CASCO ENTERPRISES, INC. | B= | C | 04/17/2024 | All other required Final inspections are complete. (This is a computer generated result) | MATTHEWA | MATTHEWA | | B= | C | 8054848 |
CASCO ENTERPRISES, INC. | BEN= | C | 04/12/2024 | Energy compliance not required. | MATTHEWA | MATTHEWA | | BEN= | C | 8050847 |
CASCO ENTERPRISES, INC. | B= | P | 04/12/2024 | Pending other finals. / Building final okay. Additional Inspections Required (computer generated): MICK HEATING & SHEET METAL CO. Mechanical Final Inspection is not Completed yet, Building Energy Final is not Completed yet. | MATTHEWA | MATTHEWA | | B= | P | 8050845 |
CASCO ENTERPRISES, INC. | BSP | P | 03/19/2024 | Letter from fire department on file. | MATTHEWA | MATTHEWA | | BSP | P | 8025700 |
CASCO ENTERPRISES, INC. | BFR | P | 03/05/2024 | Observed interior light gauge metal framing. / Pending other roughs. / Reviewed accessible elements with Casco rep on-site. | MATTHEWA | MATTHEWA | | BFR | P | 8014178 |
MEYER ELECTRIC | E= | C | 04/11/2024 | E= - OK / | DAVIDRO | DAVIDRO | | E= | C | 8049713 |
MEYER ELECTRIC | ER | C | 04/11/2024 | Reception room and Bay above ceiling - OK / No other rough needed / | DAVIDRO | DAVIDRO | | ER | C | 8049703 |
MEYER ELECTRIC | ER | P | 04/02/2024 | IT room Rough - OK / | DAVIDRO | DAVIDRO | | ER | P | 8039825 |
MEYER ELECTRIC | ER | P | 02/29/2024 | Rough complete - Hard lid - OK / | DAVIDRO | DAVIDRO | | ER | P | 8010336 |
MEYER ELECTRIC | ER | P | 02/22/2024 | Rough in for new framed walls only ok | CHIPO | CHIPO | | ER | P | 8003161 |
MICK HEATING & SHEET METAL CO. | H= | C | 04/17/2024 | NOTE / TAB REPORT RECEIVED / SEE IMAGES / | JERRYF | JERRYF | | H= | C | 8054847 |
MICK HEATING & SHEET METAL CO. | H= | P | 04/10/2024 | PARTIAL PENDING TAB REPORT NOTE / ALL SA / RA / EXHAUST / GRILLES / CONTROLS / UNIT HEATER VENTING ((OK)) / | JERRYF | JERRYF | | H= | P | 8048768 |
NMECH LLC | H= | C | 04/09/2024 | FINAL FOR GAS CONTRACTOR | BILLS | BILLS | | H= | C | 8047557 |
NMECH LLC | HI | C | 04/09/2024 | ALL NEW CONNECTIONS TO UNIT HEATER AND HOTSY MACHINE TIFFED OK. | BILLS | BILLS | | HI | C | 8047549 |
MICK HEATING & SHEET METAL CO. | HD | P | 04/02/2024 | THIS INSPECTION FOR BDA PAGE #41 (SPLICE),, PLAN PAGE M111--- I.T. ROOM #107-A EXHAUST FAN OK. | BILLS | BILLS | | HD | P | 8040545 |
MICK HEATING & SHEET METAL CO. | HD | P | 03/05/2024 | THIS INSPECTION FOR BDA PAGE #41 (SPLICE),, PLAN PAGE M111--- ABOVE HARD-LID AT BATHROOM- SUPPLY AIR PIPING AND FLEX, EXHAUST AIR FAN AND FLEX ALL OK. OK TO WRAP. OK TO COVER AS PER MECHANICAL ONLY. | BILLS | BILLS | | HD | P | 8015058 |
MICK HEATING & SHEET METAL CO. | HD | P | 02/28/2024 | NEED GAS CONTRACTOR ATTACHED TO PERMIT. BY FINAL: NEED PLAN REVISION SHOWING ACTUAL LOCATION OF THE HOTSY VENTING. THIS INSPECTION FOR BDA PAGE #41 (SPLICE),, PLAN PAGE M111--- NEW VENTING FOR EXISTING HOTSY MACHINE IN NEW LOCATION OK. | BILLS | BILLS | | HD | P | 8009270 |
SOCO PLUMBING | P= | C | 04/10/2024 | | TAYLOR | TAYLOR | | P= | C | 8047889 |
SOCO PLUMBING | PTO | C | 04/10/2024 | | TAYLOR | TAYLOR | | PTO | C | 8047887 |
SOCO PLUMBING | P= | P | 04/08/2024 | engineers letter ok ( see images ). | TAYLOR | TAYLOR | | P= | P | 8046231 |
SOCO PLUMBING | P= | P | 04/05/2024 | still need to correct scope of work and engineers approval for PVC in return plenum, missing plenum wrap above ceiling, note: revised plans ok. | TAYLOR | TAYLOR | | P= | P | 8044068 |
SOCO PLUMBING | PTO | P | 02/27/2024 | need engineers approval for PVC in return air plenum, revise plans for 1 inch POC to supply restroom/ equipment at wash bay, test ok, note: check VTR, point of use water heater, backflow protection at final. | TAYLOR | TAYLOR | | PTO | P | 8007458 |
SOCO PLUMBING | PB | C | 02/16/2024 | add electric water heater and trench drain to scope of work by final. | TAYLOR | TAYLOR | | PB | C | 7998002 |
MICK HEATING & SHEET METAL CO. | XMS | T | 04/09/2024 | PAID (REC#2051180): PLAN SPLICE FEE: $50 by: TCRIPPEN for Mechanical: new splice see clouied pages dated 04/05/24 | TCRIPPEN | TCRIPPEN | | XMS | T | 8046596 |
MICK HEATING & SHEET METAL CO. | XMS | P | 03/05/2024 | PLAN SPLICE: (No Fee) by: TCRIPPEN for Mechanical: Approved new splice for gas line size, | TCRIPPEN | TCRIPPEN | | XMS | P | 8014035 |
SOCO PLUMBING | XPS | T | 03/04/2024 | PAID (REC#2039717): PLAN SPLICE FEE: $50 by: SHANEN for Plumbing: Revised sheet P111. | SHANEN | SHANEN | | XPS | T | 8013422 |
CASCO ENTERPRISES, INC. | XES | P | 02/12/2024 | PLAN SPLICE: (No Fee) by: RICHG for Electrical: Went back to original plan. | RICHG | RICHG | | XES | P | 7993187 |
CASCO ENTERPRISES, INC. | XMS | P | 02/12/2024 | PLAN SPLICE: (No Fee) by: RICHG for Mechanical: Went back to original plan. | RICHG | RICHG | | XMS | P | 7993186 |
CASCO ENTERPRISES, INC. | XPS | P | 02/05/2024 | PLAN SPLICE: (No Fee) by: SHANEN for Plumbing: Revised sheet P001 and P111. | SHANEN | SHANEN | | XPS | P | 7986647 |
CASCO ENTERPRISES, INC. | XBS | P | 02/05/2024 | PLAN SPLICE FEE: (no fee) by: BPHILLIPS for Construction: Minor floor plan revisions, added restroom. | BPHILLIPS | BPHILLIPS | | XBS | P | 7986642 |
CASCO ENTERPRISES, INC. | XES | P | 02/05/2024 | PLAN SPLICE: (No Fee) by: RICHG for Electrical: REVISED ED111, ED121, E111, AND E121 | RICHG | RICHG | | XES | P | 7986631 |
CASCO ENTERPRISES, INC. | XMS | T | 02/05/2024 | PAID (REC#2030877) PLAN SPLICE FEE: $50 by: RICHG for Mechanical: REVISED M001,MD111, AND M111 | RICHG | RICHG | | XMS | T | 7986630 |