Electrical | Original | D | 3/6/2025 | DANIELG | DANIELG | Pending elevator approval. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Electrical | 2127881 |
Mechanical | Original | D | 3/5/2025 | DALEH | DALEH | Waiting on elevator comments * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2127516 |
Plumbing | Original | N | 3/4/2025 | SHANEN | SHANEN | | | Plumbing | 2126863 |
Elevators | Original | D | 3/3/2025 | ROBERTV | ROBERTV | Original site survey with TK and Site Facility Engineer determined there is a generator onsite that provides power to all four elevators. This is not reflected in the Electrical Drawings. Another site visit will need to take place to verify there is, or is not a generator.
Mechanical Sheet numberings need to be in a consecutive order fashion.
Mechanical work is noted as 'N/A' on 1Lifts WBO Document. Whomever is responsible for Mechanical work needs to specify that scope on a WBO Document.
See TKE Scope of Work Document page 4
Mechanical Engineer needs to specify what is to happen with all the existing elevator machine room ventilation equipment, ducts, and openings in fire rated assemblies in all the elevator machine rooms. . * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Elevators | 2126688 |
Construction | Original | N | 2/10/2025 | SHELLEY | SHELLEY | No construction scope. | | Construction | 2119031 |
Floodplain | Original | N | 2/7/2025 | KEITH | KEITH | | | Floodplain | 2118704 |
Submittal 2 | Original | / | 2/7/2025 | SIERRAC | SIERRAC | Submittal #2 | | Submittal 2 | 2118685 |
Plan Coordinator (Main) | Original | D | 2/7/2025 | SIERRAC | SIERRAC | Disapprove all remaining departments to allow plan to be resubmitted per voicemail request from Leah at TK Elevator. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plan Coordinator (Main) | 2118644 |
Energy | Original | N | 2/7/2025 | SYSTEM | SYSTEM | Energy Department review not required under 2023 PPRBC when IECC is N/A | | Energy | 2118506 |
Floodplain | Original | / | 2/7/2025 | RBD GIS | RBD GIS | Autogenerated Review: Parcel intersects with 100 Year Floodplain. (Parcel: 6307002004) | | Floodplain | 2118505 |