HENSEL PHELPS CONSTRUCTION CO | B= | C | 11/10/2023 | All other required Final inspections are complete. (This is a computer generated result) | LONNYS | LONNYS | | B= | C | 7914752 |
HENSEL PHELPS CONSTRUCTION CO | B= | P | 11/03/2023 | building final OK pending fire. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), MECHONE, INC. Mechanical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 7909067 |
HENSEL PHELPS CONSTRUCTION CO | B= | P | 10/20/2023 | building final consult only -- reviewed building final required elements with site rep -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), MECHONE, INC. Mechanical Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 7895255 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 10/18/2023 | level 6 west corridor fire barrier penetrations and labeling OK | LONNYS | LONNYS | | BSP | P | 7892282 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 10/13/2023 | 2nd side of west corridor fire barrier gyp attachment OK - still need to inspect penetrations and above ceiling labeling | LONNYS | LONNYS | | BSP | P | 7887003 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 10/12/2023 | west corridor infill wall framing OK
east side of west corridor wall infill 1st and 2nd layer gyp attachment OK per UL U411 - still need to inspect east side attachment, all penetrations and joints | LONNYS | LONNYS | | BSP | P | 7885645 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 10/09/2023 | site visit to review accessible elements with site reps for showers | LONNYS | LONNYS | | BSP | P | 7882369 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 10/04/2023 | Discussed plan splice 9-28-23 and accessible elements of the individual sleep, bathing and toilet compartments. | NATHAN | NATHAN | | BSP | P | 7876469 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 09/28/2023 | 6094- horizontal assembly 2nd and 3rd layer gyp attachment OK | LONNYS | LONNYS | | BSP | P | 7871875 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 09/27/2023 | 6094 horizontal assembly gyp attachment -- 1st layer OK per UL I501 pending other required inspections | LONNYS | LONNYS | | BSP | P | 7870327 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 09/25/2023 | 6094 ceiling framing -- framing OK pending other required inspections - still need to inspect gyp attachment when ready
discussed shower dimensions with site reps for accessibility | LONNYS | LONNYS | | BSP | P | 7867158 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 09/08/2023 | Discussed accessibility, clearances, and grab bar issues in POS toilet and bathing facility roll in shower. | NATHAN | NATHAN | | BSP | P | 7850882 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 09/07/2023 | above grid ceiling corrections OK | LONNYS | LONNYS | | BSP | P | 7850083 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 08/22/2023 | ABOVE CEILING FIRE STOP AND LABELING // missing smoke partition, fire barrier and smoke barrier labeling in several locations / rest of above ceiling OK pending other required inspections | LONNYS | LONNYS | | BSP | P | 7834238 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 07/27/2023 | room 6094 horizontal assembly framing and above ceiling fire stop // framing and firestop OK per UL I501 | LONNYS | LONNYS | | BFR | P | 7810666 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 07/18/2023 | Med gas cabinet fire protection detail per sheet A-506 C3 detail okay corridor C60-55. Smoke barrier closure detail per sheet A-504 detail C6 room 6074A okay. | NATHAN | NATHAN | | BSP | P | 7801289 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 06/22/2023 | site visit to review smoke barrier continuity requirements at exterior wall in 6074A / will need to provide joint detail at termination point | LONNYS | LONNYS | | BSP | P | 7779975 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 06/16/2023 | Above hard lid inspection
Rooms 6053, 6051 and 6095 above hard lid okay pending other inspections. | ERAMIREZ | ERAMIREZ | | BSP | P | 7773769 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 06/12/2023 | corridor 60-54 gyp attachment OK at double doors and wall to 60-74A angle / gyp attachment in electric room 6052 OK / still need to inspect all penetrations when ready | LONNYS | LONNYS | | BSP | P | 7769587 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 06/02/2023 | Gyp attachment at corridor C60-51 and room 6094 okay per V489.
Reviewed with contractor to provide fire stop detail for non-rated med gas box outside of room 6080. Observed fire putty at inlets to box from piping. | ERAMIREZ | ERAMIREZ | | BSP | P | 7761110 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 05/22/2023 | LEVEL 6 - FIRE AND SMOKE BARRIER GYP ATTACHMENT // 6056,6053,6069,6071,6072 -- attachment OK per UL V489 - still need to inspect all penetrations and above ceiling labeling when ready | LONNYS | LONNYS | | BSP | P | 7750426 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 05/15/2023 | LEVEL 6 - GYP ATTACHMENT IN ROOMS 6080,6052,6051,6082 // non rated med gas box outside room 6080 - provide penetration protection detail / still need to inspect back wall in 6051 / still need to inspect corridor corner in 6052 / still need to inspect all penetrations when ready and provide firestop details for all penetrations / rest of attachment OK per UL U465 | LONNYS | LONNYS | | BSP | P | 7743962 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 05/08/2023 | 6051 EVS ROOM GYP ATTACHMENT -- gyp attachment OK - still need to inspect penetrations | LONNYS | LONNYS | | BSP | P | 7738729 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 05/05/2023 | single sided rated assembly framing and core board in fills OK in rooms 6071,6072,6080, and 6094 OK per UL V455
door and wall framing OK at corridor doors 60-54 and 60-56 | LONNYS | LONNYS | | BSP | P | 7737489 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 05/01/2023 | top out gyp attachment over corridor door C60-54 smoke barrier / gyp attachment OK per UL V489 | LONNYS | LONNYS | | BSP | P | 7732303 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 04/21/2023 | Top out of both sides of rated wall between 6070 and 6974, 6974 A per V 489 okay. Door and wall framing between corridor 60-54 and 60-56 not ready. | NATHAN | NATHAN | | BSP | P | 7724142 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 04/04/2023 | Top out screw inspection inside room 6094 okay. | NATHAN | NATHAN | | BSP | P | 7706654 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 03/20/2023 | East and west pod framing inspection. 6050-6077 Screw inspection on east center triangle 1 side top out 694, 2nd side top out 6080, 6052, 6051, 6095, 6082, | NATHAN | NATHAN | | BFR | P | 7691906 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 03/07/2023 | Top out at 6070 equipment alcove side, 6071, 6072, 6056, 6053, 6069 2nd side top out okay. | NATHAN | NATHAN | | BSP | P | 7678889 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 03/02/2023 | prerock above ceiling at corridor 6052 and above doorway at 6052 and 6056 per v489 okay . prerock at equipment alcove at corridor 6058 okay | BOBF | BOBF | | BSP | P | 7674812 |
HENSEL PHELPS CONSTRUCTION CO | BFR | P | 02/28/2023 | Okay to 1 side only, frame and clearances checked rooms 687 - 694, 698 need all completed required inspections and second side inspection. | NATHAN | NATHAN | | BFR | P | 7672202 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 02/24/2023 | Discussed 5th floor inspections that will have separate permit, accessibility and clearances, rated assemblies. | NATHAN | NATHAN | | BSP | P | 7669631 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 02/21/2023 | Drywall at 6082 upper for equipment storage and lower interior of room 652 electric equipment surface mount | NATHAN | NATHAN | | BSP | P | 7665390 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 02/15/2023 | Wall framing and drywall top out of smoke partition and fire barrier at exterior side group of rooms 6053, 6056, 6060, 6069, 6071, 6072 with completed required inspections frame okay. | NATHAN | NATHAN | | BSP | P | 7662587 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 02/10/2023 | Pending all other required inspections /
6th Floor - Electric room 6052 - Framing for walls OK and partial drywall on 3 fire barrier walls per UL U465 interior side only OK so equipment can be moved in / Top of walls still need to have drywall installed | ADAML | ADAML | | BSP | P | 7659187 |
HENSEL PHELPS CONSTRUCTION CO | BSP | P | 02/09/2023 | Obtain, attach and complete electric / reviewed framing, rated assemblies, inspection sequencing, accessibility. | NATHAN | NATHAN | | BSP | P | 7657760 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | C | 10/03/2023 | | BRIAN | BRIAN | | E= | C | 7875348 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | EP | C | 10/03/2023 | new panels--ok / | BRIAN | BRIAN | | EP | C | 7875339 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | P | 09/28/2023 | all areas except elect room/ rest ok / | BRIAN | BRIAN | | E= | P | 7870995 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | E= | C | 09/28/2023 | FIRE ALARM INSPECTION: | BRIAN | BRIAN | | E= | C | 7870994 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 09/21/2023 | FIRE ALARM INSPECTION: same as elect / | BRIAN | BRIAN | | ER | P | 7863498 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 09/21/2023 | grid ceilings marked on plans --ok / nurses station counters--ok / | BRIAN | BRIAN | | ER | P | 7863485 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 09/13/2023 | FIRE ALARM INSPECTION: grid ceilings--see plans | BRIAN | BRIAN | | ER | P | 7855729 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 09/13/2023 | grid ceilings--see plans / | BRIAN | BRIAN | | ER | P | 7855722 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 08/30/2023 | FIRE ALARM INSPECTION: pipe and boxes same rooms as elect / | BRIAN | BRIAN | | ER | P | 7842248 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 08/30/2023 | hard lids ---see plans / | BRIAN | BRIAN | | ER | P | 7842230 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 08/02/2023 | harlids for bathrooms see plans / | BRIAN | BRIAN | | ER | P | 7814887 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 06/06/2023 | FIRE ALARM INSPECTION: pipe and boxes marked on plans --walls only | BRIAN | BRIAN | | ER | P | 7763579 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 06/06/2023 | walls marked on plans / | BRIAN | BRIAN | | ER | P | 7763576 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 05/25/2023 | bathroom hard lids marked on plans / | BRIAN | BRIAN | | ER | P | 7754924 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 04/14/2023 | head walls on 6th floor units /6092--6086--6067--6079--6074---6068--6063--ok | BRIAN | BRIAN | | ER | P | 7716377 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 03/30/2023 | rest of walls --ok / | BRIAN | BRIAN | | ER | P | 7702573 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 03/20/2023 | 6th floor rooms --walls ---see plans / | BRIAN | BRIAN | | ER | P | 7692577 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 03/16/2023 | head walls rooms --6062--6064--6066--6075--6076--6077--6078--6087--6088--6098--6090--ok | BRIAN | BRIAN | | ER | P | 7688750 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | R | 03/15/2023 | please up load pics | BRIAN | BRIAN | | ER | R | 7687520 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | P | 03/07/2023 | 6th floor walls see plans for walls inspected / note will need fire alarm permit / | BRIAN | BRIAN | | ER | P | 7679086 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | ER | R | 03/06/2023 | need to call in right permit this inspection is for the 5th floor / need to identify the power systems / marked on plans | BRIAN | BRIAN | | ER | R | 7677889 |
MECHONE, INC. | H= | C | 11/10/2023 | ENGINEER APPROVED TEST AND BALANCE REPORT RECEIVED - SEE IMAGES | MARKB | MARKB | | H= | C | 7914751 |
MECHONE, INC. | H= | P | 10/03/2023 | FINAL PENDING - Provide test and balance report SPLICE ON FILE FOR CEILING RADIATION DAMPERS | MARKB | MARKB | | H= | P | 7874882 |
MECHONE, INC. | HD | P | 09/26/2023 | ROOM 6094 - CEILING RADIATION DAMPER SUPPORTED PER CONSTRUCTION SPLICE DATED 9/21/23 PAGE A507. Still need mechanical splice showing damper make/model number and statement damper is supported to meet manufacturers instruction. CONTINUE AT OWN RISK | MARKB | MARKB | | HD | P | 7867990 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 09/21/2023 | HYDRONIC PIPING COMPLETE FOR EAST, CENTER AND WEST PODS. | MARKB | MARKB | | H= | C | 7863615 |
MECHONE, INC. | HV | P | 09/11/2023 | THIS INSPECTION WAS FOR FIRE DAMPER IN EAST POD 3 HRS CEILING WITH METAL STUDS. SPOKE WITH CONTRACTOR THEY ARE WAITING ON A DETAIL AND LETTER FROM ENGINEER TO ADDRESS | NICKE | NICKE | | HV | P | 7852728 |
MECHONE, INC. | HD | P | 08/24/2023 | EAST POD - Could not find ceiling radiation damper instruction for metal stud ceiling with 3 hr ceiling. ABOVE CEILING DUCT - SUPPLY/RETURN/EXHAUST FLEX, DIFFUSERS AND GRILLS COMPLETE IN EAST, CENTER AND WEST PODS. | MARKB | MARKB | | HD | P | 7836628 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 08/01/2023 | WEST POD - SUPPLY/RETURN BRANCHES TO EQUIPMENT INCLUDING ROOMS 6072 & 6071 OK TO INSULATE UNDER OPERATING PRESSURE. | MARKB | MARKB | | HWP | P | 7814107 |
MECHONE, INC. | HD | P | 07/31/2023 | NOTE ADDED 8/2/23: Only construction splice on file for new rated ceiling, will need approved mechanical splice for installing ceiling radiation dampers. Either need manufacturers instruction or engineer of record to give instruction or detail how to support crd in steel stud ceiling construction. FURTHER RESEARCH REQUIRED FOR NEW CEILING RADIATION DAMPERS INSTALLED IN 6094 - MORE NOTES TO FOLLOW. | MARKB | MARKB | | HD | P | 7812877 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/28/2023 | CENTER POD SUPPLY/RETURN HYDRONIC PIPING TO VAV'S AND ROOM HEAT PANELS UNDER OPERATING PRESSURE OK TO WRAP. | MARKB | MARKB | | HWP | P | 7811026 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/24/2023 | EAST POD SUPPLY/RETURN HYDRONIC PIPING TO VAV'S AND ROOM HEAT PANELS UNDER OPERATING PRESSURE OK TO WRAP. | MARKB | MARKB | | HWP | P | 7805907 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 07/21/2023 | SUPPLY/RETURN HYDRONIC PIPING MAINS IN ALL 3 PODS OK TO WRAP. UNDER OPERATING PRESSURE. | MARKB | MARKB | | HWP | P | 7805114 |
MECHONE, INC. | HD | P | 04/27/2023 | ABOVE CEILING DUCT - MEDIUM PRESSURE CONNECTIONS TO VAV'S, LOW PRESSURE MAINS/BRANCHES, RETURN AND EXHAUST OK TO WRAP IN WEST POD. No flex or diffusers this inspection. | MARKB | MARKB | | HD | P | 7728746 |
MECHONE, INC. | HD | P | 04/13/2023 | ABOVE CEILING DUCT - MEDIUM PRESSURE CONNECTIONS TO VAV'S, LOW PRESSURE MAINS/BRANCHES, RETURN AND EXHAUST OK TO WRAP IN EAST AND MIDDLE PODS. No flex or diffusers this inspection. | MARKB | MARKB | | HD | P | 7716026 |
MECHONE, INC. | HD | P | 03/21/2023 | ABOVE CEILING DUCT - MEDIUM PRESSURE SUPPLY/RETURN MAINS OK TO WRAP. HIGHLIGHTED ON SHARED PLAN SHEET M206 IN GREEN. | MARKB | MARKB | | HD | P | 7693266 |
MECHONE, INC. | HD | L | 03/17/2023 | FIELD CANCELED - WAITING FOR APPROVED SPLICE | MARKB | MARKB | | HD | L | 7690501 |
MECHONE, INC. | HD | P | 02/22/2023 | --Contractor is working from their own cad drawings that do not match approved plans. EAST POD ONLY ABOVE CEILING DUCT - OK TO WRAP 66X24 & 64X18 DUCT UP TO CENTER POD. | MARKB | MARKB | | HD | P | 7667471 |
OLSON PLUMBING & HEATING COMPANY | P= | C | 10/06/2023 | | CODYP | CODYP | | P= | C | 7880142 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 09/29/2023 | Partial pending plan revision for accessible showers, NOTE/ Rest o.k. | CODYP | CODYP | | P= | P | 7872901 |
OLSON PLUMBING & HEATING COMPANY | P= | P | 09/21/2023 | Need further review on shower stalls, Hand showers out of control zone in rooms 6086 and 6079, Adjust temp on all lavs, showers, and sinks, Need to see back flow preventer at mop sink, NOTE/ Rest o.k. for East and Center pod and both triangle areas | CODYP | CODYP | | P= | P | 7863902 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 07/06/2023 | All under floor dwv o.k./ Still need engineers approval | CODYP | CODYP | | PTO | P | 7790937 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 06/29/2023 | NOTE/ Under floor dwv o.k. for 6065, 6064, 6072, and 6053 | CODYP | CODYP | | PTO | P | 7786274 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 06/27/2023 | NOTE/ Under floor dwv o.k. for 6068 dialysis, 6067, and 6066 just the bathroom | CODYP | CODYP | | PTO | P | 7783618 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 06/23/2023 | Still need approval from engineer as previously stated, NOTE/ Underfloor dwv o.k. for East pod and Center pod/ Toilet flanges o.k. | CODYP | CODYP | | PTO | P | 7780729 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 06/16/2023 | NOTE/ Underfloor dwv o.k. for rooms 6074 and 6068 | CODYP | CODYP | | PTO | P | 7773964 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 06/13/2023 | Still need plan revision or engineer's letter for dialysis lines, NOTE/ Under floor dwv o.k. for rooms 6079, 6078, 6077, 6076, 6075, and 6074 just the sink | CODYP | CODYP | | PTO | P | 7770035 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 06/05/2023 | NOTE/ Vent tie ins o.k./ Storm o.k./ Still need to see insulation, labeling, toilet flanges, and the rest of the underfloor | CODYP | CODYP | | PTO | P | 7762415 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 05/17/2023 | NOTE/ Under floor o.k. for 6088, 6087, 6086, and 6079 | CODYP | CODYP | | PTO | P | 7746589 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 05/10/2023 | NOTE/ All overhead dwv and water lines ok./ Under floor piping o.k. for 6089 and 6090/ Still need toilet flanges secured, insulation and labeling, vent tie in, and storm drains | CODYP | CODYP | | PTO | P | 7740668 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 05/05/2023 | NOTE/ Overhead vents o.k. except West pod | CODYP | CODYP | | PTO | P | 7737006 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 05/03/2023 | NOTE/ Overhead dwv for East pod o.k./ Overhead dwv o.k. for units 6076-6086/ Under floor dwv o.k. for 6092, 6091, and 6090 just the sink | CODYP | CODYP | | PTO | P | 7734279 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 04/12/2023 | NOTE/ Overhead dwv o.k. in units 6074, 75, 76, 77, 78, 79, and 86 | CODYP | CODYP | | PTO | P | 7714313 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 04/10/2023 | NOTE/ Over head water mains o.k. from unit 6092 to 6068/ o.k. to insulate | CODYP | CODYP | | PTO | P | 7711381 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 04/07/2023 | NOTE/ Accessible measurements o.k. for units 6062, 63, 64, 65, 66, and 6067/ In wall dwv and water lines o.k. for rooms 6054 and 6059 | CODYP | CODYP | | PTO | P | 7709881 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 04/06/2023 | ok for dwv / h20 IN WALL only today @ rm#'s nourish 6069A, 6068, 6067, nurse station x2 6061, 6066, 6065, 6064, 6063. and 6062 only today OK TO INSULATE
STILL NEED nail pro and accessible measurements in these areas | JOHNS | JOHNS | | PTO | P | 7708881 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/24/2023 | ok for accessibility measurements and nail protection for all areas noted on 3/23/23 pto ONLY today | JOHNS | JOHNS | | PTO | P | 7697180 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/23/2023 | NOTE/ In wall dwv and water lines o.k. for units 6078, 6077, 6076, 6075, 6074 and just the bathroom in 6068/ Still need accessible measurements, toilet flanges, nail protection, underfloor and over head for these units | CODYP | CODYP | | PTO | P | 7696127 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/14/2023 | Note/ In wall dwv and water lines o.k. for units 6086, 6079, and just the sink in 6078/ Accessibility measurements o.k. for units 6092, 91, 90, 89, 88, 87, 86, 79 minus the toilet flanges | CODYP | CODYP | | PTO | P | 7686754 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/10/2023 | In wall dwv and water lines o.k. for rooms 6092, 6091, 6090, 6089, 6088, 6087, and 6086 just the sink/ Under floor o.k. for rooms 6088 and 6087/ Over head dwv o.k. for these units/ Need to see over head water lines and accessibility measurements for these rooms | CODYP | CODYP | | PTO | P | 7683888 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/06/2023 | NOTE/ Re routed water mains and dwv re routed from 7th floor to 5th floor o.k. | CODYP | CODYP | | PTO | P | 7677431 |
OLSON PLUMBING & HEATING COMPANY | PTO | P | 03/02/2023 | NOTE/ In wall o.k. for rooms 6072, 6069, 6053, 6095, 6057, and 6082 dwv and water lines | CODYP | CODYP | | PTO | P | 7674801 |
HENSEL PHELPS CONSTRUCTION CO | XBS | P | 10/17/2023 | PLAN SPLICE: (No Fee) by: DANM for Construction: Minor revision adding glass film to one door | DANM | DANM | | XBS | P | 7890801 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 10/02/2023 | PAID (REC#1993924): PLAN SPLICE FEE: $50 by: JUSTINL for Construction: Add sheet A602 for clarification of accessibility width at roll in showers. | JUSTINL | JUSTINL | | XBS | T | 7873369 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 09/27/2023 | PAID (REC#1993327): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Added damper location and support details | JUSTINC | JUSTINC | | XMS | T | 7869296 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 09/21/2023 | PAID (REC#1990624): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: ceiling damper framing | SHELLEY | SHELLEY | | XBS | T | 7863314 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 09/13/2023 | PAID (REC#1989900): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Re route duct on 6 th floor | DALEH | DALEH | | XMS | T | 7855106 |
HENSEL PHELPS CONSTRUCTION CO | XBS | P | 09/13/2023 | PLAN SPLICE: (No Fee) by: SHELLEY for Construction: Revised RCP to match electrical, added trim to headwall. | SHELLEY | SHELLEY | | XBS | P | 7854864 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | XES | T | 08/28/2023 | PAID (REC#1983137): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Revised lighting and schedules. | BERTHA | BERTHA | | XES | T | 7840167 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 08/21/2023 | PAID (REC#1980727): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Added two fire dampers | DALEH | DALEH | | XMS | T | 7832082 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 08/21/2023 | PAID (REC#1980445): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Sill clarification | SHELLEY | SHELLEY | | XBS | T | 7832044 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | XES | P | 08/18/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised power and lighting. Revised schedules. | BERTHA | BERTHA | | XES | P | 7831331 |
OLSON PLUMBING & HEATING COMPANY | XPS | P | 07/25/2023 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Revised sheet P001. | SHANEN | SHANEN | | XPS | P | 7807289 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 07/25/2023 | PAID (REC#1973006): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Ceiling details, card reader/PP locations, flooring and finish clarifications. | SHELLEY | SHELLEY | | XBS | T | 7807207 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 07/12/2023 | PAID (REC#1969133): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Smoke barrier termination | SHELLEY | SHELLEY | | XBS | T | 7796283 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 06/16/2023 | PAID (REC#1962802): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Added wall types, minor floor plan revision | SHELLEY | SHELLEY | | XBS | T | 7774856 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 05/03/2023 | PAID (REC#1952085): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Listed ceiling, dimensions, and finish details | SHELLEY | SHELLEY | | XBS | T | 7734760 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | XES | T | 05/02/2023 | PAID (REC#1952042): PLAN SPLICE FEE: $50 by: BERTHA for Electrical: Minor power and lighting revisions. | BERTHA | BERTHA | | XES | T | 7733243 |
OLSON PLUMBING & HEATING COMPANY | XMS | P | 05/02/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical | JUSTINC | JUSTINC | | XMS | P | 7733217 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | XES | P | 04/05/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised lighting. | BERTHA | BERTHA | | XES | P | 7707804 |
OLSON PLUMBING & HEATING COMPANY | XPS | P | 04/03/2023 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Delta 4 revisions: Adjusted sheet P204. | SHANEN | SHANEN | | XPS | P | 7705308 |
GUARANTEE ELECTRICAL CONTRACTING, LLC | XES | P | 03/20/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Revised circuits for plug mold. | BERTHA | BERTHA | | XES | P | 7692357 |
OLSON PLUMBING & HEATING COMPANY | XMS | P | 03/15/2023 | PLAN SPLICE: (No Fee) by: JUSTINC for Mechanical: Layout revisions | JUSTINC | JUSTINC | | XMS | P | 7688210 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 03/14/2023 | PAID (REC#1940373): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Dimension clarifications, shaft wall replacement, and ceiling details. | SHELLEY | SHELLEY | | XBS | T | 7686761 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 02/15/2023 | PAID (REC#1933644): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Revise layout at restroom | SHELLEY | SHELLEY | | XBS | T | 7662239 |
OLSON PLUMBING & HEATING COMPANY | XPS | T | 02/14/2023 | PAID (REC#1936683): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Delta 3 revisions: Adjusted sheet P204, P205, P206, P401 & P501. | SHANEN | SHANEN | | XPS | T | 7661170 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 02/09/2023 | PAID (REC#1933153): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Ceiling heights | SHELLEY | SHELLEY | | XBS | T | 7658271 |
HENSEL PHELPS CONSTRUCTION CO | XES | P | 02/07/2023 | PLAN SPLICE: (No Fee) by: BERTHA for Electrical: Minor power and lighting revisions. | BERTHA | BERTHA | | XES | P | 7655925 |
OLSON PLUMBING & HEATING COMPANY | XPS | P | 01/27/2023 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Delta 2 revisions: Adjusted sheet P204, P205, P206, P401, P501 and P601. | SHANEN | SHANEN | | XPS | P | 7646572 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 01/27/2023 | PAID (REC#1930282): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Equipment locations | SHELLEY | SHELLEY | | XBS | T | 7646451 |
HENSEL PHELPS CONSTRUCTION CO | XBS | T | 01/25/2023 | PAID (REC#1929043): PLAN SPLICE FEE: $50 by: SHELLEY for Construction: Finishes and finish details | SHELLEY | SHELLEY | | XBS | T | 7643607 |