Energy | Original | A | 1/11/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1950614 |
Electrical | Original | A | 1/11/2024 | BERTHA | BERTHA | | | Electrical | 1950613 |
Electronic Plan | Original | / | 1/11/2024 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 1950497 |
Enumeration | Original | N | 12/28/2023 | BECKYA | BECKYA | Per correspondence with the facility project manager, all structures on this site all have the same address. | | Enumeration | 1944867 |
Enumeration | Original | D | 12/28/2023 | BECKYA | BECKYA | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Enumeration | 1944837 |
Submittal 2 | Original | / | 12/26/2023 | QUINTONW | QUINTONW | Submittal #2 | | Submittal 2 | 1944174 |
Tri-Lakes Fire (CSFD) | Original | N | 10/26/2023 | CSFIRE | CSFIRE | electrical only - no fire final | dwithee | Tri-Lakes Fire (CSFD) | 1919330 |
Energy | Original | D | 10/26/2023 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1919066 |
Electrical | Original | D | 10/26/2023 | BERTHA | BERTHA | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1919065 |
Electronic Plan | Original | / | 10/19/2023 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 1916337 |
County Zoning | Original | N | 10/19/2023 | DSDRANGEL | DSDRANGEL | | | County Zoning | 1915853 |
Zoning/Planning | Original | / | 10/19/2023 | DSDRANGEL | DSDRANGEL | In Current Review by DSDRANGEL | | Zoning/Planning | 1915851 |
Construction | Original | N | 10/18/2023 | SHELLEY | SHELLEY | No construction scope | | Construction | 1915814 |
Floodplain | Original | N | 10/18/2023 | AMY | AMY | | | Floodplain | 1915496 |
Enumeration | Original | D | 10/18/2023 | AMY | AMY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Enumeration | 1915492 |
Electronic Plan | Original | / | 10/18/2023 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1915455 |
Fire | Original | / | 10/18/2023 | SYSTEM | SYSTEM | You will need to contact Fire department for approval prior to permit. This department will not review the plan electronically. | | Fire | 1915173 |
Energy | Original | / | 10/18/2023 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1915172 |