COMMERCIAL RESTORATION COMPANY, LLC | B= | C | 09/13/2023 | All other required Final inspections are complete. (This is a computer generated result) | SHAUN | SHAUN | | B= | C | 7854493 |
COMMERCIAL RESTORATION COMPANY, LLC | B= | P | 09/11/2023 | bolt and weld letter received and uploaded in field/ Building final OK pending other finals. Additional Inspections Required (computer generated): ADVANTAGE HEATING AND COOLING Mechanical Final Inspection is not Completed yet. | SHAUN | SHAUN | | B= | P | 7852492 |
COMMERCIAL RESTORATION COMPANY, LLC | BFR | P | 05/16/2023 | Framing has already been completed pending 3rd party letter for structural steel as noted previously | ADAML | ADAML | | BFR | P | 7745043 |
COMMERCIAL RESTORATION COMPANY, LLC | BIN | P | 04/06/2023 | Insulation ok / Still need to complete BFR inspection and correct previous inspectors notes and attach permits / | ERIKK | ERIKK | | BIN | P | 7708629 |
COMMERCIAL RESTORATION COMPANY, LLC | BFR | P | 01/26/2023 | Attach electric and complete required inspections / Provide 3rd party letter for structural steel beams and columns as well as additional footing that is not shown in plans / This is a type 2 construction and there is some existing wood framed construction on partial walls however the framing wasn't damaged and it is not in the scope | ADAML | ADAML | | BFR | P | 7645533 |
COMMERCIAL RESTORATION COMPANY, LLC | BFT | C | 12/09/2022 | 2 pads and reinforcement okay. | NATHAN | NATHAN | | BFT | C | 7606593 |
TRUSTED ELECTRIC | E= | C | 08/03/2023 | Interior remodel/repair complete | CHIPO | CHIPO | | E= | C | 7816275 |
TRUSTED ELECTRIC | ER | C | 08/03/2023 | rough in complete | CHIPO | CHIPO | | ER | C | 7816263 |
TRUSTED ELECTRIC | ES | C | 07/25/2023 | Commercial Service: 200 amp 4 wire commercial service repair from fire - ok to set meter | CHIPO | CHIPO | | ES | C | 7807108 |
TRUSTED ELECTRIC | ESPR | P | 07/18/2023 | Residential Underground: Pre release ok / | ROB | ROB | | ESPR | P | 7800521 |
TRUSTED ELECTRIC | ER | P | 04/20/2023 | walls ok / | BRIAN | BRIAN | | ER | P | 7721596 |
TRUSTED ELECTRIC | ER | R | 04/18/2023 | need the hr's landed into the panel / need the bottom fan to be with in the 12" zone now at 21" AFF / pics ok / | BRIAN | BRIAN | | ER | R | 7719671 |
ADVANTAGE HEATING AND COOLING | H= | C | 09/13/2023 | NOTE / TAB REPORT RECEIVED / SEE IMAGES / | JERRYF | JERRYF | | H= | C | 7854492 |
ADVANTAGE HEATING AND COOLING | H= | P | 09/01/2023 | NEW UNIT HEATER ON WEST SIDE OF BUILDING IS NOT ON SCOPE OF WORK. NO GAS OR VENTING RAN AT THIS TIME. IS THIS FUTURE? PROVIDE TAB REPORT FOR EXHAUST FAN. NOTE / INTERLOCKS ((((OK)))) | NICKE | NICKE | | H= | P | 7845206 |
ADVANTAGE HEATING AND COOLING | HSP | P | 04/25/2023 | HAD CONSULT WITH JON FROM ADVANTAGE ON FURNACE / DUCT / UNIT HEATER REPLACEMENT IN WEST SIDE OF BUILDING (WILL NEED REVISED PLAN SPLICE AND PERMIT FOR THIS WORK - STILL NEED TAB REPORT / INTERLOCKS AT EXHAUST NOTE / EXHAUST FAN HAS BEEN LOWERED TO MEET ELECTRICAL REQUIREMENTS / | JERRYF | JERRYF | | HSP | P | 7725903 |
ADVANTAGE HEATING AND COOLING | HSP | P | 04/19/2023 | SPOKE WITH BUILDING INSPECTOR THE BOTTOM EXHAUST FAN NEEDS TO DRAW WITH IN 12 INCHES OF FLOOR WILL VERIFY AT FINAL | NICKE | NICKE | | HSP | P | 7720281 |
ADVANTAGE HEATING AND COOLING | HD | P | 03/29/2023 | THIS INSPECTION WAS FOR UNIT HEATER, EXHAUST FANS AND MAKEUP AIR LOUVER. FIRE DAMPER ACCESS AND LABELING. ALL ((((((OK)))))). FOR FINAL NEED TO SEE INTER LOCK FOR FANS TO LOUVER FOR MAKEUP AIR. | NICKE | NICKE | | HD | P | 7702075 |
ADVANTAGE HEATING AND COOLING | HV | C | 03/29/2023 | UNIT HEATER VENTING ((((OK)))) | NICKE | NICKE | | HV | C | 7702015 |
REPLUMB SPECIALTIES, INC. | H= | C | 03/22/2023 | NOTE / FINAL CONNECTION IS COMPLETE / | JERRYF | JERRYF | | H= | C | 7694709 |
REPLUMB SPECIALTIES, INC. | HC | C | 03/22/2023 | RELEASE METER | JERRYF | JERRYF | | HC | C | 7694708 |
REPLUMB SPECIALTIES, INC. | HI | C | 03/22/2023 | NOTE / PRESSURE TEST OK / PIPING PER REVISED PLAN DATED 3 / 22 / 23 | JERRYF | JERRYF | | HI | C | 7694706 |
REPLUMB SPECIALTIES, INC. | HI | P | 03/13/2023 | INSTALLATION DOES NOT MATCH ENGINEERED PLAN - BEFORE METER RELEASE WILL NEED 1" LINE TO UNIT HEATER PER PLAN OR NEW APPROVED PLAN SPLICE TO MATCH INSTALLED - IF 1" LINE IS RUN FROM METER WILL NEED NEW PRESSURE TEST - AT THIS TIME UNIT HEATER IS SUPPLIED WITH 1/ 2" FROM 11/4" LINE - STOPPED INSPECTION NOTE / INSPECTION PER BDA PAGE 38 APPROVED SPLICE / | JERRYF | JERRYF | | HI | P | 7685205 |
COMMERCIAL RESTORATION COMPANY, LLC | XES | T | 03/22/2023 | PAID (REC#1941365) PLAN SPLICE FEE: $50 by: DANIELG for Electrical: As built. | DANIELG | DANIELG | | XES | T | 7694458 |
COMMERCIAL RESTORATION COMPANY, LLC | XES | T | 12/20/2022 | PAID (REC#1921995) PLAN SPLICE FEE: $50 by: DANIELG for Electrical: Spliced in electrical plans. | DANIELG | DANIELG | | XES | T | 7616100 |