LOEWEN CONSTRUCTION, INC. | BE | P | 08/21/2023 | | JANE | JANE | | BE | P | 7832028 |
FAITH ENTERPRISES INCORPORATED | EE | C | 03/12/2024 | | MATTHEW | MATTHEW | | EE | C | 8021540 |
FAITH ENTERPRISES INCORPORATED | E= | P | 10/10/2023 | Unit heaters - Ok / CUH - 2B1 & 2 / HWUH - SLC - 1, 2, 3 & 4 / HWUHPHB - 1, 2 & 3 / HWUHPHC - 1, 2, 3, 4 & 5 / UH - 1, 2, 3, 4 & 5 | BRETC | BRETC | | E= | P | 7883715 |
FAITH ENTERPRISES INCORPORATED | E= | P | 09/25/2023 | All 20 amp - Ok / FSCH-1, CUH-3 & 6, CH1B- 1, CH1B1 - 2, CH1B - 3, CHSLC-1, CH2A-1, CUH-9, CH3B-1 | BRETC | BRETC | | E= | P | 7866452 |
FAITH ENTERPRISES INCORPORATED | ER | P | 09/22/2023 | HPU-B, 20 amp / HVP-B-1, 20 amp / RO - 1, 25 amp / HVP-B-2, 20 amp / DPHPB, HVP-C & HPU-C ----- Ok | BRETC | BRETC | | ER | P | 7865808 |
FAITH ENTERPRISES INCORPORATED | ER | P | 09/21/2023 | AHU-1 Supply 80 amp fused in controller, AHU-1 Return 35 amp fused in controller / HPU - A / HVPA-1 & 2 / 2 - Resurc pumps / AHU-2 Supply 90 amp fused in controller / AHU-2 Return 60 amp fused in controller | BRETC | BRETC | | ER | P | 7863672 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HE | P | 02/26/2024 | | JACKIEP | JACKIEP | | HE | P | 8006137 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HWP | P | 06/22/2023 | PLAN PAGE 1.51 (BDA 20) AHU-2 / PHA-2: HEAT WATER SUPPLY AND RETURN PIPING UNDER OPERATING PRESSURE OK . NO VISIBLE LEAKS. PIPING INSTALLED PER PLAN. OK TO INSULATE / CHILLED WATER SUPPLY AND RETURN PIPING UNDER OPERATING PRESSURE OK . NO VISIBLE LEAKS. PIPING INSTALLED PER PLAN. OK TO INSULATE / | LIDO | LIDO | | HWP | P | 7779480 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HSP | P | 06/22/2023 | PICTURES OF PLAN PAGE FOR AREA BEING INSPECTED RECEIVED. USED FOR REFERENCE ONLY. SEE IMAGES. | LIDO | LIDO | | HSP | P | 7778867 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | HWP | P | 04/25/2023 | PLAN PAGE 1.51 (BDA 20) AHU-1/ PHA-1: 55LB TEST FOR HEAT WATER SUPPLY AND RETURN PIPING OK. PIPING INSTALLED PER PLAN. OK TO INSULATE / 55LB TEST FOR CHILLED WATER SUPPLY AND RETURN PIPING OK. PIPING INSTALLED PER PLAN. OK TO INSULATE / | LIDO | LIDO | | HWP | P | 7726927 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | P= | C | 09/08/2023 | Corrections complete , one via image | FRANKM | FRANKM | | P= | C | 7850335 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | P= | P | 09/06/2023 | Add 1 - floor sink & 1 - backflow preventer to permit work scope / trap guard required @ floor sink (pic ok for correction) | FRANKM | FRANKM | | P= | P | 7848232 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | PTO | C | 09/06/2023 | OK on DWV & RO water | FRANKM | FRANKM | | PTO | C | 7848228 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | PTO | R | 08/29/2023 | Wrong permit inspection requested per contractor / add 1- floor sink & 1 - RPBFP to permit work scope | FRANKM | FRANKM | | PTO | R | 7841280 |
LOEWEN CONSTRUCTION, INC. | XES | T | 09/08/2023 | PAID (REC#1986376): PLAN SPLICE FEE: $50 by: DANIELG for Electrical: As builts. Added equipment schedule. | DANIELG | DANIELG | | XES | T | 7850687 |
LOEWEN CONSTRUCTION, INC. | XES | T | 09/06/2023 | PAID (REC#1986382): PLAN SPLICE FEE: $50 by: DANIELG for Electrical: As builts. | DANIELG | DANIELG | | XES | T | 7848026 |
MTECH MECHANICAL TECHNOLOGIES GROUP, INC. | XMS | T | 08/28/2023 | PAID (REC#1982908): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Clouds replacing existing exhaust fans | DALEH | DALEH | | XMS | T | 7839828 |