CO Springs DRE | Original | A | 11/12/2024 | SSADLER | SSADLER | Approval letter uploaded. Approved for commercial interior finish. Use is compatible with the approved development plan. No exterior changes (see full review) | | CO Springs DRE | 2084227 |
Energy | Original | A | 11/12/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2084215 |
Mechanical | Original | A | 11/12/2024 | DALEH | DALEH | | | Mechanical | 2084214 |
Zoning/Planning | Original | / | 11/8/2024 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2083240 |
Plumbing | Original | A | 11/8/2024 | SHANEN | SHANEN | | | Plumbing | 2082992 |
| Original | / | 11/8/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2082970 |
| Original | / | 11/8/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2082969 |
Submittal 5 | Original | / | 11/8/2024 | SIERRAC | SIERRAC | Submittal #5 | | Submittal 5 | 2082968 |
CO Springs Hazmat | Original | A | 11/7/2024 | CSFIRE | CSFIRE | This was a defered submittal submitted through the ACA submitted on 10/8/2024 and permit issued 10/15/20224. DFM-C-CG-24-00047 You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! DFM-C-HM-24-00047 (see full review) | mark.stanwood@colora | CO Springs Hazmat | 2082909 |
CO Springs Fire | Original | A | 11/7/2024 | CSFIRE | CSFIRE | You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | phil.valdez | CO Springs Fire | 2082753 |
Energy | Original | D | 11/6/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2082275 |
Mechanical | Original | D | 11/6/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2082274 |
CO Springs DRE | Original | D | 11/4/2024 | SSADLER | SSADLER | Approval still applies. However, we need the approval letter for the entitlement uploaded. (see full review) | | CO Springs DRE | 2080842 |
Plumbing | Original | D | 11/1/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2080207 |
Zoning/Planning | Original | / | 10/31/2024 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2079715 |
Mechanical | Original | D | 10/31/2024 | DALEH | DALEH | Still need to upload all kitchen hood spec sheets into mechanical upload 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2079699 |
Construction | Original | A | 10/31/2024 | BPHILLIPS | BPHILLIPS | | | Construction | 2079692 |
| Original | / | 10/30/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2079642 |
| Original | / | 10/30/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2079619 |
Submittal 4 | Original | / | 10/30/2024 | QUINTONW | QUINTONW | Submittal #4 | | Submittal 4 | 2079618 |
CO Springs DRE | Original | A | 10/30/2024 | SSADLER | SSADLER | Plans match the approved entitlements on file. FBZN 24-0011. Approved for a commercial interior remodel with patio addition. (see full review) | | CO Springs DRE | 2079391 |
CO Springs Hazmat | Original | D | 10/29/2024 | CSFIRE | CSFIRE | SEE FIRE COMMENTS | michael.davis1@color | CO Springs Hazmat | 2078555 |
CO Springs Fire | Original | D | 10/29/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | michael.davis1@color | CO Springs Fire | 2078554 |
Energy | Original | D | 10/28/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2077970 |
Mechanical | Original | D | 10/28/2024 | DALEH | DALEH | No revisions to previous comments 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2077969 |
Plumbing | Original | D | 10/28/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2077928 |
Zoning/Planning | Original | / | 10/28/2024 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2077886 |
Construction | Original | D | 10/28/2024 | BPHILLIPS | BPHILLIPS | Appears there was an issue uploading revised G0.2. Missing information previously present. 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2077866 |
| Original | / | 10/25/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2077274 |
| Original | / | 10/25/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2077249 |
Submittal 3 | Original | / | 10/25/2024 | BRIANNAM | BRIANNAM | Submittal #3 | | Submittal 3 | 2077248 |
CO Springs Hazmat | Original | D | 10/24/2024 | CSFIRE | CSFIRE | | rpeterson | CO Springs Hazmat | 2076666 |
CO Springs Fire | Original | D | 10/24/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | rpeterson | CO Springs Fire | 2076665 |
Energy | Original | D | 10/17/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2073848 |
Plumbing | Original | D | 10/17/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2073847 |
CO Springs DRE | Original | D | 10/16/2024 | SSADLER | SSADLER | Entitlement applications are not approved. Once they are approved, please upload the approval letter and the approved stamped plans. (see full review) | | CO Springs DRE | 2073127 |
Mechanical | Original | D | 10/15/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2072569 |
Electrical | Original | A | 10/14/2024 | DANIELG | DANIELG | | | Electrical | 2072097 |
Zoning/Planning | Original | / | 10/14/2024 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2071918 |
Construction | Original | D | 10/14/2024 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2071916 |
Electronic Plan | Original | / | 10/11/2024 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2071627 |
Submittal 2 | Original | / | 10/11/2024 | BRIANNAM | BRIANNAM | Submittal #2 | | Submittal 2 | 2071441 |
Health Dept. | Original | A | 9/27/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment approved in plan review. A pre-operational inspection will be required before final approval for opening is granted. AB | abrannon | Health Dept. | 2065336 |
CO Springs Fire | Original | D | 9/12/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | chiptaylor | CO Springs Fire | 2059236 |
CO Springs Hazmat | Original | D | 9/12/2024 | CSFIRE | CSFIRE | | chiptaylor | CO Springs Hazmat | 2059235 |
Energy | Original | D | 9/5/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2056324 |
Electrical | Original | D | 9/5/2024 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2056323 |
Electronic Plan | Original | / | 9/5/2024 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 2056299 |
Mechanical | Original | D | 9/3/2024 | DALEH | DALEH | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2054534 |
Electronic Plan | Original | / | 9/3/2024 | DALEH | DALEH | In Current Review by DALEH | | Electronic Plan | 2054515 |
CO Springs DRE | Original | D | 8/30/2024 | SSADLER | SSADLER | Once the pre application is complete, upload the summary to show that no entitlement is needed. If an entitlement is needed, upload the approval letter along with the approved and stamped plans. (see full review) | | CO Springs DRE | 2054299 |
Plumbing | Original | D | 8/29/2024 | SHANEN | SHANEN | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Plumbing | 2053211 |
CSU Waste Water | Original | N | 8/28/2024 | CSUREVIEW | CSUREVIEW | Variance for an interior grease trap is approved. No new wastewater service outside of building. CJS | cjsavage | CSU Waste Water | 2052992 |
CSU Water | Original | N | 8/28/2024 | CSUREVIEW | CSUREVIEW | No new water service outside of building. CJS | cjsavage | CSU Water | 2052985 |
Zoning/Planning | Original | / | 8/28/2024 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2052956 |
Construction | Original | D | 8/28/2024 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2052864 |
Electronic Plan | Original | / | 8/26/2024 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2051612 |
Health Dept. | Original | D | 8/20/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment plan review is in process and not yet approved. If your assigned plan reviewer has questions, they will contact you directly. For questions, contact Environmental Health at 719-578-3199 option 3. AB | abrannon | Health Dept. | 2048880 |
Enumeration | Original | N | 8/19/2024 | BECKYA | BECKYA | | | Enumeration | 2048435 |
Energy | Original | / | 8/15/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2047370 |
Floodplain | Original | N | 8/15/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6418317001) | | Floodplain | 2047369 |