INNOVATIVE CONSTRUCTION, INC. | B= | C | 04/13/2022 | All other required Final inspections are complete. (This is a computer generated result) | ADAML | ADAML | | B= | C | 7337676 |
INNOVATIVE CONSTRUCTION, INC. | B= | P | 04/13/2022 | Final items OK pending mechanical. Additional Inspections Required (computer generated): PEAK HEATING & AIR CONDITIONING, INC. Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7337157 |
INNOVATIVE CONSTRUCTION, INC. | BSP | P | 03/23/2022 | Pending all other required inspections / Ceiling grid wires OK | ADAML | ADAML | | BSP | P | 7312204 |
INNOVATIVE CONSTRUCTION, INC. | BFR | P | 03/10/2022 | Attach plumbing and mechanical and complete required inspections / All light gauge metal framing OK / Reviewed accessible elements | ADAML | ADAML | | BFR | P | 7297710 |
INTERMOUNTAIN POWER SERVICES INC | E= | C | 04/05/2022 | | BRETC | BRETC | | E= | C | 7326251 |
INTERMOUNTAIN POWER SERVICES INC | ER | C | 03/25/2022 | Corrections made / Ceilings - Ok / Pictures sent to my phone of corrections | BRETC | BRETC | | ER | C | 7314379 |
INTERMOUNTAIN POWER SERVICES INC | ER | R | 03/24/2022 | I.T. Room strap MC in ceiling - MC strapped 8' from box / Re-lock touching grid / Ko fill box in conference room | BRETC | BRETC | | ER | R | 7313788 |
STILSON ELECTRIC SYSTEMS, INC. | E= | C | 03/18/2022 | FIRE ALARM INSPECTION: | BRETC | BRETC | | E= | C | 7306535 |
STILSON ELECTRIC SYSTEMS, INC. | ER | C | 03/18/2022 | FIRE ALARM INSPECTION: Ceiling FA rough ok, Electric not complete ---------do not close ceiling-------------- / Relock on grid, open j-boxes / | BRETC | BRETC | | ER | C | 7306526 |
INTERMOUNTAIN POWER SERVICES INC | ER | P | 02/28/2022 | Fire alarm contractor to attach to permit / All walls only - Ok / Conference and break rm | BRETC | BRETC | | ER | P | 7283811 |
INTERMOUNTAIN POWER SERVICES INC | ER | P | 02/23/2022 | New walls only - Ok - 150, 151 & IT room | BRETC | BRETC | | ER | P | 7279837 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | C | 04/13/2022 | CORRECTION MADE | MARKB | MARKB | | H= | C | 7337675 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 04/12/2022 | TEST AND BALANCE REPORT RECEIVED - SEE IMAGES | MARKB | MARKB | | H= | P | 7334745 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 04/11/2022 | FINAL PENDING - Balance report not attached to inspection request. TF-1 thermostat is a heating stat instead of a cooling stat required by equipment schedule. DIFFUSERS COMPLETE IN 150 & 151. THERMOSTATS COMPLETE. | MARKB | MARKB | | H= | P | 7334312 |
PEAK HEATING & AIR CONDITIONING, INC. | H= | P | 03/24/2022 | CONTRACTOR TO ADDRESS THE FOLLOWING-- MISSING DIFFUSERS FOR ROOMS #150 & 151, NO THERMOSTATS, TEST AND BALANCE REPORT. Note / All remainder of flex/grills and diffusers ok, TF-1 ok, Transfer grills ok. | PAULO | PAULO | | H= | P | 7314121 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | C | 03/24/2022 | Note / All corrections made from previous notes. | PAULO | PAULO | | HD | C | 7314117 |
PEAK HEATING & AIR CONDITIONING, INC. | HD | P | 03/17/2022 | NOTE ADDED 3/21/22: AFTER DISCUSSION WITH BUILD CONTRACTOR AND FURTHER RESEARCH ON SITE, FIRE DAMPERS WERE OVER SPRAYED PRIOR TO THIS PERMIT. ----ENGINEER TO ADDRESS: 3 Existing fire dampers for transfer in corridor wall have been sprayed with texture and paint. ---- --NEED SUITE NUMBER POSTED FOR FUTURE INSPECTIONS. Plans call for existing CRAC unit to be demo out and all related items. Need to seal or cap all unused holes in existing duct board duct - found 4 but may be more. Cannot run low volt wire through fire damper opening. ABOVE CEILING DUCT - SUPPLY MAINS/BRANCHES FOR ALL VAV'S OK TO WRAP. No flex, diffusers, grills or controls this inspection. | MARKB | MARKB | | HD | P | 7306194 |
CRONEN PLUMBING AND HEATING, INC. | P= | C | 04/08/2022 | correction made verified electronically | JOSEPHD | JOSEPHD | | P= | C | 7332083 |
CRONEN PLUMBING AND HEATING, INC. | P= | P | 04/08/2022 | need p-trap and indirect drain for water heater pan under breakroom sink, rest ok | JOSEPHD | JOSEPHD | | P= | P | 7331865 |
CRONEN PLUMBING AND HEATING, INC. | PTO | C | 03/17/2022 | coffee and ice maker supplies ok | JOSEPHD | JOSEPHD | | PTO | C | 7305900 |
CRONEN PLUMBING AND HEATING, INC. | PTO | P | 03/11/2022 | MISSING COFFEE AND ICE MAKER H20 -- REST OK | LEE | LEE | | PTO | P | 7298896 |
INNOVATIVE CONSTRUCTION, INC. | XMS | T | 02/22/2022 | PAID (REC#1845359): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: NEW BACKGROUND LAYOUT | DALEH | DALEH | | XMS | T | 7277417 |
INTERMOUNTAIN POWER SERVICES INC | XES | T | 02/17/2022 | PAID (REC#1846599): PLAN SPLICE FEE: $50 by: SHELBY for Electrical: As builts | SHELBY | SHELBY | | XES | T | 7275186 |
INNOVATIVE CONSTRUCTION, INC. | XPS | T | 02/17/2022 | PAID (REC#1844476): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 1 revisions: Adjusted sheet P100 and P200. | SHANEN | SHANEN | | XPS | T | 7273969 |
INNOVATIVE CONSTRUCTION, INC. | XBS | T | 02/17/2022 | PAID (REC#1844476): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Floor plan revision. Occupant load increased to 68. | SHELLEY | SHELLEY | | XBS | T | 7273894 |