Waste Water Div | Original | / | 4/9/2024 | SYSTEM | SYSTEM | Contact Waste Water Div department for approval prior to permit | | Waste Water Div | 1986716 |
Water Division | Original | / | 4/9/2024 | SYSTEM | SYSTEM | Contact Water Division department for approval prior to permit | | Water Division | 1986715 |
Energy | Original | A | 4/9/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1986634 |
Electrical | Original | A | 4/9/2024 | BERTHA | BERTHA | | | Electrical | 1986633 |
Electronic Plan | Original | / | 4/9/2024 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 1986593 |
Construction | Original | N | 4/8/2024 | SHELLEY | SHELLEY | Heater has been removed from plans UNCONDITIONED BUILDING. | | Construction | 1985304 |
| Original | / | 4/5/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 1985218 |
| Original | / | 4/4/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 1984504 |
Submittal 3 | Original | / | 4/4/2024 | BRIANNAM | BRIANNAM | Submittal #3 | | Submittal 3 | 1984503 |
Energy | Original | D | 3/11/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1973528 |
Electrical | Original | D | 3/11/2024 | SHELBY | SHELBY | Previous review comments have not been addressed. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1973527 |
Electronic Plan | Original | / | 3/11/2024 | SHELBY | SHELBY | In Current Review by SHELBY | | Electronic Plan | 1973523 |
Construction | Original | D | 3/6/2024 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1971519 |
Enumeration | Original | N | 3/6/2024 | AMY | AMY | | | Enumeration | 1971461 |
Electronic Plan | Original | / | 3/6/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1971460 |
Submittal 2 | Original | / | 3/5/2024 | BRIANNAM | BRIANNAM | Submittal #2 | | Submittal 2 | 1971411 |
Energy | Original | D | 1/5/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1947678 |
Electrical | Original | D | 1/5/2024 | SHELBY | SHELBY | See Construction comments. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1947677 |
Electronic Plan | Original | / | 1/5/2024 | SHELBY | SHELBY | In Current Review by SHELBY | | Electronic Plan | 1947676 |
Construction | Original | D | 12/14/2023 | SHELLEY | SHELLEY | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1940715 |
Electronic Plan | Original | / | 12/13/2023 | BERTHA | BERTHA | In Current Review by BERTHA | | Electronic Plan | 1939668 |
Black Forest Fire (CSFD) | Original | N | 12/12/2023 | CSFIRE | CSFIRE | N/A No Fire Final (see full review) | phil.valdez | Black Forest Fire (CSFD) | 1939214 |
Black Forest Hazmat (CSFD) | Original | N | 12/12/2023 | CSFIRE | CSFIRE | | phil.valdez | Black Forest Hazmat (CSFD) | 1939199 |
County Zoning | Original | N | 12/12/2023 | DSDRANGEL | DSDRANGEL | | | County Zoning | 1939101 |
Mechanical | Original | N | 12/12/2023 | JUSTINC | JUSTINC | | | Mechanical | 1939017 |
Zoning/Planning | Original | / | 12/12/2023 | DSDRANGEL | DSDRANGEL | In Current Review by DSDRANGEL | | Zoning/Planning | 1939005 |
Plumbing | Original | N | 12/12/2023 | SHANEN | SHANEN | | | Plumbing | 1938994 |
Enumeration | Original | D | 12/12/2023 | AMY | AMY | Include a vicinity map of the lot showing both structures. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Enumeration | 1938963 |
Electronic Plan | Original | / | 12/12/2023 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1938956 |
Floodplain | Original | N | 12/12/2023 | KEITH | KEITH | | | Floodplain | 1938916 |
Energy | Original | / | 12/11/2023 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1938884 |