WD CONSULTING LLC | B= | C | 08/11/2022 | | BRIANB | BRIANB | | B= | C | 7479107 |
WD CONSULTING LLC | B= | P | 07/29/2022 | Need to complete roofing - missing drip edge and flashing / Rest of final complete pending other final inspections -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection Z= by ZONING is not Completed yet (Contact: 719-385-5982), EL PASO ELECTRIC, LLC. Electrical Final Inspection is not Completed yet. | JUSTINL | JUSTINL | | B= | P | 7464822 |
WD CONSULTING LLC | BFR | P | 07/25/2022 | Observed bench framing per updated plans on file / Mechanical and plumbing have been removed from scope of work / Need electrical permit attachment and rough inspections / Frame complete pending electrical | JUSTINL | JUSTINL | | BFR | P | 7458470 |
WD CONSULTING LLC | BFT | C | 07/21/2022 | Engineer letter for welding and bolting on file / Open hole observation on file | JUSTINL | JUSTINL | | BFT | C | 7454457 |
WD CONSULTING LLC | BFR | R | 07/20/2022 | No inspection performed - still need to address all items noted in previous BSP 7-13-22 / Attempted to make contract with contractor on site - left VM / Next wasted trip will result in a trip fee | JUSTINL | JUSTINL | | BFR | R | 7452873 |
WD CONSULTING LLC | BSP | P | 07/13/2022 | Changed from BFR to BSP - Inspection request for benches per Detail 7 on sheet 6.1 - Details on file show steel framing - benches framed using wood - Need stamped detail from design professional in order to inspect / Need stamped open hole to complete foundation inspections / Need stamped welding and bolting observations / Reviewed scope of work and permit attachments for MEP / Reviewed handrail requirements - Handrails required when 4 or more risers are installed at steps / Pending other rough inspections | JUSTINL | JUSTINL | | BSP | P | 7444544 |
WD CONSULTING LLC | BFR | P | 07/01/2022 | Still need to stamped open hole to complete foundation inspections / Need stamped 3rd party observations for welding and bolting / Detail 7 framing on sheet on sheet 6.1 incomplete - Rest of framing OK pending other rough inspections / NOTE - Need mechanical - electrical - plumbing permit attachments and inspections | JUSTINL | JUSTINL | | BFR | P | 7433363 |
WD CONSULTING LLC | BFT | P | 06/15/2022 | Observed reinforced foundation per updated foundation design on file / Observed field copy of open hole report on site - 1500 PSF - Provide stamped copy of open hole to complete BFT / pending other rough inspections | JUSTINL | JUSTINL | | BFT | P | 7411999 |
WD CONSULTING LLC | BFT | R | 06/13/2022 | Need open hole report per foundation design on file - Bearing capacity of 1500 PSF required / Foundation at locations (5) and (6) details not reinforced per details - Depths and dimensions of footings per plan / Plans call for (2) interior footings - observed only 1 footing - Updated foundation designs must be submitted to plan review / Observed remaining foundations per plan | JUSTINL | JUSTINL | | BFT | R | 7409015 |
EL PASO ELECTRIC, LLC. | E= | C | 08/01/2022 | Pipe and j-boxes - Ok / Fans are future | BRETC | BRETC | | E= | C | 7466492 |
EL PASO ELECTRIC, LLC. | E= | P | 07/26/2022 | See rough notes | BRETC | BRETC | | E= | P | 7460372 |
EL PASO ELECTRIC, LLC. | ER | P | 07/26/2022 | Not Ready /--------------- Need to install ceiling fans per drawings or resubmit remove with plan review showing future / Splice required, please submit splice for changes in scope. If unfamiliar in submitting electronic splice, please click the following link: https://youtu.be/dG3kHpgDP0w / | BRETC | BRETC | | ER | P | 7460369 |
EL PASO ELECTRIC, LLC. | XES | T | 07/28/2022 | PAID (REC#1887140): PLAN SPLICE FEE: $50 by: DANIELG for Electrical: Revised plans to address inspector's comment. | DANIELG | DANIELG | | XES | T | 7462843 |
WD CONSULTING LLC | XMS | P | 07/22/2022 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Mechanical: Approved removed mechanical scope of work. | TCRIPPEN | TCRIPPEN | | XMS | P | 7456173 |
WD CONSULTING LLC | XPS | P | 07/21/2022 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Clouded revisions: Adjusted sheet P1.1 to remove plumbing scope of work. | SHANEN | SHANEN | | XPS | P | 7454685 |
WD CONSULTING LLC | XBS | T | 07/21/2022 | PAID (REC#1885657): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Wall/bench detail | SHELLEY | SHELLEY | | XBS | T | 7454642 |
WD CONSULTING LLC | XBS | T | 06/10/2022 | PAID (REC#1874145): PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Revised columns | LBENNETT | LBENNETT | | XBS | T | 7407414 |
WD CONSULTING LLC | XES | P | 06/09/2022 | PLAN SPLICE: (No Fee) by: DANIELG for Electrical: As built. | DANIELG | DANIELG | | XES | P | 7405076 |
WD CONSULTING LLC | XBS | T | 06/08/2022 | PAID (REC#1874145): PLAN SPLICE FEE: $50 by: LBENNETT for Construction: Added stairs, revised framing | LBENNETT | LBENNETT | | XBS | T | 7404294 |