EPC Health Dept | Original | D | 3/7/2025 | HEALTHDEPT | HEALTHDEPT | Retail food establishment plan review required for the warming kitchen. Information and application may be accessed online at https://www.elpasocountyhealth.org/licenses-permits-inspections-water-testing/retail-food/retail-food-establishments/. Please email application and all required documents to healthinfo@elpasoco.com. For questions, contact Environmental Health at 719-578-3199 option 3. AM | Amanda Furno | EPC Health Dept | 2128770 |
CO Springs DRE | Original | D | 3/7/2025 | MAMBUUL | MAMBUUL | Proposed adult day care is a conditional use in the MX-N zone district. A conditional use permit will need to be obtained, and approved plans will need to be uploaded to permit. See pre-application meeting comments, city file number PRE-24-0551. | | CO Springs DRE | 2128747 |
Zoning/Planning | Original | / | 3/7/2025 | MAMBUUL | MAMBUUL | In Current Review by MAMBUUL | | Zoning/Planning | 2128741 |
CSU Water | Original | D | 3/7/2025 | CSUREVIEW | CSUREVIEW | Submit a Commercial Water Meter Sizing Form to verify service and water meter size. mjg | mgackle | CSU Water | 2128712 |
CSU Waste Water | Original | D | 3/7/2025 | CSUREVIEW | CSUREVIEW | Contact CSU Industrial Pretreatment representative Bob Bowren via email at fog@csu.org to request a variance for a Grease Interceptor. Provide a copy of the Variance Letter in the building plan set. If a Grease Interceptor is required a Utility Service Plan is required. mjg | mgackle | CSU Waste Water | 2128710 |
Construction | Original | D | 3/7/2025 | SHELLEY | SHELLEY | Life safety plan and code data issues, accessibility issues, see plan. * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2128706 |
Electronic Plan | Original | / | 3/7/2025 | SHELLEY | SHELLEY | In Current Review by SHELLEY | | Electronic Plan | 2128395 |
Plumbing | Original | D | 3/6/2025 | SHANEN | SHANEN | Compliance with 2021 IPC and CO state amendments to 2021 IPC must be stated on the plumbing plans. Provided water pipe size analysis data is incomplete. Data must include: service pressure, service size, meter size, pressure loss, available pressure, distribution size, WSFU served, developed length, etc. See highlighted sections on clouded additional requirements for 2021 IECC block. Scheduled EXP-TANK is for residential use only per manufacturer website. Provide a water distribution isometric drawing.Lavatories must show compliance with 2021 IECC section C404.5.1. Discharge warming kitchen plumbing fixtures through a grease interceptor or provide a CSU variance letter to certify compliance with best management practices. Contact Robert Bowren at 719-668-1735 or fog@csu.org * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Plumbing | 2127873 |
Enumeration | Original | A | 2/27/2025 | AMY | AMY | The 2nd floor must now use a suite number, suite 200. | | Enumeration | 2125761 |
Electronic Plan | Original | / | 2/27/2025 | AMY | AMY | In Current Review by AMY | | Electronic Plan | 2125752 |
Energy | Original | / | 2/27/2025 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC (2021 IECC Amended) is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2125462 |
Floodplain | Original | N | 2/27/2025 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6410101054) | | Floodplain | 2125461 |