GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | C | 12/20/2023 | All other required Final inspections are complete. (This is a computer generated result) | ADAML | ADAML | | B= | C | 7949866 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | B= | P | 11/15/2023 | Final items OK pending all other finals. Additional Inspections Required (computer generated): COLORADO SHEET METAL CO., INC. Mechanical Final Inspection is not Completed yet, OLSON PLUMBING & HEATING COMPANY Mechanical Final Inspection is not Completed yet. | ADAML | ADAML | | B= | P | 7919523 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BSP | P | 09/11/2023 | Drywall OK on both sides of UL U419 wall at UPS room / Complete head of wall and protect all penetrations | ADAML | ADAML | | BSP | P | 7852079 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | BFR | P | 08/02/2023 | Attach mechanical and electrical / Light gauge metal framing OK / Note* Wall around UPS room is a one hour UL U419 which is a USG drywall proprietary listing | ADAML | ADAML | | BFR | P | 7815262 |
ENCORE ELECTRIC, INC. | E= | C | 10/10/2023 | | CRAIGS | CRAIGS | | E= | C | 7883786 |
ENCORE ELECTRIC, INC. | ER | C | 09/28/2023 | walls and above ceiling OK | CRAIGS | CRAIGS | | ER | C | 7871764 |
COLORADO SHEET METAL CO., INC. | H= | C | 12/20/2023 | TEST AND BALANCE REPORT RECEIVED - SEE IMAGES | MARKB | MARKB | | H= | C | 7949865 |
OLSON PLUMBING & HEATING COMPANY | H= | C | 11/30/2023 | BECAUSE ROOM IN USE, PICTURES PROVIDED. | MARKB | MARKB | | H= | C | 7932153 |
COLORADO SHEET METAL CO., INC. | H= | P | 11/21/2023 | FINAL PENDING - Provide test and balance report. SPLICE ON FILE. PERMIT SCOPE CORRECTED. | MARKB | MARKB | | H= | P | 7925372 |
OLSON PLUMBING & HEATING COMPANY | H= | P | 11/14/2023 | FINAL PENDING - Need to see condensate completed to humidifier. CONDENSATE PIPING TO MOP SINK AND MINI-SPLIT OK. | MARKB | MARKB | | H= | P | 7918683 |
COLORADO SHEET METAL CO., INC. | HD | P | 10/10/2023 | ----ENGINEER TO ADDRESS: Diffusers layout does not match approved plan---- FOR FINAL: Correct permit scope - change evap cooler to 1 condenser, 1 air handling unit. Remove 1 vent. Install condensate piping for mini-split. Provide test and balance report. Label condenser on roof. ABOVE CEILING DUCT, FLEX & DIFFUSERS COMPLETE. EXHAUST TERMINATION ON ROOF COMPLETE. | MARKB | MARKB | | HD | P | 7883796 |
COLORADO SHEET METAL CO., INC. | HRP | C | 10/10/2023 | 300 PSI PRESSURE TEST ON CONCEALED LINESET OK. | MARKB | MARKB | | HRP | C | 7883780 |
OLSON PLUMBING & HEATING COMPANY | HWP | P | 09/29/2023 | --NEED MECHANICAL "A" CONTRACTOR ATTACHED TO PERMIT FOR DUCT AND MINI-SPLIT STEAM SUPPLY/RETURN CONDENSATE PIPING FOR HUMIDIFIER OK TO INSULATE. Gravity/pumped condensate not ready at this time. | MARKB | MARKB | | HWP | P | 7873042 |
OLSON PLUMBING & HEATING COMPANY | XMS | T | 11/06/2023 | PAID (REC#2005579): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Revised layout | JUSTINC | JUSTINC | | XMS | T | 7910106 |
ENCORE ELECTRIC, INC. | XES | P | 09/20/2023 | PLAN SPLICE: (No Fee) by: DANIELG for Electrical: As builts. | DANIELG | DANIELG | | XES | P | 7862269 |
GE JOHNSON CONSTRUCTION COMPANY, INC. | XMS | T | 09/19/2023 | PAID (REC#1990261): PLAN SPLICE FEE: $50 by: JUSTINC for Mechanical: Added grill plenum system to cath lab | JUSTINC | JUSTINC | | XMS | T | 7860625 |