WELLS & WEST GENERAL CONTRACTORS, INC. | B= | C | 09/02/2022 | | NATHAN | NATHAN | | B= | C | 7504865 |
WELLS & WEST GENERAL CONTRACTORS, INC. | B= | P | 08/29/2022 | Temp CO: extension ( Expires: 9/28/2022 12:00:00 AM) | NELIDA | NELIDA | | B= | P | 7499648 |
WELLS & WEST GENERAL CONTRACTORS, INC. | B= | P | 08/01/2022 | Temp CO: Pending required inspections ( Expires: 8/31/2022 12:00:00 AM) | AMYP | AMYP | | B= | P | 7466798 |
WELLS & WEST GENERAL CONTRACTORS, INC. | B= | P | 06/16/2022 | Engineer letter on file for structural welding at RTU supports -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), PROCOM ELECTRICAL SERVICES, INC. Electrical Final Inspection is not Completed yet, NIELSEN MECHANICAL CONTRACTORS, LLC Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7413043 |
WELLS & WEST GENERAL CONTRACTORS, INC. | BFR | P | 05/25/2022 | need to attach elec to permit , pending other required inspections, new entry framing at corridor okay | BOBF | BOBF | | BFR | P | 7388460 |
PROCOM ELECTRICAL SERVICES, INC. | E= | C | 08/08/2022 | Splice on one-line and handle ties in panel R3 verified - complete | CHIPO | CHIPO | | E= | C | 7474202 |
PROCOM ELECTRICAL SERVICES, INC. | E= | P | 07/22/2022 | install handle ties in 100A panel R3 / revise one-line and panel to show RTU-1 20A , currently showing 50A / RTUs 1, 2, 3 ok / | MIGUEL | MIGUEL | | E= | P | 7457492 |
PROCOM ELECTRICAL SERVICES, INC. | ER | C | 07/14/2022 | above ceiling ok / | MIGUEL | MIGUEL | | ER | C | 7447157 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 07/08/2022 | FIRE ALARM INSPECTION: fire alarm complete | CHIPO | CHIPO | | E= | C | 7438996 |
SPECIAL SYSTEMS DESIGN,LLC | ER | C | 07/08/2022 | FIRE ALARM INSPECTION: fire alarm complete | CHIPO | CHIPO | | ER | C | 7438994 |
SPECIAL SYSTEMS DESIGN,LLC | E= | C | 07/08/2022 | FIRE ALARM INSPECTION: fire alarm complete | CHIPO | CHIPO | | E= | C | 7438995 |
PROCOM ELECTRICAL SERVICES, INC. | ER | P | 06/30/2022 | Above ceiling okay except where EM lights are going - leave tiles open around EM lights to verify support, and wiring method | CHIPO | CHIPO | | ER | P | 7431105 |
SPECIAL SYSTEMS DESIGN,LLC | E= | P | 05/23/2022 | FIRE ALARM INSPECTION: demo of old system in suit 122--ok / no new installed at this time / | BRIAN | BRIAN | | E= | P | 7385323 |
DRUMMOND PLUMBING LLC | H= | C | 09/01/2022 | 2 PSI SERVICE COMPLETE AND 2 PSI APPROVAL ON FILE FROM CSU. | MARKB | MARKB | | H= | C | 7503753 |
DRUMMOND PLUMBING LLC | HC | C | 08/30/2022 | RELEASE METER TO INCREASE BUILDING TO A 2 PSI SYSTEM | MARKB | MARKB | | HC | C | 7500506 |
DRUMMOND PLUMBING LLC | HI | C | 08/30/2022 | STILL NEED: 2 psi approval letter from CSU. 60 PSI PRESSURE TEST ON EXISTING BUILDING PIPE AND NEW WELDS OK. | MARKB | MARKB | | HI | C | 7500494 |
DRUMMOND PLUMBING LLC | HI | L | 08/29/2022 | PER PLAN SPLICE EXISTING BUILDING GAS PRESSURE WILL BE INCREASED TO MEDIUM PRESSURE. REGULATORS AND MEDIUM PRESSURE LABELS COMPLETE. STILL NEED - 2 psi approval from CSU not on file. Will need a 60 psi pressure test for going to medium pressure and new welded fittings in mechanical room. | MARKB | MARKB | | HI | L | 7499787 |
NIELSEN MECHANICAL CONTRACTORS, LLC | H= | C | 08/08/2022 | CORRECTIONS MADE. TEST AND BALANCE REPORT RECEIVED - SEE IMAGES. | MARKB | MARKB | | H= | C | 7474107 |
DRUMMOND PLUMBING LLC | H= | P | 08/01/2022 | PER CONVERSATION WITH WELLS AND WEST ENGINEER IS ADDRESSING THE MEDIUM PRESSURE GAS PROBLEM. ENGINEER WILL PROVIDE SPLICE WHEN MEDIUM PRESSURE SYSTEM HAS BEEN DESIGNED. WILL NEED GAS INSPECTION WHEN SPLICE HAS BEEN SUBMITTED. ADDED PARTIAL H= SO GENERAL CONTRACTOR CAN GET TCO FOR TENANTS TO START MOVING IN. | NANCY | NANCY | | H= | P | 7466780 |
DRUMMOND PLUMBING LLC | HI | L | 08/01/2022 | Contractor not on site and no approved plan splices found to address previous inspection notes. | MARKB | MARKB | | HI | L | 7466201 |
DRUMMOND PLUMBING LLC | HSP | P | 07/25/2022 | Spoke with engineer by phone and discussed his plan shows existing medium pressure gas but there are no indications on site that this building ever had medium pressure gas. Did walk on site, no appliances in building to include existing RTU, boilers or water heater have line regulators or medium pressure labels. Regulator in front of meter is labeled 8" w.c. Will either RBD approved plan to change over building to medium pressure and CSU approval or RBD approved splice for new gas piping design at low pressure. | MARKB | MARKB | | HSP | P | 7458219 |
DRUMMOND PLUMBING LLC | HI | R | 06/28/2022 | ----ENGINEER TO ADDRESS: Gas plan is designed shows building with existing 2 psi system only: No 2 psi approval on file from CSU for building address, existing meter regulator is rated for 8" w.c., no existing regulators found, no medium pressure labels on existing piping in building and meter location and existing piping size on plans does not mtch current conditions.---- 10 PSI PRESSURE TEST ON NEW 2PSI PIPING INSTALLED PER PLAN OK. | MARKB | MARKB | | HI | R | 7427894 |
NIELSEN MECHANICAL CONTRACTORS, LLC | H= | P | 06/20/2022 | FINAL PENDING-- NEED MECHANICAL (GAS) CONTRACTOR ATTACHED TO PERMIT WITH INSPECTIONS, MISSING ECONOMIZERS TO RTU's 1 & 3, MISSING SECONDARY PROTECTION TO RTU 1 (MAY ATTACH CLEAR PHOTOS TO PERMIT AND RECALL FOR INSPECTION/All clearances for RTU's 1,2 & 3 economizers are and will be met), TEST AND BALANCE REPORT. | PAULO | PAULO | | H= | P | 7417205 |
NIELSEN MECHANICAL CONTRACTORS, LLC | HD | C | 06/20/2022 | ABOVE CEILING DUCT-- All supply/return air duct flex/grills & diffusers for RTU's 1/2 &3 ok / | PAULO | PAULO | | HD | C | 7417196 |
NIELSEN MECHANICAL CONTRACTORS, LLC | HD | P | 05/26/2022 | ABOVE CEILING DUCT - SUPPLY MAINS/BRANCHES INSTALLED PER PLAN FOR RTU'S 1, 2 & 3 OK TO WRAP. No flex diffusers or roof this inspection. | MARKB | MARKB | | HD | P | 7391251 |
DRUMMOND PLUMBING LLC | XMS | T | 08/17/2022 | PAID (REC#1892590): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Gas revision | DALEH | DALEH | | XMS | T | 7486621 |
SPECIAL SYSTEMS DESIGN,LLC | XES | T | 08/02/2022 | PAID (REC#1888660): PLAN SPLICE FEE: $50 by: DANIELG for Electrical: Delta revision 2. As built. | DANIELG | DANIELG | | XES | T | 7467730 |
DRUMMOND PLUMBING LLC | XMS | T | 07/21/2022 | PAID (REC#1885340): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: revised gas | DALEH | DALEH | | XMS | T | 7455184 |