BOTTIN CONSTRUCTION, INC | B= | C | 04/17/2024 | R-19 replaced Final OK Finished basement -- rear covered deck | SHAWND | SHAWND | | B= | C | 8055700 |
BOTTIN CONSTRUCTION, INC | B= | P | 04/15/2024 | Temp CO: needs builidng final ( Expires: 5/15/2024 12:00:00 AM) | JANE | JANE | | B= | P | 8052551 |
BOTTIN CONSTRUCTION, INC | B= | P | 04/15/2024 | Need to provide evaluation or test report to show installation of R19 batt insulation is an acceptable method of fire protection of floor per IRC 302.13 EX #4 / Rest corrected -- Schedule a new Building Final when above items are complete. | TRENTP | TRENTP | | B= | P | 8052384 |
BOTTIN CONSTRUCTION, INC | B= | R | 04/12/2024 | 1.) wire penetrations in garage lid need to be sealed through out 2.) top of garage door in main garage needs to sealed 3.) unfinished room in basement larger then 80 sq ft needs floor system fire protected 4.) unstairs east bedroom missing smoke detector rest of final OK | SHAWND | SHAWND | | B= | R | 8050866 |
BOTTIN CONSTRUCTION, INC | BSP | P | 10/10/2023 | Insulation installation certificate and No burn documentation on file | ANGELW | ANGELW | | BSP | P | 7882774 |
BOTTIN CONSTRUCTION, INC | BIN | C | 10/09/2023 | Provide insulation installation certificate / Air Leakage Testing Requirements Per 2015 IECC Section R402.4.1.2 to be Provided by Final Inspection / UPDATE: 10/10/23 by Angel W. - Insulation installation certificate on file | ANGELW | ANGELW | | BIN | C | 7881925 |
BOTTIN CONSTRUCTION, INC | BFR | C | 10/02/2023 | Note: Finished basement / Engineer details for steel brackets in lieu of beam pockets received on site / | ANGELW | ANGELW | | BFR | C | 7874180 |
BOTTIN CONSTRUCTION, INC | BSP | R | 09/29/2023 | Inspection changed from BFR to BSP. / Inspection stopped due to too many items to list. | MATTHEWA | MATTHEWA | | BSP | R | 7872386 |
BOTTIN CONSTRUCTION, INC | BLA | C | 09/05/2023 | | ANGELW | ANGELW | | BLA | C | 7847154 |
BOTTIN CONSTRUCTION, INC | BSP | P | 07/17/2023 | Portal frames OK / Back deck ceiling insulation OK / Engineer letters for Deck cover beam support and Deck piers received on site / | ANGELW | ANGELW | | BSP | P | 7799628 |
BOTTIN CONSTRUCTION, INC | BSP | P | 07/10/2023 | Portal frames missing interior straps and 3" OC grid pattern / | ANGELW | ANGELW | | BSP | P | 7793152 |
BOTTIN CONSTRUCTION, INC | BFT | C | 06/26/2023 | Soils report received onsite | TRENTP | TRENTP | | BFT | C | 7781772 |
BOTTIN CONSTRUCTION, INC | BSP | P | 06/26/2023 | Rear deck cover posts and lid okay / Need to provide copy of engineer letter viewed onsite for LVL repair for cover beam | TRENTP | TRENTP | | BSP | P | 7781768 |
BOTTIN CONSTRUCTION, INC | BSP | R | 06/09/2023 | Inspection for front porch and rear cover framing / LVL beams at north end of rear cover has been notched and is not bearing at interior per plan / Missing straps for rear cover posts to deck posts below / Front porch cover framing okay, rear cover lid okay | TRENTP | TRENTP | | BSP | R | 7767795 |
BOTTIN CONSTRUCTION, INC | BFI | C | 06/09/2023 | Designer letter for foundation insulation received / Note: Need to complete BFT and BFN | TRENTP | TRENTP | | BFI | C | 7767784 |
BOTTIN CONSTRUCTION, INC | BFD | C | 06/09/2023 | Engineer letter for perimeter drain received -- Damp proofing noted / | TRENTP | TRENTP | | BFD | C | 7767783 |
BOTTIN CONSTRUCTION, INC | BFN | P | 06/09/2023 | Need to complete BFT / Exterior piers not inspected per footing and foundation letters, Need to provide 3rd party observation or request inspection / Engineer letter for foundation received -- Eufer noted / Foundation design in plans (Bearing Capacity Verified) | TRENTP | TRENTP | | BFN | P | 7767779 |
BOTTIN CONSTRUCTION, INC | BFT | P | 06/09/2023 | Need to provide soils report noted on open hole received onsite / open hole received -- 5000 PSF -- usable -- 10% / footing and foundation observation received - ufer noted / foundation design in plans (bearing capacity verified) / Note: Exterior piers not inspected per footing and foundation letters | TRENTP | TRENTP | | BFT | P | 7767776 |
BOTTIN CONSTRUCTION, INC | BFT | P | 03/31/2023 | AUTHORIZED INSPECTION BY ENGINEER | SYDNEYB | SYDNEYB | SYDNEYB | BFT | P | 7704085 |
BOTTIN CONSTRUCTION, INC | BFN | P | 03/31/2023 | AUTHORIZED INSPECTION BY ENGINEER | SYDNEYB | SYDNEYB | SYDNEYB | BFN | P | 7704084 |
LONGHORN ELECTRIC, INC. | E= | C | 04/11/2024 | E= OK ------ 2 - 40 AMP A/C UNITS ------ | GREGM | GREGM | | E= | C | 8049477 |
LONGHORN ELECTRIC, INC. | ES | C | 04/11/2024 | Residential Underground: 2 -150-amp 3 Wire New Residence ok need meter seal. / | GREGM | GREGM | | ES | C | 8049474 |
LONGHORN ELECTRIC, INC. | ES | R | 12/13/2023 | relocate ufer gec to neutral bar | BRET | BRET | | ES | R | 7943736 |
LONGHORN ELECTRIC, INC. | EUG | C | 12/13/2023 | 2/0 urd | BRET | BRET | | EUG | C | 7943734 |
LONGHORN ELECTRIC, INC. | ES | R | 08/29/2023 | service lateral not in | TOMC | TOMC | | ES | R | 7841563 |
LONGHORN ELECTRIC, INC. | ER | C | 08/29/2023 | 2 - 2/0 AL , 1 - # 2 AL , 3 - # 6 AL , 4 - # 10 , irreversible ufer , no mcc , no central vac , finished basement , 2 - sub-panels on lower level , 1 - sub-panel upstairs | TOMC | TOMC | | ER | C | 7841557 |
AIR CONCEPTS HEATING & COOLING | H= | C | 04/12/2024 | CORRECTION MADE, SEE IMAGES / | JONH | JONH | | H= | C | 8050546 |
AIR CONCEPTS HEATING & COOLING | H= | P | 04/10/2024 | INSTALL OVER FLOW SAFETY SWITCH ON UPPER FURNACE COIL/ COMPLETE CONDENSATE ON LOWER FURNACE COIL/ MECHANICAL ROOM LACKS COMBUSTION AIR. WHERE IS THE GAS SHUT OFF FOR FIREPLACE? PROVIDE 2LB APPROVAL LETTER FROM GAS PURVEYOR/ OK TO ATTACH IMAGES TO AN INSPECTION REQUEST. WHOLE HOUSE VENTILATION BEING ACHIEVED THROUGH EXHAUST FAN LOCATED IN POWDER ROOM / WHOLE HOUSE VENTILATION SWITCH LOCATED IN POWDER ROOM / NOTE / DIRECT VENT FURNACE(X3) / NO OUTSIDE AIR TO FURNACE RETURN / A/C COMPLETE(X2) / | JONH | JONH | | H= | P | 8048221 |
ADVANTAGE FIREPLACE & GAS, LLC. | HC | C | 09/28/2023 | RELEASE METER | JONH | JONH | | HC | C | 7870837 |
ADVANTAGE FIREPLACE & GAS, LLC. | HV | C | 09/28/2023 | MAIN LEVEL FIREPLACE CLEARANCE TO COMBUSTIBLES AND VENT TERMINATION OK(x2) / | JONH | JONH | | HV | C | 7870823 |
AIR CONCEPTS HEATING & COOLING | HRR | C | 09/28/2023 | | CASEYM | CASEYM | | HRR | C | 7870646 |
AIR CONCEPTS HEATING & COOLING | HRR | P | 09/27/2023 | PARTIAL PENDING HV INSPECTION CALLED IN/ PROVIDE EQUIPMENT CHANGE FORM BY FINAL/ Whole house ventilation being achieved through exhaust fan located in powder room x 2 / Verify whole house ventilation switch location at final / NOTE / Finished basement / No outside air to furnace return / Direct vent furnace x 3 / A/C rough, coil and lineset. x 2/ | JONH | JONH | | HRR | P | 7869472 |
AIR CONCEPTS HEATING & COOLING | HRP | C | 09/26/2023 | 300lb test ok on upper level lineset, concealed joint over ceiling in basement just outside of mechanical room / | CASEYM | CASEYM | | HRP | C | 7868426 |
AIR CONCEPTS HEATING & COOLING | HRR | T | 09/26/2023 | PAID (REC#1992471): By final provide equipment change letter for both coils (4PXCCU060B installed) / 3 upper level and on lower level fireplaces to be verified by electrical inspector / Need 2lb approval letter by final / Some corrections made, not all / Basement bathroom exhaust termination still within 3' of openable window / B-vent gore broken at elbow on main level / Upper level framing around b-vent will not allow for 1" clearance to combustibles once drywall is installed, remove spray foam insulation at floor / Is range hood 600 or 1200cfms, documentation on-site shows both / seal lineset insulation in multiple locations on main level and in basement / Whole house ventilation being achieved through exhaust fan located in powder room x 2 / Verify whole house ventilation switch location at final / NOTE / Finished basement / No outside air to furnace return / Direct vent furnace x 3 / A/C rough, coil and lineset. x 2/ | CASEYM | CASEYM | | HRR | T | 7868421 |
AIR CONCEPTS HEATING & COOLING | HRR | P | 09/25/2023 | DUCT LEAKAGE REPORT RECEIVED, SEE IMAGES / | JONH | JONH | | HRR | P | 7866111 |
O.M.A.G.M., INC. | HI | C | 09/12/2023 | 10 lb test ok/ 3/4 inch main/(2lb system) 3 FURNACE / 2 FIREPLACE / 2 WATER HEATER / 1 RANGE / 1 BBQ 1/2 INCH STUB OUT GOOD UP TO 67K BTUS/
VERIFY 3 REGULATORS AT FINAL/1 IN MECHANICAL ROOM, 1 IN BASEMENT CEILING TO THE LEFT OF THE BACK DOOR, AND 1 IN 2ND FLOOR MECHANICAL ROOM. PROVIDE 2LB APPROVAL FROM GAS PURVEYOR BY FINAL. | JONH | JONH | | HI | C | 7853516 |
AIR CONCEPTS HEATING & COOLING | HRR | R | 09/11/2023 | Not ready, stopped inspection / Upper and main level inspected / By final provide duct leakage report for upper level system and equipment change letter for upper level coil (4PXCCU060B installed) / Contractor to provide CFMs of kitchen exhaust, not listed on ventilation verification form / 3 x electric fireplaces on upper level to be verified by electrical inspector / Replace all upper level and master bath exhaust ducts, water damaged / B-vent chase framing not complete on upper and main level / Bath exhaust lacks minimum 3' clearance to window on west wall near deck / Missing return on main level bedroom near garage entry / | CASEYM | CASEYM | | HRR | R | 7852566 |
JOLLY PLUMBING & HEATING INC. | P= | C | 03/18/2024 | OK PER PHOTOS ( SEE IMAGES ) | LEE | LEE | | P= | C | 8024228 |
JOLLY PLUMBING & HEATING INC. | P= | P | 03/13/2024 | NEED TO VERIFY AAV AT MAIN LEVEL W-BOX -- EACH W/H TO HAVE COLD ISOLATION VALVE -- NOTES FOR RBD -- NO IRRIGATION STUB | LEE | LEE | | P= | P | 8022982 |
JOLLY PLUMBING & HEATING INC. | P= | P | 03/13/2024 | ENTRY TO ADD POTABLE WATER CERT ( SEE IMAGES ) | LEE | LEE | | P= | P | 8022068 |
JOLLY PLUMBING & HEATING INC. | P= | R | 03/07/2024 | No access (2:11pm - 3:11pm) | FRANKM | FRANKM | | P= | R | 8017796 |
HOMEOWNER | PWO | C | 01/26/2024 | Note: Need certificate of potable water by final. | PATRICKS | PATRICKS | | PWO | C | 7979243 |
JOLLY PLUMBING & HEATING INC. | PTO | C | 09/14/2023 | NEED ALL WATER ENTRY PIPING AT FINAL | LEE | LEE | | PTO | C | 7856957 |
JOLLY PLUMBING & HEATING INC. | PTO | P | 09/13/2023 | LOW TEST UPPER W-BOX DWV -- MAIN FLOOR POWDER HAS DISHWASHER ON WET VENT -- OTHER OK -- NOTES FOR RBD -- NINE VTR -- REQUIRED AAV AT UPPER RIGHT MASTER LAV, POWDER LAV, W-BOX OFF SMALL GARAGE, UTILITY SINK, SINK OFF MASTER BEDROOM, BAR SINK, BOTH BSMT BATH LAVS -- TUB TEMPERING IN VANITYS X-4 -- DRAFT HOOD W-H X-2 | LEE | LEE | | PTO | P | 7855217 |
JOLLY PLUMBING & HEATING INC. | PB | C | 05/03/2023 | | LEE | LEE | | PB | C | 7734267 |
JOLLY PLUMBING & HEATING INC. | PB | P | 05/02/2023 | 25' OF WATER SERVICE COVERED UP -- OTHER OK | LEE | LEE | | PB | P | 7732996 |