STILSON ELECTRIC SYSTEMS, INC. | ER | C | 04/20/2022 | FIRE ALARM INSPECTION: 2nd floor --ok / | BRIAN | BRIAN | | ER | C | 7346018 |
MARQUARDT ELECTRIC, INC | ER | C | 04/20/2022 | rest of the walls and hard lid in 2nd floor --ok / grid ceilings--ok / | BRIAN | BRIAN | | ER | C | 7346017 |
STILSON ELECTRIC SYSTEMS, INC. | ER | P | 03/30/2022 | FIRE ALARM INSPECTION: 1st floor only--ok / | BRIAN | BRIAN | | ER | P | 7320397 |
STILSON ELECTRIC SYSTEMS, INC. | ER | P | 03/09/2022 | FIRE ALARM INSPECTION: 1st floor --ok / | BRIAN | BRIAN | | ER | P | 7295593 |
MARQUARDT ELECTRIC, INC | ER | P | 03/07/2022 | 1st floor grid ceiling ok need fire alarm / | BRIAN | BRIAN | | ER | P | 7292105 |
MARQUARDT ELECTRIC, INC | ER | P | 02/18/2022 | west wall see plans / | BRIAN | BRIAN | | ER | P | 7275719 |
HVAC SOLUTIONS, INC. | H= | C | 09/27/2022 | Engineer letter received for thermostat locations and FC-1 - see images | MARKB | MARKB | | H= | C | 7530551 |
HVAC SOLUTIONS, INC. | H= | P | 09/22/2022 | TEST AND BALANCE REPORT RECEIVED - SEE IMAGES | MARKB | MARKB | | H= | P | 7525911 |
HVAC SOLUTIONS, INC. | H= | P | 06/21/2022 | NEED TEST AND BALANCE REPORT / ENGINEER TO ADDRESS: THERMOSTAT LOCATIONS DO NOT MATCH PLANS AND EXISTING FC-1 DOES NOT HAVE DUCT SMOKE DETECTOR PER EQUIPMENT SCHEDULE NOTE 8 | MATTM | MATTM | | H= | P | 7418805 |
CLIMATE SYSTEMS, INC | H= | C | 06/17/2022 | HYDRONIC FINAL OK / | MATTM | MATTM | | H= | C | 7415174 |
CLIMATE SYSTEMS, INC | HWP | P | 05/25/2022 | 4 x 50 PSI PRESSURE TEST ON 2ND HALF OF SUPPLY/RETURN, HEAT/CHILLED PIPING OK TO INSULATE. | MARKB | MARKB | | HWP | P | 7388255 |
CLIMATE SYSTEMS, INC | HWP | R | 05/24/2022 | NO PICTURES ATTACHED TO INSPECTION REQUEST. | MARKB | MARKB | | HWP | R | 7387634 |
HVAC SOLUTIONS, INC. | H= | P | 05/17/2022 | FINAL FOR SECOND FLOOR BATHROOMS ONLY / Still need test and balance and all associated inspections for HVAC / | MATTM | MATTM | | H= | P | 7379220 |
CLIMATE SYSTEMS, INC | HWP | P | 05/10/2022 | NO ON SITE INSPECTION NEEDED - INSPECTION WAS ONLY TO UPLOAD PICTURES | MARKB | MARKB | | HWP | P | 7369942 |
CLIMATE SYSTEMS, INC | HWP | P | 05/10/2022 | 3 X 50 PSI PRESSURE TEST ON CHILLED/HEAT PIPING OVER SHOWER AREA OK
| MARKB | MARKB | | HWP | P | 7369437 |
CLIMATE SYSTEMS, INC | HSP | P | 05/05/2022 | SUPPLY/RETURN, CHILLED/HEAT PIPING TO FAN COIL UNITS ABOVE HARD LID IN SHOWERS OK FOR SUPPORT. No pressure test at this time. HAD DISCUSSION ABOUT CONDENSATE PIPING AND SECONDARY PROTECTION. | MARKB | MARKB | | HSP | P | 7365560 |
HVAC SOLUTIONS, INC. | HD | P | 04/04/2022 | ABOVE CEILING DUCT - SUPPLY/RETURN/EXHAUST/OUTSIDE AIR ROUGH DUCT COMPLETE FOR ROOMS 201, 203, 204, 205, 206, 207, 208 & 210. No diffusers. At Final - will need to see access provided for all volume dampers and fan coil units. PANS SWITCHES INSTALLED UNDER ALL FAN COIL UNITS WITH PUCK SWITCHES. OUTSIDE AIR DUCT INSULATION COMPLETE. | MARKB | MARKB | | HD | P | 7325374 |
HVAC SOLUTIONS, INC. | HD | P | 03/23/2022 | ABOVE CEILING DUCT - 20X14 SA DUCT FROM MENS SHOWER TO EXERCISE ROOM OK TO WRAP(plan sheet M112B). SUPPLY OUTLET DUCT MAINS/BRANCHES FOR FC-3 OK TO WRAP(plan sheet 112). Had discussion with mechanical and general contractors about access and condensate requirements for existing units above new hard lid. | MARKB | MARKB | | HD | P | 7312120 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | C | 09/27/2022 | Engineer Letter For Pluming Needs ( SEE IMAGES ) | TRAVISR | TRAVISR | | P= | C | 7531425 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 06/21/2022 | Need Letter For Point Of Use Water Heater T&P Termination Location / Need Letter For Tie In For DWV @ 1st Floor Closet / Still Waiting On Correct Water Heater | TRAVISR | TRAVISR | | P= | P | 7418633 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 06/17/2022 | Point Of Use Water Heater @ Women's Locker Room Need Letter For T&P Drain Women's Locker Room Lav's Incomplete / Rest OK Janitor Closet @ Men's Restroom Incomplete / Rest OK Still Need To Flow Test Tie-Ins From Second Floor & Letter For Re-Locate Of Tie - In's Mechanical Room Incomplete
| TRAVISR | TRAVISR | | P= | P | 7415907 |
NEWCOMER'S PLUMBING AND HEATING, INC. | P= | P | 05/17/2022 | No Hot Water / Re-Setting Fixtures / No Site Visit Required Will Check When All Is Complete | TRAVISR | TRAVISR | | P= | P | 7378475 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 04/25/2022 | Rooms 207 Mens Showers - DWV & Water @ Wall's & Ceiling OK / Need To Insulate Water / Went Over Accessible With Contractor @ Shower | TRAVISR | TRAVISR | | PTO | P | 7350836 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 04/21/2022 | Room 206 & 207 DWV & Water OK / Went Over Accessible With Contractor / Mop Sink Room DWV OK By Room 206 / Need To Inspect Under Floor
Need To Decide On What To Do With Point Of Use Water Heater /
Point Of Connection For DWV From 2nd Floor To 1st Floor Not In Plans / Need To Speak With Engineer To See Where Connection Will Be & For Plan @ New Point Of Connection
Condensate From HVAC Piped Through 206-207 Wall To Mop Sink | TRAVISR | TRAVISR | | PTO | P | 7347856 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 04/12/2022 | Shower Room 204 Complete / | TRAVISR | TRAVISR | | PTO | P | 7334934 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 04/11/2022 | Need To Insulate All Water / Need To Complete Showers @ Rm 204 / Need To Add Hub Drain To Scope And Get Letter To Reflect Changes For Condensate For Water Heater
Note: Over Head OK Till RM 203 / Water OK Till RM 206 | TRAVISR | TRAVISR | | PTO | P | 7333165 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 03/23/2022 | 1 - restraint required on 4" DWV down from women's water closets (ok to upload image of correction @ next inspection request) OK on DWV hanging base below women's restroom & showers only | FRANKM | FRANKM | | PTO | P | 7312325 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/10/2022 | Consultation on freeze protection of plumbing located in cantilever location | FRANKM | FRANKM | | PTO | P | 7267132 |
NEWCOMER'S PLUMBING AND HEATING, INC. | PTO | P | 02/03/2022 | OK on level 1 in wall DWV & H2O @ mens 103, women's 104 & restroom 102 only (ok to upload images of completed H2O insulation @ next inspection request) Note : existing VTR / wall access panels for shock arrestors & isolation valves | FRANKM | FRANKM | | PTO | P | 7258770 |
CLIMATE SYSTEMS, INC | XMS | T | 06/15/2022 | PAID (REC#1875352): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised to add duct detectors | JUSTINC | JUSTINC | | XMS | T | 7412674 |
NEWCOMER'S PLUMBING AND HEATING, INC. | XPS | T | 05/24/2022 | PAID (REC#1873332): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 0, 3 revisions: Adjusted sheet P001, P112 and P112A. Added sheet P011, P011A and P011.1. | SHANEN | SHANEN | | XPS | T | 7387596 |
MARQUARDT ELECTRIC, INC | XES | T | 04/12/2022 | PAID (REC#1859565): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: As builts | SHELBY | SHELBY | | XES | T | 7334810 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XMS | T | 02/23/2022 | PAID (REC#1848047): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised GRD schedule and layout | JUSTINC | JUSTINC | | XMS | T | 7280631 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XES | T | 01/31/2022 | PAID (REC#1840411) PLAN SPLICE FEE: $50 by: SHELBY for Electrical: Revised roof plan and cooling equipment SCCR | SHELBY | SHELBY | | XES | T | 7256120 |
SAUNDERS NORWOOD CONSTRUCTION, LLC | XMS | P | 01/31/2022 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Layout, schedule and demo revisions. Delta 3 | JUSTINC | JUSTINC | | XMS | P | 7255240 |