CO Springs Fire | Original | D | 5/3/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | chiptaylor | CO Springs Fire | 1998281 |
CO Springs Hazmat | Original | N | 5/3/2024 | CSFIRE | CSFIRE | | chiptaylor | CO Springs Hazmat | 1998280 |
Energy | Original | D | 5/2/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1997744 |
Mechanical | Original | D | 5/2/2024 | TCRIPPEN | TCRIPPEN | Disapproved:See construction comments, 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 1997743 |
Electrical | Original | D | 4/26/2024 | SHELBY | SHELBY | 1. Show location of existing service. 2. Please provide fault current information for existing service and re fed panels. 3. Two bedroom feeders and panels are over loaded. 4. Three bedroom feeders are overloaded. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 1995036 |
Plumbing | Original | D | 4/26/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 1994945 |
Electronic Plan | Original | / | 4/25/2024 | TCRIPPEN | TCRIPPEN | In Current Review by TCRIPPEN | | Electronic Plan | 1994484 |
Electronic Plan | Original | / | 4/23/2024 | SHELBY | SHELBY | In Current Review by SHELBY | | Electronic Plan | 1993135 |
CO Springs DRE | Original | D | 4/19/2024 | MOBRIEN | MOBRIEN | 1. Per Land Use Review approval letter, irrigation plan submittal is due before approval of this building permit. 2. Park, school, police and fire fees are due. Please contact Charla.Hudspeth@coloradosprings.gov to pay fees. (see full review) | | CO Springs DRE | 1991642 |
Health Dept. | Original | N | 4/19/2024 | HEALTHDEPT | HEALTHDEPT | Not applicable. MT | mtemple | Health Dept. | 1991577 |
CSU Waste Water | Original | D | 4/18/2024 | CSUREVIEW | CSUREVIEW | Requires submittal of a Backflow Assembly Plan Review Form to determine if the service backflow prevention meets Standards. Form can be found at: https://www.csu.org/Documents/DomesticAssembly.pdf?csf=1&e=KLQNrS
***Form must be submitted to crossconnection@csu.org. Contact Utilities Development Services at 719-668-8259 with any questions.***
Submit a Commercial Water Meter Sizing Form for review to verify size of water service and water meter size. mjg | mgackle | CSU Waste Water | 1990887 |
CSU Water | Original | D | 4/18/2024 | CSUREVIEW | CSUREVIEW | Will re-review after reviewing the Commercial water meter sizing form. mjg | mgackle | CSU Water | 1990885 |
Zoning/Planning | Original | / | 4/17/2024 | MOBRIEN | MOBRIEN | In Current Review by MOBRIEN | | Zoning/Planning | 1990637 |
Construction | Original | D | 4/17/2024 | JUSTINL | JUSTINL | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 1990608 |
Electronic Plan | Original | / | 4/15/2024 | JUSTINL | JUSTINL | In Current Review by JUSTINL | | Electronic Plan | 1989099 |
Enumeration | Original | D | 4/15/2024 | AMY | AMY | Lettering with numbering cannot be combined within a unit number. Change the studio unit numbering and remove the lettering. See floor plan numbering as to how Enumerations would like to see the numbering layout. Splitting the hallway in half with evens on one side and odd on the other. | | Enumeration | 1989040 |
Electronic Plan | Original | / | 4/15/2024 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 1989015 |
Energy | Original | / | 4/12/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 1988516 |
Floodplain | Original | N | 4/12/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6420202017) | | Floodplain | 1988515 |