CO Springs Fire | Original | D | 4/25/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | Jacob.Watson | CO Springs Fire | 1994552 |
CO Springs Hazmat | Original | D | 4/25/2024 | CSFIRE | CSFIRE | See Fire Comments | Jacob.Watson | CO Springs Hazmat | 1994551 |
Mechanical | Original | D | 4/15/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1989161 |
CO Springs DRE | Original | A | 4/12/2024 | MOBRIEN | MOBRIEN | Approved for change of use from nursing home use to residential drug and alcohol treatment facility. Use is permitted in zone district. No CDI fees owed, by determination of C. Miller. Parking is sufficient. (see full review) | | CO Springs DRE | 1988543 |
CSU Contract Admin. | Original | A | 4/10/2024 | CSUAPPSPRM | CSUAPPSPRM | Commercial water meter sizing form approved. No additional fees required for this plan set.
AMS | ASweet | CSU Contract Admin. | 1987623 |
Electrical | Original | D | 4/10/2024 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1987146 |
Electronic Plan | Original | / | 4/10/2024 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1987073 |
Plumbing | Original | D | 4/9/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 1986601 |
Zoning/Planning | Original | / | 4/9/2024 | MOBRIEN | MOBRIEN | In Current Review by MOBRIEN | | Zoning/Planning | 1986502 |
Elevators | Original | D | 4/9/2024 | ERIC | ERIC | Please see E-0.02 . 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Elevators | 1986397 |
CSU Water | Original | D | 4/9/2024 | CSUREVIEW | CSUREVIEW | New comment: Requires submittal of a Backflow Assembly Plan Review Form to determine if the service backflow prevention meets Standards. Form can be found at: https://www.csu.org/Documents/DomesticAssembly.pdf?csf=1&e=KLQNrS
***Form must be submitted to crossconnection@csu.org. Contact Utilities Development Services at 719-668-8259 with any questions.*** ----------------------------------------------------------------------------------------------------- Previous comments: Plumbing Sheet P-003: Backflow assembly must be installed after domestic meter. Replace this detail with CSU detail B4-8. ----------------------------------------------------------------------------------------------------------------------------------- Obtain approval of Commercial Water Meter Sizing Form through Customer Contract Administration. MLW | mlwilliams | CSU Water | 1986341 |
CSU Contract Admin. | Original | D | 4/9/2024 | CSUAPPSPRM | CSUAPPSPRM | Same comment as previously noted - requires approved Commercial Water Meter Sizing Form (CWMSF) and possible payment of applicable utility charges and fees. Please contact Customer Contract Administration at 719-668-8111 to discuss charges/fees and request an estimate. CWMSF available online at:
https://www.csu.org/CSUDocuments/watermetersizingforminteractive.pdf
AMS | ASweet | CSU Contract Admin. | 1986324 |
Construction | Original | D | 4/9/2024 | DANM | DANM | Appears that all restrooms are for men only - clarify 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1986264 |
Electronic Plan | Original | / | 4/2/2024 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1982671 |
Submittal 3 | Original | / | 4/2/2024 | SIERRAC | SIERRAC | Submittal #3 | | Submittal 3 | 1982450 |
CO Springs Fire | Original | D | 10/26/2023 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | rpeterson | CO Springs Fire | 1919072 |
CO Springs Hazmat | Original | D | 10/26/2023 | CSFIRE | CSFIRE | | rpeterson | CO Springs Hazmat | 1919071 |
Health Dept. | Original | N | 10/23/2023 | HEALTHDEPT | HEALTHDEPT | Not applicable. Per Christopher Gong, Development Manager, existing kitchen is solely a patient feeding operation. AB | abrannon | Health Dept. | 1917399 |
CO Springs DRE | Original | D | 10/19/2023 | APAQUETTE | APAQUETTE | Update parking to UDC standards. CDI fees may apply to this site due to the increase in beds. (see full review) | | CO Springs DRE | 1916219 |
Mechanical | Original | D | 10/18/2023 | JUSTINC | JUSTINC | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1915505 |
CSU Contract Admin. | Original | D | 10/16/2023 | CSUAPPSPRM | CSUAPPSPRM | Requires approved Commercial Water Meter Sizing Form (CWMSF) and may require payment of applicable utility charges and fees. Please contact Customer Contract Administration at 719-668-8111 to discuss charges/fees and request an estimate. CWMSF available online at:
https://www.csu.org/CSUDocuments/watermetersizingforminteractive.pdf
CZ | c.zani | CSU Contract Admin. | 1914183 |
CSU Water | Original | D | 10/16/2023 | CSUREVIEW | CSUREVIEW | Plumbing Sheet P-003: Backflow assembly must be installed after domestic meter. Replace this detail with CSU detail B4-8. ----------------------------------------------------------------------------------------------------------------------------------- Obtain approval of Commercial Water Meter Sizing Form through Customer Contract Administration. MLW | mlwilliams | CSU Water | 1914166 |
CSU Waste Water | Original | N | 10/16/2023 | CSUREVIEW | CSUREVIEW | No new wastewater service outside of building. MLW | mlwilliams | CSU Waste Water | 1914161 |
Electrical | Original | D | 10/16/2023 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1914037 |
Electronic Plan | Original | / | 10/16/2023 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 1913924 |
Plumbing | Original | D | 10/16/2023 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 1913786 |
Zoning/Planning | Original | / | 10/16/2023 | APAQUETTE | APAQUETTE | In Current Review by APAQUETTE | | Zoning/Planning | 1913769 |
Elevators | Original | D | 10/16/2023 | ERIC | ERIC | See FA-0.02 . 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Elevators | 1913767 |
Construction | Original | D | 10/16/2023 | DANM | DANM | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1913756 |
Electronic Plan | Original | / | 10/12/2023 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1912698 |
Submittal 2 | Original | / | 9/20/2023 | SHELLEY | SHELLEY | Submittal #2 | | Submittal 2 | 1902112 |
Plan Coordinator (Main) | Original | D | 3/23/2023 | DANM | DANM | Too many issues for other departments to review submittal.
Disapprove all remaining departments to allow plan to be resubmitted | | Plan Coordinator (Main) | 1819763 |
Construction | Original | D | 3/23/2023 | DANM | DANM | PRELIMINARY REVIEW ONLY
Incorrect Construction Type. No accessibility review - incorrect accessibility calculations. Incorrect ratings for existing building. Multiple missed required ratings for change of occupancy. Incorrect occupant load factors used throughout. Indicate partition types on enlarged plans for all new walls, new wall infill and walls that are changing their fire-resistance-rating or that have a new fire-resistance-rating (e.g. corridor walls changing from smoke partition to fire partition) - typical throughout on all levels. Issues with some rated partition types.
PLEASE NOTE - THE DISAPPROVAL COMMENTS ABOVE MAY NOT REPRESENT THE COMPLETE LIST OF CORRECTIONS REQUIRED ON THE PLAN 1. FOR ELECTRONIC SUBMITTALS, A "PROGRESS SET" IS NOW AVAILABLE FOR REVIEW OF REQUIRED CORRECTIONS. 2. FOR ALL SUBMITTALS, A "REVIEW SET" WILL BE AVAILABLE UPON COMPLETION OF ALL DEPARTMENT REVIEWS. 3. PLANS CANNOT BE RE-SUBMITTED UNTIL EVERY DEPARTMENT HAS COMPLETED THIS CURRENT ROUND OF REVIEW. | | Construction | 1819760 |
Electronic Plan | Original | / | 3/10/2023 | DANM | DANM | In Current Review by DANM | | Electronic Plan | 1814688 |
Enumeration | Original | N | 3/7/2023 | AMY | AMY | Secondary addressing to be checked and verified with CSFD. | | Enumeration | 1811730 |
Electronic Plan | Original | / | 3/7/2023 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1811717 |
Floodplain | Original | N | 2/28/2023 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6334104023) | | Floodplain | 1808458 |