Monument Water | Original | A | 6/28/2023 | TOWNOFMON | TOWNOFMON | Plan conditionally approved by Town of Monument. Permit Fees are due within 10 days of permit authorization. Note that no final Monument Inspection for C/O can be completed unless all permit fees are paid, Development items/requests are completed and inspection requirements are met which could include the Monument Water Department. Any change to the approved plot plan or variations in the model as depicted on the plot plan requires a plot plan modification and re-review. For more information you may email the Planning Department at planning@tomgov.org. Thank you | lukejameskerr | Monument Water | 1863612 |
Monument Zoning | Original | A | 6/13/2023 | TOWNOFMON | TOWNOFMON | Plan conditionally approved by Town of Monument. Permit Fees are due within 10 days of permit authorization. Note that no final Monument Inspection for C/O can be completed unless all permit fees are paid, Development items/requests are completed and inspection requirements are met which could include the Monument Water Department. Any change to the approved plot plan or variations in the model as depicted on the plot plan requires a plot plan modification and re-review. For more information you may email the Planning Department at planning@tomgov.org. Thank you | lukejameskerr | Monument Zoning | 1855590 |
Tri-Lakes Hazmat (CSFD) | Original | D | 5/8/2023 | CSFIRE | CSFIRE | | jt09ff | Tri-Lakes Hazmat (CSFD) | 1840616 |
Tri-Lakes Fire (CSFD) | Original | D | 5/5/2023 | CSFIRE | CSFIRE | Submitted By: Valdez, Philip Warren We regret to inform you, this plan is disapproved. You are responsible for reviewing the DISAPPROVAL comments found on the CSFD website and responding to them in your resubmittal: https://web1.coloradosprings.gov/PreventionPlanReview/FPS_WebFPS.asp
PLEASE ALLOW UP TO AN HOUR FOR COMMENTS TO LOAD TO THE SERVERS – COMMENTS ARE AVAILABLE FOR ONLY 30 DAYS! (see full review) | csfdit | Tri-Lakes Fire (CSFD) | 1840391 |
Electrical | Original | A | 4/28/2023 | SHELBY | SHELBY | | | Electrical | 1837029 |
Electronic Plan | Original | / | 4/28/2023 | SHELBY | SHELBY | In Current Review by SHELBY | | Electronic Plan | 1836979 |
Mechanical | Original | A | 4/25/2023 | JUSTINC | JUSTINC | | | Mechanical | 1835315 |
Gas/Elec. Utils | Original | D | 4/25/2023 | CSUREVIEW | CSUREVIEW | Not in Colorado Springs Utilities' electric service territory. Not in Colorado Springs Utilities' gas service territory. SSM | stefanm | Gas/Elec. Utils | 1835299 |
Plumbing | Original | D | 4/25/2023 | SHANEN | SHANEN | All backgrounds must match per PPRBD plan review requirements. MEP plans do not match the architectural floor plans. Provide, schedule and show location of/piping for the required drinking fountain. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Plumbing | 1835168 |
Construction | Original | D | 4/25/2023 | JUSTINL | JUSTINL | Need to address review comments for previous review ( 11/11/2022 ) PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1835119 |
Electronic Plan | Original | / | 4/25/2023 | JUSTINL | JUSTINL | In Current Review by JUSTINL | | Electronic Plan | 1834966 |
Enumeration | Original | D | 4/25/2023 | AMY | AMY | See progress set for Enumerations comments on the main A page. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Enumeration | 1834642 |
Submittal 2 | Original | / | 4/24/2023 | KALLISTAJ | KALLISTAJ | Submittal #2 | | Submittal 2 | 1834331 |
Plan Coordinator (Main) | Original | D | 12/19/2022 | JAY | JAY | Disapprove all remaining departments to allow plan to be resubmitted | | Plan Coordinator (Main) | 1783318 |
Plumbing | Original | D | 11/23/2022 | SHANEN | SHANEN | All backgrounds must match per PPRBD plan review requirements. MEP plans do not match the architectural floor plans. Provide, schedule and show location of/piping for the required drinking fountain. All gas piping related items shall be on the mechanical plans. Remove all references to gas piping from the plumbing plans. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Plumbing | 1774757 |
Tri-Lakes Hazmat (CSFD) | Original | D | 11/21/2022 | CSFIRE | CSFIRE | PENDING DOCUMENTS/INFO REQUIRED BY FIRE CONSTRUCTION REVIEW | dwithee | Tri-Lakes Hazmat (CSFD) | 1773645 |
Tri-Lakes Fire (CSFD) | Original | D | 11/21/2022 | CSFIRE | CSFIRE | We regret to inform you, this plan is disapproved. You are responsible for reviewing the DISAPPROVAL comments found on the CSFD website and responding to them in your resubmittal: https://web1.coloradosprings.gov/PreventionPlanReview/FPS_WebFPS.asp PLEASE ALLOW UP TO AN HOUR FOR COMMENTS TO LOAD TO THE SERVERS – COMMENTS ARE AVAILABLE FOR ONLY 30 DAYS! (see full review) | csfdit | Tri-Lakes Fire (CSFD) | 1773639 |
Electrical | Original | D | 11/18/2022 | SHELBY | SHELBY | 1. Please provide fault current information in tabular form ( SCA, SCCR, AIC ) See https://www.pprbd.org/File/Resources/Downloads/CommercialHandout/Com%20Elect%20reqs%202020%20NEC.pdf for fault current terms and methodologies. 2. Transformer GEC incorrect. 3. Show service GEC on one line. 4. Use 2015 IECC the 2018 has not been adopted. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Electrical | 1772792 |
Electronic Plan | Original | / | 11/18/2022 | SHELBY | SHELBY | In Current Review by SHELBY | | Electronic Plan | 1772775 |
Mechanical | Original | D | 11/14/2022 | JUSTINC | JUSTINC | Add note: Provide (1) copy of test and balance report to mechanical inspector at time of heating final inspection. Metal fabrication? Room #8 Wood/metal shops per 2015 IMC 403.3.1.1 Add note that all overhead equipment must be installed 12" above roll up door Indicate roof access How complying with 2015 IECC C403.2.4.3? All gas piping related items to be on mechanical plans.Remove all references to gas piping from the plumbing plans and provide on mechanical plans.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Mechanical | 1770443 |
Electronic Plan | Original | / | 11/14/2022 | JUSTINC | JUSTINC | In Current Review by JUSTINC | | Electronic Plan | 1770426 |
Gas/Elec. Utils | Original | D | 11/14/2022 | CSUREVIEW | CSUREVIEW | Approved Development Plan must be attached to the permit set. Contact Utilities Development Services at 719-668-8259 with any questions. SSM | stefanm | Gas/Elec. Utils | 1770418 |
Health Dept. | Original | N | 11/14/2022 | HEALTHDEPT | HEALTHDEPT | Not applicable. KM | kmaldonado | Health Dept. | 1769906 |
CSU Contract Admin. | Original | N | 11/14/2022 | CSUAPPSPRM | CSUAPPSPRM | No fees due. Outside of service territory. CZ | c.zani | CSU Contract Admin. | 1769856 |
Construction | Original | D | 11/11/2022 | MICHAELA | MICHAELA | Code study indicates non-separated use and the building is compliant without separation. Clarify the purpose of the rated construction. If separated use to reduce fire areas revise the Code Study form. If for other than the IBC add a note to that effect. A0.3 - Code Details - Revise to 2015 IBC. Occupancy separation - 508.4 does not apply if 508.3 is used to comply. Correct Code Study if separated use. Although the structure prescriptively complies you will still be required to provide the sum of the ratios calculations if separated use is chosen. A2.03 - Provide all wall types. A6.03 - Provide compliant access to attic. A8.00 - Verify that all required egress doors with a cylinder lock are operable with a single action. Provide metal building plans. Metal building plans may not be deferred. IECC - Provide the commercial IECC certificate. Structural plans - Fix overlapping text on footing schedule. Include allowable soil nearing pressure and reference the specific soils report the number comes from. Include all design loads. Indicate codes being complied with. PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1769364 |
Elevators | Original | N | 11/9/2022 | ERIC | ERIC | No conveyance | | Elevators | 1768416 |
Electronic Plan | Original | / | 11/9/2022 | MICHAELA | MICHAELA | In Current Review by MICHAELA | | Electronic Plan | 1768328 |
Enumeration | Original | D | 11/8/2022 | AMY | AMY | 1. Code Study, IECC, RBD, and the plan label all changed to Monument from Colorado Springs.
2. Plat is pending. a. Enumerations will review the mylar prior to plat for address placement, street names, and title block. b. A $10.00 per lot and tract platting fee will be due at the time of the review of the mylar, (two addresses per lot and tract). If an address is not needed on a tract then no fee applies. Check should be made out to PIKES PEAK REGIONAL BUILDING DEPARTMENT or PPRBD. Paid directly to the Enumerations Department. As of September 28th, 2022, an additional over the phone transaction fee of 2.95% of the total transaction will apply for any credit card payment. c. A copy of the final recorded plat is required prior to approval in the Enumerations department on any COMMERCIAL plan submittal. Amy@pprbd.org Mylar reviews can be reviewed via “pdf”. The mylar will be stamped by Enumerations for accuracy and returned to the applicant and the planner. All payments to be mailed to RBD via a check or credit card payment over the phone. Plats should not be recorded prior to Enumerations receiving payment. If you would like an in-person review, please make an appointment on our website.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Enumeration | 1767927 |
Electronic Plan | Original | / | 11/8/2022 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1767897 |
Waste Water Div | Original | / | 11/3/2022 | SYSTEM | SYSTEM | You will need to contact Waste Water Div department for approval prior to permit. This department will not review the plan electronically. | | Waste Water Div | 1765942 |
Floodplain | Original | N | 11/3/2022 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 7135000004) | | Floodplain | 1765941 |