Construction | Splice 03/03/22 | A | 3/4/2022 | MICHAELA | MICHAELA | Remove door | | Construction | 1645091 |
Mechanical | Original | A | 1/10/2022 | JUSTINC | JUSTINC | | | Mechanical | 1618852 |
Electronic Plan | Original | / | 1/10/2022 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1618813 |
CO Springs DRE | Original | A | 1/6/2022 | AODOM | AODOM | previous approval still applies | | CO Springs DRE | 1617944 |
Plumbing | Original | A | 1/6/2022 | SHANEN | SHANEN | | | Plumbing | 1617862 |
Construction | Original | A | 1/6/2022 | MICHAELA | MICHAELA | | | Construction | 1617670 |
Enumeration | Original | A | 1/5/2022 | BRENT | BRENT | | | Enumeration | 1617245 |
Electronic Plan | Original | / | 1/5/2022 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 1617238 |
Construction | Original | / | 1/5/2022 | WEBSITE | WEBSITE | Overtime Authorized for Construction by DIXIE SNYDER | DSnyder | Construction | 1617223 |
Resubmittal 1 | Original | / | 1/5/2022 | AUSTINK | AUSTINK | Resubmittal #1 | | Resubmittal 1 | 1617205 |
CO Springs Fire | Original | A | 12/21/2021 | CSFIRE | CSFIRE | You are responsible for reviewing the APPROVAL comments found on the CSFD website as they contain important inspection information: https://web1.coloradosprings.gov/PreventionPlanReview/FPS_WebFPS.asp PLEASE ALLOW UP TO AN HOUR FOR COMMENTS TO LOAD TO THE SERVERS – NOTE COMMENTS ARE AVAILABLE FOR 30 DAYS! ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | rpeterson | CO Springs Fire | 1611289 |
CO Springs Hazmat | Original | N | 12/21/2021 | CSFIRE | CSFIRE | | rpeterson | CO Springs Hazmat | 1611288 |
Mechanical | Original | D | 12/3/2021 | JUSTINC | JUSTINC | Clarify VAV's? all shown as grills? provide more clarity? Match background with (A) sheets
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1602258 |
Electronic Plan | Original | / | 12/3/2021 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1602247 |
Plumbing | Original | D | 12/2/2021 | SHANEN | SHANEN | All backgrounds must match per PPRBD plan review requirements. MEP plans do not match architectural floor plans. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Plumbing | 1601852 |
Electrical | Original | A | 12/2/2021 | BERTHA | BERTHA | | | Electrical | 1601696 |
Electronic Plan | Original | / | 12/2/2021 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 1601694 |
CO Springs DRE | Original | A | 12/1/2021 | AODOM | AODOM | office suite in existing office, building, no exterior work at this time | | CO Springs DRE | 1601021 |
Zoning/Planning | Original | / | 11/29/2021 | AODOM | AODOM | In Current Review by AODOM | | Zoning/Planning | 1599834 |
Plumbing | Original | / | 11/29/2021 | WEBSITE | WEBSITE | Overtime Authorized for Plumbing by DIXIE SNYDER | DSnyder | Plumbing | 1599687 |
Electrical | Original | / | 11/29/2021 | WEBSITE | WEBSITE | Overtime Authorized for Electrical by DIXIE SNYDER | DSnyder | Electrical | 1599686 |
Mechanical | Original | / | 11/29/2021 | WEBSITE | WEBSITE | Overtime Authorized for Mechanical by DIXIE SNYDER | DSnyder | Mechanical | 1599684 |
CSU Water | Original | N | 11/29/2021 | CSUREVIEW | CSUREVIEW | Backflow okay. No new water service outside of building. CJS | cjsavage | CSU Water | 1599616 |
CSU Waste Water | Original | N | 11/29/2021 | CSUREVIEW | CSUREVIEW | No new wastewater service outside of building. CJS | cjsavage | CSU Waste Water | 1599615 |
Construction | Original | D | 11/29/2021 | MICHAELA | MICHAELA | Travel distance must be measured to an exit, not the corridor. Add common path of travel distance. Code Study - Where is A-2? See IBC sec. 303.1.1 & 2 Correct Code Study (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1599491 |
Electronic Plan | Original | / | 11/29/2021 | MICHAELA | MICHAELA | In Current Review by MICHAELA | | Electronic Plan | 1599403 |
Enumeration | Original | A | 11/18/2021 | BRENT | BRENT | | | Enumeration | 1596549 |
Electronic Plan | Original | / | 11/18/2021 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 1596531 |
Floodplain | Original | N | 11/17/2021 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6327120008) | | Floodplain | 1595306 |