| Original | / | 11/26/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2090299 |
| Original | / | 11/26/2024 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2089854 |
Submittal 3 | Original | / | 11/26/2024 | SIERRAC | SIERRAC | Submittal #3 | | Submittal 3 | 2089853 |
CO Springs Fire | Original | D | 11/21/2024 | CSFIRE | CSFIRE | WALK OK
(DISAPPROVED) COMPRESSED GASSES - CARBON DIOXIDE, NITROGEN, OXYGEN, ETC
Provide Compressed Gases form due to CO2 cylinders and BagNBox called out on sheet A-1
It appears that compressed gas will be used in this facility. Prior to approval of these plans we will need a compressed gas questionnaire completed, signed, dated, and returned with construction set of plans. You can access this form on our website. https://coloradosprings.gov/hazmat | Jacob.Watson | CO Springs Fire | 2088677 |
CO Springs Hazmat | Original | D | 11/21/2024 | CSFIRE | CSFIRE | See Fire Comments | Jacob.Watson | CO Springs Hazmat | 2088676 |
EPC Health Dept | Original | A | 11/15/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment approved in plan review. A pre-operational inspection will be required before final approval for opening is granted. As a reminder, install handwashing sink near 4-compartment sink, and near #11 and #14. MT | mtemple | EPC Health Dept | 2086025 |
CO Springs DRE | Original | D | 11/15/2024 | KSCHOTT | KSCHOTT | 1. Please include the most recent amended/approved development plan (DEPN-24-0099) 2. And please provide overall site plan and specify/cloud the building and unit this permit is for 3. Cannot approve this interior finish until a CO is granted for the core and shell of the building. Currently have a TCO because all private financial assurances must be posted for CO of core/shell and for approval of this interior finish | | CO Springs DRE | 2085826 |
CSU Waste Water | Original | D | 11/12/2024 | CSUREVIEW | CSUREVIEW | See previous comments. A variance is required for this unit as it is too far from the existing grease interceptor. Contact CSU Industrial Pretreatment representative Bob Bowren via email at fog@csu.org to determine if a variance for an interior grease trap is applicable. If applicable, provide a copy of the Variance letter in the building plan set.MDA | malcuran | CSU Waste Water | 2084005 |
Energy | Original | A | 11/12/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2083975 |
Mechanical | Original | A | 11/12/2024 | TREVORH | TREVORH | Approved; | | Mechanical | 2083974 |
Zoning/Planning | Original | / | 11/12/2024 | KSCHOTT | KSCHOTT | In Current Review by KSCHOTT | | Zoning/Planning | 2083905 |
Electrical | Original | A | 11/11/2024 | DANIELG | DANIELG | | | Electrical | 2083465 |
Construction | Original | A | 11/11/2024 | BPHILLIPS | BPHILLIPS | | | Construction | 2083359 |
Electronic Plan | Original | / | 11/11/2024 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2083347 |
Enumeration | Original | A | 11/7/2024 | BRENT | BRENT | | | Enumeration | 2082705 |
Electronic Plan | Original | / | 11/7/2024 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 2082689 |
Submittal 2 | Original | / | 11/7/2024 | SIERRAC | SIERRAC | Submittal #2 | | Submittal 2 | 2082667 |
Energy | Original | D | 10/29/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2078588 |
Plumbing | Original | A | 10/29/2024 | SHANEN | SHANEN | | | Plumbing | 2078587 |
CO Springs Fire | Original | D | 10/25/2024 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. (see full review) | Jacob.Watson | CO Springs Fire | 2077803 |
CO Springs Hazmat | Original | D | 10/25/2024 | CSFIRE | CSFIRE | See Fire Comments | Jacob.Watson | CO Springs Hazmat | 2077802 |
Electrical | Original | D | 10/22/2024 | DANIELG | DANIELG | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Electrical | 2075555 |
Electronic Plan | Original | / | 10/22/2024 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 2075551 |
CO Springs DRE | Original | D | 10/18/2024 | KSCHOTT | KSCHOTT | 1. Please provide an overall site map with clouded building for this permit 2. Please include the approved/stamped development plan with resubmittal Informational: CDI fees paid with core/shell permit. Private FA has been posted. | | CO Springs DRE | 2074541 |
Zoning/Planning | Original | / | 10/17/2024 | KSCHOTT | KSCHOTT | In Current Review by KSCHOTT | | Zoning/Planning | 2074266 |
Zoning/Planning | Original | / | 10/17/2024 | RDCUSER | RDCUSER | In Current Review by RDCUSER | | Zoning/Planning | 2074265 |
Zoning/Planning | Original | / | 10/17/2024 | KSCHOTT | KSCHOTT | In Current Review by KSCHOTT | | Zoning/Planning | 2074263 |
Zoning/Planning | Original | / | 10/17/2024 | DSEXTON | DSEXTON | In Current Review by DSEXTON | | Zoning/Planning | 2074262 |
EPC Health Dept | Original | D | 10/16/2024 | HEALTHDEPT | HEALTHDEPT | Retail food establishment plan review required. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/retail-food/retail-food-establishments/. Please email application and all required documents to healthinfo@elpasoco.com. For questions, contact Environmental Health at 719-578-3199 option 3. AM | Amanda Furno | EPC Health Dept | 2073702 |
CSU Contract Admin. | Original | N | 10/16/2024 | CSUAPPSPRM | CSUAPPSPRM | Commercial Water Meter Sizing Form approved and applicable development fees/charges paid - master meter configuration.
AMS | ASweet | CSU Contract Admin. | 2073362 |
Zoning/Planning | Original | / | 10/16/2024 | KSCHOTT | KSCHOTT | In Current Review by KSCHOTT | | Zoning/Planning | 2073070 |
City Engr | Original | N | 10/15/2024 | JDAGNILLO | JDAGNILLO | | | City Engr | 2073018 |
Mechanical | Original | D | 10/15/2024 | TREVORH | TREVORH | Disapproved; 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Mechanical | 2072938 |
CSU Water | Original | A | 10/15/2024 | CSUREVIEW | CSUREVIEW | Refer to core and shell permit for approved utility construction drawings. MLW | mlwilliams | CSU Water | 2072898 |
Gas/Elec. Utils | Original | A | 10/15/2024 | CSUREVIEW | CSUREVIEW | CSU Field Engineer to determine final gas/electric meter, transformer and service line locations. Contact Field Engineering at 719-668-4985 (Gas) or 719-668-5564 (Electric) with any questions. MLW | mlwilliams | Gas/Elec. Utils | 2072897 |
CSU Waste Water | Original | D | 10/15/2024 | CSUREVIEW | CSUREVIEW | A variance is required for this unit as it is located too far from the existing grease interceptor. Contact CSU Industrial Pretreatment representative Bob Bowren via email at fog@csu.org to request a variance for this condition. If variance is approved, provide a copy of the Variance Letter in the building plan set. MLW | mlwilliams | CSU Waste Water | 2072888 |
Elevators | Original | N | 10/15/2024 | ERIC | ERIC | No conveyance | | Elevators | 2072780 |
Construction | Original | D | 10/15/2024 | BPHILLIPS | BPHILLIPS | 1. Please see either the "Progress Set" or the "Review Set" for required corrections. 2. The "Review Set" will become available after all department reviews are complete. 3. Electronic Plans may be re-submitted after the "Review Set" has been created. 4. After all reviews are complete, paper plans may be picked up from the same location they were submitted. | | Construction | 2072761 |
Electronic Plan | Original | / | 10/15/2024 | BPHILLIPS | BPHILLIPS | In Current Review by BPHILLIPS | | Electronic Plan | 2072427 |
Enumeration | Original | A | 10/14/2024 | BRENT | BRENT | Tenant will occupy suites 140 and 150 as shown on the core and shell plan. Will use Suite 140 as business address. | | Enumeration | 2071946 |
Electronic Plan | Original | / | 10/14/2024 | BRENT | BRENT | In Current Review by BRENT | | Electronic Plan | 2071935 |
Energy | Original | / | 10/8/2024 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2069856 |
Floodplain | Original | N | 10/8/2024 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6233201014) | | Floodplain | 2069855 |