MARK YOUNG CONSTRUCTION, LLC | B= | R | 03/13/2024 | letter provided does not have state eng stamp | BOBF | BOBF | | B= | R | 8022327 |
MARK YOUNG CONSTRUCTION, LLC | B= | P | 02/23/2024 | need eng letter for welding, rest of finAL OKAY -- Schedule a new Building Final when above items are complete. | BOBF | BOBF | | B= | P | 8004316 |
MARK YOUNG CONSTRUCTION, LLC | BE | L | 02/22/2024 | | JACKIEP | JACKIEP | | BE | L | 8002400 |
BIBLE ELECTRIC, INC. | E= | C | 11/15/2023 | AHU 1 & 2 125 amp each / (19) RTU's 1-15a, 2-50a, 3-50a, 4-25a, 5-50a, 6-15a, 7-50a, 9-50a, 10-50a, 12-15a, 1325a, 14-50a, 15-20a, 16-15a, 17-50a, 18-20a, 19-15a, 20-15a & 22-15a / 8 EVap Freezers 15 amp each | BRETC | BRETC | | E= | C | 7920205 |
BIBLE ELECTRIC, INC. | E= | L | 11/14/2023 | Need past notes / Not ready per contractor | BRETC | BRETC | | E= | L | 7918331 |
BIBLE ELECTRIC, INC. | ER | P | 09/01/2023 | Need to see nameplates (take picture for next inspection) and brkrs (could not gain access) of Evap coils in 2 freezers wiring - ok / 2 Heat trace circuits will need GFPE protection / Inside 2 freezers - Ok | BRETC | BRETC | | ER | P | 7845824 |
ROCKY MECHANICAL LLC | H= | C | 02/02/2024 | MECHANICAL FINAL OK / | LIDO | LIDO | | H= | C | 7985843 |
ROCKY MECHANICAL LLC | HI | C | 02/02/2024 | CORRECTIONS COMPLETED / | LIDO | LIDO | | HI | C | 7985842 |
ROCKY MECHANICAL LLC | H= | P | 02/02/2024 | PICTURES OF OVERFLOW MONITORING DEVISES INSTALLED RECEIVED. SEE IMAGES. | LIDO | LIDO | | H= | P | 7984926 |
ROCKY MECHANICAL LLC | H= | P | 12/28/2023 | REVISED TEST AND BALANCE REPORT RECEIVED. SEE IMAGES / FINAL PENDING: SEE HI AND HD NOTES DATED 11/3/23 FOR CORRECTIONS THAT ARE STILL NEEDED / | LIDO | LIDO | | H= | P | 7954876 |
ROCKY MECHANICAL LLC | H= | P | 12/15/2023 | TEST AND BALANCE REPORT REVIEW: RTU-4 OUTSIDE AIR IS NOT PER THE DESIGNED CFM'S / FINAL PENDING: SEE HI AND HD NOTES DATED 11/3/23 FOR CORRECTIONS THAT ARE STILL NEEDED / NEED REVISED TEST AND BALANCE REPORT OR ENGINEER TO APPROVE THE READINGS / | LIDO | LIDO | | H= | P | 7945988 |
ROCKY MECHANICAL LLC | HI | P | 11/03/2023 | RTU-1 / RTU-20: MISSING MEDIUM PRESSURE LABELS AHEAD OF REGULATORS / RTU-1, 3, 9, 12 AND AHU-1 MEDIUM PRESSURE LABELS INSTALLED ON THE WRONG SIDE OF THE REGULATORS / | LIDO | LIDO | | HI | P | 7909059 |
ROCKY MECHANICAL LLC | HD | C | 11/03/2023 | ROOF EQUIPMENT INSPECTION: ALL RTU'S AND AHU'S MISSING OVERFLOW MONITORING DEVISES / AHU-1 AND 2: GLUE CONDENSATE PVC DRAIN PIPES / | LIDO | LIDO | | HD | C | 7909053 |
ROCKY MECHANICAL LLC | HI | P | 10/17/2023 | INSTALL MEDIUM PRESSURE LABELS AHEAD OF ALL NEW GAS REGULATORS / NEED REGULATORS AND FINAL GAS CONNECTIONS TO AHU-1, AHU-2 AND RTU-14. (REST OF REGULATORS AND FINAL CONNECTIONS OK) / AHU-1, AHU-2 AND RTU-14 ---10LB TEST OK (this completes all required pressure test) // | LIDO | LIDO | | HI | P | 7890176 |
ROCKY MECHANICAL LLC | HI | P | 10/09/2023 | NEED TO LABEL MEDIUM PRESSURE GAS PIPE / NEED ALL REGULATORS AND FINAL CONNECTION TO ROOF TOP EQUIPMENT / 60LB TEST FOR NEW WELDED GAS MAIN OK. MAIN INSTALLED PER PLAN / RTU-14 LOW TEST/ 10 LB TEST FOR REST OF NEW BRANCH LINE OK /
| LIDO | LIDO | | HI | P | 7882223 |
S&R CONSTRUCTION LLC | P= | R | 10/27/2023 | Wrong permit inspection requested per contractor | FRANKM | FRANKM | | P= | R | 7901607 |
S&R CONSTRUCTION LLC | P= | R | 10/06/2023 | GAS MUST BE CLAIMED BY PROPERLY LICENSED CONTRACTOR. GAS INSPECTION TO BE REQUESTED AS A MECHANICAL (HI) TYPE INSPECTION / | LIDO | LIDO | | P= | R | 7879947 |