THOMAS GENERAL CONTRACTORS, INC. | B= | C | 04/17/2024 | All other required Final inspections are complete. (This is a computer generated result) | LONNYS | LONNYS | | B= | C | 8055228 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 04/11/2024 | building final OK pending other required inspections. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), DRUMMOND PLUMBING LLC Mechanical Final Inspection is not Completed yet, DRUMMOND PLUMBING LLC Plumbing Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 8049549 |
THOMAS GENERAL CONTRACTORS, INC. | BFT | C | 04/11/2024 | engineer letter for footings on file | LONNYS | LONNYS | | BFT | C | 8049166 |
THOMAS GENERAL CONTRACTORS, INC. | B= | P | 04/04/2024 | pending other required inspections / provide footing obs. to complete BFT / missing reduced vertical clearance detection at both sets of risers / west stair wall handrail not returned to wall / rest of building final OK -- Schedule a new Building Final when above items are complete. Additional Inspections Required (computer generated): External Agency Inspection F= by FIREDEPT is not Completed yet (Contact: 385-5982, x2), DRUMMOND PLUMBING LLC Mechanical Final Inspection is not Completed yet, DRUMMOND PLUMBING LLC Plumbing Final Inspection is not Completed yet. | LONNYS | LONNYS | | B= | P | 8042535 |
THOMAS GENERAL CONTRACTORS, INC. | BFR | P | 04/04/2024 | 3rd party structural steel welding and bolting obs. on file | LONNYS | LONNYS | | BFR | P | 8042318 |
THOMAS GENERAL CONTRACTORS, INC. | BFT | P | 04/04/2024 | provide footing pad observations / engineer letter for open hole on file 2500PSF | LONNYS | LONNYS | | BFT | P | 8042317 |
THOMAS GENERAL CONTRACTORS, INC. | BFR | P | 02/13/2024 | framing OK pending other required inspections - reviewed accessible elements with site rep | LONNYS | LONNYS | | BFR | P | 7994343 |
MATRIX ELECTRIC, INC. | E= | C | 03/20/2024 | bathrooms ok / shell only / | MIGUEL | MIGUEL | | E= | C | 8027327 |
MATRIX ELECTRIC, INC. | E= | C | 03/20/2024 | FIRE ALARM INSPECTION: FA ok / | MIGUEL | MIGUEL | | E= | C | 8027324 |
MATRIX ELECTRIC, INC. | E= | C | 03/20/2024 | FIRE ALARM INSPECTION: cable and raceway ok / | MIGUEL | MIGUEL | | E= | C | 8027322 |
MATRIX ELECTRIC, INC. | ER | C | 03/20/2024 | FIRE ALARM INSPECTION: cable and raceway ok / | MIGUEL | MIGUEL | | ER | C | 8027321 |
MATRIX ELECTRIC, INC. | ES | C | 02/14/2024 | Commercial Service: 200 amp 4-w--ok to set meter / | BRIAN | BRIAN | | ES | C | 7996087 |
MATRIX ELECTRIC, INC. | ER | P | 02/13/2024 | roof and bath room walls--ok / | BRIAN | BRIAN | | ER | P | 7994944 |
MATRIX ELECTRIC, INC. | ESPR | P | 02/05/2024 | Commercial Service: Pre release OK | DAVIDRO | DAVIDRO | | ESPR | P | 7987130 |
DRUMMOND PLUMBING LLC | H= | C | 04/16/2024 | CORRECTIONS MADE. | MARKB | MARKB | | H= | C | 8054119 |
DRUMMOND PLUMBING LLC | H= | P | 04/03/2024 | FINAL PENDING - Gas line at rtu missing medium pressure sticker. Need meter labeled with addressed served. REST OK. | MARKB | MARKB | | H= | P | 8041334 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | C | 03/25/2024 | INSULATION SHIELD SIGNED OFF 3/6/24. TAB RECEIVED - SEE IMAGES | MARKB | MARKB | | H= | C | 8031630 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 03/21/2024 | FINAL PENDING - Add rtu's to permit scope. Insulation shield needs to provide 1" clearance to insulation. REST OK. | MARKB | MARKB | | H= | P | 8029551 |
RIAL HEATING AND AIR CONDITIONING, INC. | HV | C | 03/06/2024 | Picture of insulation shield installed and verified via picture sent to inspector / VENT AND TERMINATION OK | MICHAELM | MICHAELM | | HV | C | 8016108 |
RIAL HEATING AND AIR CONDITIONING, INC. | HV | P | 03/06/2024 | INSTALL AN INSULATION SHIELD AT THE ROOF PENETRATION / OK to attach picture of correction to next inspection request | MICHAELM | MICHAELM | | HV | P | 8016077 |
RIAL HEATING AND AIR CONDITIONING, INC. | H= | P | 02/26/2024 | FINAL PENDING - Address cat1 furnace vent. Add 3 RTU'S to permit scope. Complete rtu condensate and secondary switches. Provide test and balance report. OUTSIDE AIR COMPLETE AND EXHAUST FANS/BACK DRAFT DAMPERS ON ROOF COMPLETE. | MARKB | MARKB | | H= | P | 8006246 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | P | 02/20/2024 | --Contractor to correct permit scope - No hoods are shown on plans. ----ENGINEER TO ADDRESS: Furnace was moved per plan but now lacks required service space and cat1 vent horizontal exceeds vertical.---- EXHAUST DUCT COMPLETE. No roof this inspection. | MARKB | MARKB | | HD | P | 8000083 |
RIAL HEATING AND AIR CONDITIONING, INC. | HD | R | 12/01/2023 | WRONG PERMIT NUMBER CALL IN. | MARKB | MARKB | | HD | R | 7933395 |
DRUMMOND PLUMBING LLC | HC | C | 11/14/2023 | RELEASE 2 PSI METER | MARKB | MARKB | | HC | C | 7918443 |
DRUMMOND PLUMBING LLC | HI | C | 11/14/2023 | --Need 2psi approval letter from CSU. 3 x 10 PSI PRESSURE TEST TO RTU'S OK. Still need medium pressure labels and regulators installed. Install address label at meter. | MARKB | MARKB | | HI | C | 7918435 |
DRUMMOND PLUMBING LLC | P= | C | 04/17/2024 | Correction Made | TRAVISR | TRAVISR | | P= | C | 8055227 |
DRUMMOND PLUMBING LLC | P= | R | 04/16/2024 | Did not request attached letter | CODYP | CODYP | | P= | R | 8053537 |
DRUMMOND PLUMBING LLC | P= | P | 04/03/2024 | Need access to mixing valves at all lavs, Need to adjust temp on all lavs, Need to correct scope of work, Need plan revision for water piping, NOTE/ Rest ok | CODYP | CODYP | | P= | P | 8041394 |
DRUMMOND PLUMBING LLC | P= | L | 03/27/2024 | Field canceled by contractor | CODYP | CODYP | | P= | L | 8034388 |
DRUMMOND PLUMBING LLC | P= | P | 03/20/2024 | In Response To Proposed Panel -
ACCESS PANEL WILL NEED TO HAVE A LOUVER DOOR FOR AIR FLOW | TRAVISR | TRAVISR | | P= | P | 8027114 |
DRUMMOND PLUMBING LLC | PTO | P | 02/21/2024 | VTR @ 2nd Level & H20 Complete
Need Flanges & Plans Revised For H20 | TRAVISR | TRAVISR | | PTO | P | 8001988 |
DRUMMOND PLUMBING LLC | PTO | P | 02/14/2024 | Need to pipe water lines per plan or revise drawings to show all changes to water piping size and routing, Need to see insulation on all hot water piping, Install and secure all toilet flanges, Correct scope of work by final, NOTE/ Rest ok for in wall and overhead dwv and water lines | CODYP | CODYP | | PTO | P | 7996042 |
DRUMMOND PLUMBING LLC | PB | C | 01/16/2024 | Underground DWV @ Mens Room OK / Tenant To Finish | TRAVISR | TRAVISR | | PB | C | 7968734 |
DRUMMOND PLUMBING LLC | PB | P | 01/11/2024 | Underground Grease Waste Up To Halfway Between Bathroom Groups OK Future Stack Upstairs OK | TRAVISR | TRAVISR | | PB | P | 7966226 |
DRUMMOND PLUMBING LLC | PB | P | 01/08/2024 | Under Ground Grease Waste OK Splice In OK
Need To Correct Scope Of Work By Final To Reflect All Work Being Performed | TRAVISR | TRAVISR | | PB | P | 7962398 |
DRUMMOND PLUMBING LLC | PB | P | 01/05/2024 | Per conversation with contractor this morning: No new plans are uploaded in the system for the added grease trap and associated piping / Inspector did see piping on test yesterday and has picture of installed piping. Will need to verify installed Grease trap is installed per manufacturer and matches per drawings - will need installation instructions and model number on pit. | DANR | DANR | | PB | P | 7960567 |
DRUMMOND PLUMBING LLC | PB | R | 01/04/2024 | Re-inspect all / the drawing s do not show any grease waste or grease trap / need plans / piping was on test / need to claim grease trap on scope of work. | DANR | DANR | | PB | R | 7959392 |
DRUMMOND PLUMBING LLC | PB | P | 12/29/2023 | 4" DWV Stub & Tie In @ Men's Restroom OK | TRAVISR | TRAVISR | | PB | P | 7956005 |
DRUMMOND PLUMBING LLC | PB | P | 11/17/2023 | Under Ground DWV @ Women OK | TRAVISR | TRAVISR | | PB | P | 7921873 |
DRUMMOND PLUMBING LLC | XPS | T | 04/12/2024 | PAID (REC#2052695): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Revised sheet P1.1 and P1.2. | SHANEN | SHANEN | | XPS | T | 8050673 |
RIAL HEATING AND AIR CONDITIONING, INC. | XMS | T | 01/26/2024 | PAID (REC#2029534): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: Clouds | DALEH | DALEH | | XMS | T | 7978669 |
THOMAS GENERAL CONTRACTORS, INC. | XES | T | 01/17/2024 | PAID (REC#2029534): PLAN SPLICE FEE: $50 by: DANIELG for Electrical: Added rooftop receptacle. | DANIELG | DANIELG | | XES | T | 7969640 |
DRUMMOND PLUMBING LLC | XPS | T | 01/05/2024 | PAID (REC#2021904): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Revised sheet P0.1, P1.1, P1.2, P1.3 and P1.4. | SHANEN | SHANEN | | XPS | T | 7960451 |
RIAL HEATING AND AIR CONDITIONING, INC. | XMS | T | 11/20/2023 | PAID (REC#2011561): PLAN SPLICE FEE: $50 by: DALEH for Mechanical: See Engineers and plan review applied clouds for approval | DALEH | DALEH | | XMS | T | 7924105 |
THOMAS GENERAL CONTRACTORS, INC. | XBS | T | 11/20/2023 | PAID (REC#2011561): PLAN SPLICE FEE: $50 by: DANM for Construction: Architectural revisions throughout | DANM | DANM | | XBS | T | 7924007 |