CO Springs DRE | Original | D | 5/16/2024 | SSADLER | SSADLER | The code study needs to speak to the exterior changes. This project will need a zoning final to check for ADA compliance. (see full review) | | CO Springs DRE | 2004898 |
Energy | Original | D | 5/15/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2004449 |
Electrical | Original | D | 5/15/2024 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2004448 |
Electronic Plan | Original | / | 5/15/2024 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 2004408 |
Elevators | Original | D | 5/15/2024 | ERIC | ERIC | Garaventa 3 stop enclosed VPL.
See E121 . 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Elevators | 2004302 |
Plumbing | Original | D | 5/15/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2004283 |
Mechanical | Original | D | 5/15/2024 | TREVORH | TREVORH | Disapproved; need existing HVAC Equipment schedule 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2004272 |
Electronic Plan | Original | / | 5/15/2024 | TREVORH | TREVORH | In Current Review by TREVORH | | Electronic Plan | 2004207 |
Zoning/Planning | Original | / | 5/15/2024 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2004197 |
CSU Water | Original | N | 5/15/2024 | CSUREVIEW | CSUREVIEW | No new water service outside of building. MAR | MRoberts | CSU Water | 2004186 |
CSU Waste Water | Original | N | 5/15/2024 | CSUREVIEW | CSUREVIEW | No new wastewater service outside of building. MAR | MRoberts | CSU Waste Water | 2004183 |
Construction | Original | D | 5/15/2024 | CGIECK | CGIECK | Please review progress set. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2004126 |
Electronic Plan | Original | / | 5/10/2024 | CGIECK | CGIECK | In Current Review by CGIECK | | Electronic Plan | 2002146 |
Enumeration | Original | D | 5/10/2024 | BRENT | BRENT | This plan establishes multiple new suites. All tenant spaces need to have a suite number which follows the RBD secondary addressing guidelines available on our website. The suite numbering shown on this plan for the lower level does not follow these guidelines. The upper level tenant will need a suite number as well. Show updated suite numbering on this plan. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Enumeration | 2002066 |
Electronic Plan | Original | / | 5/10/2024 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 2002020 |
Energy | Original | / | 5/8/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2000672 |
Floodplain | Original | N | 5/8/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6407416017) | | Floodplain | 2000670 |