IICON CONSTRUCTION COLORADO, LLC | B= | C | 08/03/2023 | All other required Final inspections are complete. (This is a computer generated result) | BRIANB | BRIANB | | B= | C | 7816087 |
IICON CONSTRUCTION COLORADO, LLC | BE | P | 02/21/2023 | | SYDNEYB | SYDNEYB | | BE | P | 7665162 |
IICON CONSTRUCTION COLORADO, LLC | B= | P | 08/26/2022 | pending other final inspections. Additional Inspections Required (computer generated): COLORADO MECHANICAL SYSTEMS, LLC Mechanical Final Inspection is not Completed yet, COLORADO MECHANICAL SYSTEMS, LLC Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 7498099 |
IICON CONSTRUCTION COLORADO, LLC | B= | P | 08/25/2022 | corrections from previous inspection are incomplete -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): COLORADO MECHANICAL SYSTEMS, LLC Mechanical Final Inspection is not Completed yet, COLORADO MECHANICAL SYSTEMS, LLC Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 7495865 |
IICON CONSTRUCTION COLORADO, LLC | B= | P | 08/24/2022 | missing all restroom signage / need to complete other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): COLORADO MECHANICAL SYSTEMS, LLC Mechanical Final Inspection is not Completed yet, COLORADO MECHANICAL SYSTEMS, LLC Plumbing Final Inspection is not Completed yet. | BRIANB | BRIANB | | B= | P | 7493801 |
IICON CONSTRUCTION COLORADO, LLC | BSP | P | 07/08/2022 | observed above grid gyp penetrations at smoke partition | BRIANB | BRIANB | | BSP | P | 7439601 |
IICON CONSTRUCTION COLORADO, LLC | BFR | R | 05/24/2022 | HARD LIDS - SOFFITS / Toilet 4203 not ready / have above grid gyp penetrations - gyp incomplete in smoke partition wall clean linen room / observed hard lid - soffit framing | BRIANB | BRIANB | | BFR | R | 7387204 |
IICON CONSTRUCTION COLORADO, LLC | BFR | P | 05/02/2022 | observed interior light gauge wall framing / reviewed accessible elements with superintendent / pending other rough inspections | BRIANB | BRIANB | | BFR | P | 7359616 |
IICON CONSTRUCTION COLORADO, LLC | BSP | P | 04/25/2022 | courtesy inspection / discussed inspection processes and procedures with superintendent and framing rep / discussed smoke partition wall construction | BRIANB | BRIANB | | BSP | P | 7351328 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | C | 08/04/2022 | | AARONR | AARONR | | E= | C | 7471249 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | P | 07/27/2022 | Need GFCI protection on 4 receptacles throughout within 6' of sink. --- Need GFCI protection on water cooler...Will need to be readily accessible. --- Still need to label water heaters in bathroom and provide breaker locks for them...................VAV clearance OK. | AARONR | AARONR | | E= | P | 7462404 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | R | 07/06/2022 | Low volt wire hanging below and on ceiling in various areas. --- Duct work in way of working clearance of VAV in west hallway.............All electrical OK................Will need label on water heaters of panel and circuit numbers with breaker locks in panel due to existing disconnects for water heaters before final. | AARONR | AARONR | | E= | R | 7437093 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | C | 06/27/2022 | FIRE ALARM INSPECTION: | AARONR | AARONR | | E= | C | 7426842 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 06/01/2022 | 5x hard lid rough OK. | AARONR | AARONR | | ER | P | 7395064 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 05/26/2022 | Wall rough by reception window OK. | AARONR | AARONR | | ER | P | 7390470 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 05/13/2022 | All electrical wall rough OK. | AARONR | AARONR | | ER | P | 7376102 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 05/13/2022 | FIRE ALARM INSPECTION: All wall rough OK. | AARONR | AARONR | | ER | P | 7376093 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | R | 05/12/2022 | Need at least one side of walls clear to inspect. Too many areas with walls covered --- Need to verify on medical grade MC spec sheet that bare ground can be wrapped around MC and not cut off. | AARONR | AARONR | | ER | R | 7374431 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | C | 08/03/2023 | STAMPED ENGINEER LETTER RECEIVED APPROVING THE TEST AND BALANCE REPORT.SEE IMAGES. | LIDO | LIDO | | H= | C | 7816086 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | P | 06/23/2023 | REVISED TEST AND BALANCE REPORT REVIEW: REPORT IS MISSING THE NATIONALLY GROUP CERTIFICATION STAMP / FPVAV-411 SUPPLY GRILLS ARE STILL NOT PER THE DESIGN CFM'S. THE READINGS MUST BE WITHIN 10% +/- OF THE DESIGNED CFM'S / ALL RETURN AIR READINGS ARE NOT PER THE DESIGN CFM'S. THE READINGS MUST BE WITHIN 10% +/- OF THE DESIGNED CFM'S / | LIDO | LIDO | | H= | P | 7780342 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | P | 06/22/2023 | test and balance report is being reviewed / | LIDO | LIDO | | H= | P | 7778925 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | P | 02/15/2023 | TEST AND BALANCE REPORT REVIEW: FPVAV-411 SUPPLY GRILL NOT PER THE DESIGN CFM'S AND IS OUTSIDE THE 10% +/- ALLOWED / ALL RETURN AIR READINGS ARE NOT PER THE DESIGN CFM'S AND ARE OUTSIDE THE 10% +/- ALLOWED / MISSING AL EXHAUST AIR READINGS / | LIDO | LIDO | | H= | P | 7662769 |
COLORADO MECHANICAL SYSTEMS, LLC | HSP | P | 02/15/2023 | MISSING THERMOSTATS INSTALLED. SEE IMAGES . | LIDO | LIDO | | HSP | P | 7662653 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | P | 02/06/2023 | UNABLE TO ACCESS ROOMS TO VERIFY THERMOSTAT CENSORS 404, 407 AND 410 / OK TO ATTACH PICTURE OF CORRECTION TO AN INSPECTION REQUEST / SEE NOTES DATED 1/30/23 FOR TEST AND BALANCE REPORT / | LIDO | LIDO | | H= | P | 7654315 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | P | 01/30/2023 | TEST AND BALANCE REPORT MUST HAVE NATIONAL GROUP CERTIFICATION STAMP ON IT BEFORE IT CAN BE REVIEWED / FINAL PENDING : STILL NEED THERMOSTATS. SENSORS AND TEST AND BALANCE REPORT / | LIDO | LIDO | | H= | P | 7647632 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | L | 01/24/2023 | TEST AND BALANCE REPORT IS BEING REVIEWED. | LIDO | LIDO | | H= | L | 7642763 |
COLORADO MECHANICAL SYSTEMS, LLC | H= | P | 07/15/2022 | ALL RELOCATED DUCT HEATERS OK / ALL SUPPLY, RETURN, EXHAUST FLEX DUCT, GRILL AND REGISTERS OK / FINAL PENDING : NEED THERMOSTATS. SENSORS AND TEST AND BALANCE REPORT / | LIDO | LIDO | | H= | P | 7447695 |
COLORADO MECHANICAL SYSTEMS, LLC | HD | P | 07/11/2022 | EXHAUST OK PER PLANS FOR TOILET ROOM 4229, BUT THE SUPPLY DUCT ABOVE DOES NOT MATCH PLANS / NEED TO ADDRESS THE FOLLOWING: EHC 402 does not match approved duct design. plans call for 12X10 duct, but 12 inch round installed. / CAP DEMOED SUPPLY IN ROOM # 4238 / NEED INSTALL INSTRUCTIONS TO INSPECT ALL RELOCATED ELECTRIC DUCT HEATERS (EHC) / REST OF SUPPLY. RETURN AND EXHAUST DUCT ROUGH OK / | LIDO | LIDO | | HD | P | 7441505 |
COLORADO MECHANICAL SYSTEMS, LLC | HD | P | 07/07/2022 | CALLED CONTRACTOR MULTIPLE TIMES WITH NO ANSWER, LEFT VOICE MAIL / CALLED CONTRACTOR WHEN I ARRIVED AT JOB SITE WITH NO ANSWER / WILL NEED CONTRACTOR ON SITE FOR INSPECTION / | LIDO | LIDO | | HD | P | 7438765 |
COLORADO MECHANICAL SYSTEMS, LLC | HD | P | 05/25/2022 | ABOVE CEILING OK FOR TROPHENS AREA (4233), STAFF TOILET (ROOM 4222), TOILET (ROOM 4215 & 4230) / EXHAUST OK PER PLANS FOR TOILET ROOM 4229, BUT THE SUPPLY DUCT ABOVE DOES NOT MATCH PLANS / NEED TO ADDRESS THE FOLLOWING: EHC 402 does not match approved duct design. plans call for 12X10 duct, but 12 inch round installed. / Fire damper wall between Electrical room 404 and Toilet Room 4230 is no longer going to be furred out. | MATTM | MATTM | | HD | P | 7389645 |
COLORADO MECHANICAL SYSTEMS, LLC | P= | C | 09/13/2022 | correction made see image | JOSEPHD | JOSEPHD | | P= | C | 7513983 |
COLORADO MECHANICAL SYSTEMS, LLC | PTO | C | 09/13/2022 | water heater pan run to hub drain | JOSEPHD | JOSEPHD | | PTO | C | 7513982 |
COLORADO MECHANICAL SYSTEMS, LLC | P= | P | 07/26/2022 | Drinking fountain ok. | DANR | DANR | | P= | P | 7460006 |
COLORADO MECHANICAL SYSTEMS, LLC | P= | P | 07/22/2022 | update 7/22/22 hub drain wall box will need to be installed per plans page P500 item 1 & 10 | JOSEPHD | JOSEPHD | | P= | P | 7455824 |
COLORADO MECHANICAL SYSTEMS, LLC | P= | P | 07/21/2022 | drinking fountain lacking knee clearance, will need to conduct more research into hub drain will update notes in morning, rest ok | JOSEPHD | JOSEPHD | | P= | P | 7455171 |
COLORADO MECHANICAL SYSTEMS, LLC | PTO | P | 05/24/2022 | need to see water heater pan drain and hub drain for pan drain competed, rest ok note: at final check water point of connection | JOSEPHD | JOSEPHD | | PTO | P | 7387528 |
COLORADO MECHANICAL SYSTEMS, LLC | PTO | P | 05/20/2022 | not ready | JOSEPHD | JOSEPHD | | PTO | P | 7384182 |
COLORADO MECHANICAL SYSTEMS, LLC | PTO | P | 05/19/2022 | in wall and over head dwv ok | JOSEPHD | JOSEPHD | | PTO | P | 7382712 |
COLORADO MECHANICAL SYSTEMS, LLC | PTO | P | 05/18/2022 | for water piping only, need to see rooms 4228,4230,4232, and drinking fountain, rest of in wall and over head water ok, need to see water pipe insulation, need all in wall and over head dwv | JOSEPHD | JOSEPHD | | PTO | P | 7380718 |
COLORADO MECHANICAL SYSTEMS, LLC | PTO | P | 05/02/2022 | for dwv only, need plans to reflect drinking fountain run to 4" drain near column C not column B, rest of under floor tested and sized per plan, still need all in-wall and overhead completed | JOSEPHD | JOSEPHD | | PTO | P | 7359849 |