CO Springs Fire | Original | N | 11/16/2022 | CSFIRE | CSFIRE | You are responsible for reviewing the comments found on the CSFD website as they contain important inspection information: https://web1.coloradosprings.gov/PreventionPlanReview/FPS_WebFPS.asp PLEASE ALLOW UP TO AN HOUR FOR COMMENTS TO LOAD TO THE SERVERS – NOTE COMMENTS ARE AVAILABLE FOR 30 DAYS! ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! (see full review) | csfdit | CO Springs Fire | 1771481 |
Plumbing | Original | A | 11/10/2022 | SHANEN | SHANEN | Living areas not reviewed. Must comply with current adopted codes. | | Plumbing | 1768994 |
CO Springs DRE | Original | A | 11/3/2022 | ZNOYES | ZNOYES | See previous approval comments from 7/26/2022. Per JPM. | | CO Springs DRE | 1765746 |
Zoning/Planning | Original | / | 11/3/2022 | JMALPICA | JMALPICA | In Current Review by JMALPICA | | Zoning/Planning | 1765745 |
Electrical | Original | A | 11/3/2022 | DANIELG | DANIELG | | | Electrical | 1765687 |
Zoning/Planning | Original | / | 11/3/2022 | ZNOYES | ZNOYES | In Current Review by ZNOYES | | Zoning/Planning | 1765685 |
Electronic Plan | Original | / | 11/3/2022 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1765662 |
Mechanical | Original | N | 11/3/2022 | JUSTINC | JUSTINC | All mechanical is existing with no changes as indicated on plan | | Mechanical | 1765634 |
Construction | Original | A | 11/3/2022 | SHELLEY | SHELLEY | As noted on plan. | | Construction | 1765450 |
Submittal 3 | Original | / | 11/2/2022 | KALLISTAJ | KALLISTAJ | Submittal #3 | | Submittal 3 | 1765227 |
CO Springs DRE | Original | A | 10/20/2022 | JMALPICA | JMALPICA | See previous approval comments from7/26/22. (see full review) | | CO Springs DRE | 1759429 |
CO Springs Fire | Original | D | 10/20/2022 | CSFIRE | CSFIRE | INCOMPLETE SUBMITTAL PER RBD - INDENTIFY CODES BEING USED - CSFD RECORDS INDICATED BUILDING IS EQUIPPED WITH A SPRINKLER SYSTEM TO SOME DEGREE - UPDATE PLAN SET ACCORDINGLY BASED ON FIELD VERIFICATION | csfdit | CO Springs Fire | 1759187 |
Electrical | Original | D | 10/14/2022 | DANIELG | DANIELG | Provide electrical plans for the scope of work.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Electrical | 1756580 |
Electronic Plan | Original | / | 10/14/2022 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1756577 |
Zoning/Planning | Original | / | 10/13/2022 | JMALPICA | JMALPICA | In Current Review by JMALPICA | | Zoning/Planning | 1756349 |
Plumbing | Original | D | 10/13/2022 | SHANEN | SHANEN | Provide plumbing plans that comply with PPRBD plumbing plan review requirements. See link:https://www.pprbd.org/File/Resources/Downloads/CommercialHandout/comm%20plumb%20reqs.pdf PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Plumbing | 1756301 |
Mechanical | Original | D | 10/13/2022 | JUSTINC | JUSTINC | Clarify how there is no mechanical scope of work? Per the (A) pages this is an empty shell space
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Mechanical | 1756225 |
Electronic Plan | Original | / | 10/13/2022 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1756170 |
Construction | Original | D | 10/13/2022 | SHELLEY | SHELLEY | Previous comments not address. Please review plans and address all comments prior to resubmittal. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1756160 |
Submittal 2 | Original | / | 10/12/2022 | KALLISTAJ | KALLISTAJ | Submittal #2 | | Submittal 2 | 1755715 |
CO Springs Hazmat | Original | N | 8/8/2022 | CSFIRE | CSFIRE | | dwithee | CO Springs Hazmat | 1724795 |
CO Springs Fire | Original | D | 8/8/2022 | CSFIRE | CSFIRE | incomplete submittal per RBD - identify codes being used. | dwithee | CO Springs Fire | 1724793 |
CO Springs DRE | Original | A | 7/26/2022 | JMALPICA | JMALPICA | Interior residential suite finish. No changes to exterior. All dimensional standards have been met. Approved. (see full review) | | CO Springs DRE | 1718926 |
Electrical | Original | D | 7/21/2022 | DANIELG | DANIELG | Provide electrical plans for the scope of work.
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Electrical | 1716848 |
CSU Water | Original | N | 7/21/2022 | CSUREVIEW | CSUREVIEW | No plumbing work. MLW | mlwilliams | CSU Water | 1716843 |
CSU Waste Water | Original | N | 7/21/2022 | CSUREVIEW | CSUREVIEW | No plumbing work. MLW | mlwilliams | CSU Waste Water | 1716841 |
Electronic Plan | Original | / | 7/21/2022 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1716838 |
Mechanical | Original | D | 7/21/2022 | JUSTINC | JUSTINC | Provide stamped mechanical plan for scope of work
MECHANICAL REVIEW INCOMPLETE
(NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Mechanical | 1716701 |
Plumbing | Original | D | 7/21/2022 | SHANEN | SHANEN | Provide plumbing plans that comply with PPRBD plumbing plan review requirements. See link:https://www.pprbd.org/File/Resources/Downloads/CommercialHandout/comm%20plumb%20reqs.pdf (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Plumbing | 1716699 |
Electronic Plan | Original | / | 7/21/2022 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1716693 |
Zoning/Planning | Original | / | 7/21/2022 | JMALPICA | JMALPICA | In Current Review by JMALPICA | | Zoning/Planning | 1716623 |
Construction | Original | D | 7/21/2022 | SHELLEY | SHELLEY | Complete/revise code study form Provide building code data. If complying with IBC, compliance with IBC 1107 will be required. Show how unit meets all ANSI Type B dwelling unit requirements. If Complying with the IEBC, accessibility compliance may be exempted based on level of alteration. Show code path. Provide an overall floor plan of at least this portion of the floor, showing where the building exits are and the travel distance to those exits. (NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF COMMENTS. FOR ALL COMMENTS, THE DESIGNER SHALL CONDUCT A FULL EXAMINATION OF THE DISAPPROVED SET, WHICH WILL BE ACCESSIBLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. AFTER THE DESIGNER’S EXAMINATION, INDIVIDUAL REVIEWERS ARE AVAILABLE FOR DISCUSSION ON COMMENTS VIA PHONE, EMAIL, OR IN PERSON.) | | Construction | 1716594 |
Electronic Plan | Original | / | 7/21/2022 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 1716535 |
Enumeration | Original | N | 7/21/2022 | AMY | AMY | | | Enumeration | 1716500 |
Electronic Plan | Original | / | 7/20/2022 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1716478 |
Floodplain | Original | N | 7/20/2022 | KEITH | KEITH | | | Floodplain | 1716351 |
Floodplain | Original | / | 6/22/2022 | RBD GIS | RBD GIS | Autogenerated Review: Parcel intersects with 100 Year Floodplain. (Parcel: 6422103043) | | Floodplain | 1702663 |