| Zoning/Planning | Original | / | 7/23/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2338336 |
| | Original | / | 7/23/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee(s) Paid | | | 2338326 |
| | Original | / | 7/23/2026 | SYSTEM | SYSTEM | Resubmittal Processing Fee Due | | | 2338321 |
| Submittal 3 | Original | / | 7/23/2026 | MELISSAF | MELISSAF | Submittal #3 | | Submittal 3 | 2338320 |
| CO Springs Hazmat | Original | D | 7/16/2026 | CSFIRE | CSFIRE | CSFD Record Number: DFM-C-HM-26-00032
You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Division of the Fire Marshal staff to link the review to your account. | smitty91 | CO Springs Hazmat | 2335422 |
| Energy | Original | A | 7/15/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2334564 |
| Mechanical | Original | A | 7/15/2026 | TREVORH | TREVORH | Approved; | | Mechanical | 2334563 |
| Energy | Original | D | 7/14/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2334054 |
| Mechanical | Original | D | 7/14/2026 | TREVORH | TREVORH | pending Hazmat review * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Mechanical | 2334053 |
| Energy | Original | A | 7/14/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2334051 |
| Mechanical | Original | A | 7/14/2026 | TREVORH | TREVORH | pending Hazmat review | | Mechanical | 2334050 |
| Energy | Original | / | 7/14/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2334044 |
| CO Springs DRE | Original | D | 7/13/2026 | SSADLER | SSADLER | Once minor modification record DEPN-26-0071 is approved, upload the approved and stamped plans and the approval letter. There may be fees owed for the use change. | | CO Springs DRE | 2333410 |
| Zoning/Planning | Original | / | 7/8/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2331693 |
| Energy | Original | A | 7/8/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2331606 |
| Construction | Original | A | 7/8/2026 | DOUGC | DOUGC | | | Construction | 2331605 |
| CO Springs Fire | Original | A | 7/6/2026 | CSFIRE | CSFIRE | CSFD FCS: You are responsible for reviewing the comments through your ACA account. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. ALL PLAN APPROVALS SUBJECT TO FINAL INSPECTION! | chiptaylor | CO Springs Fire | 2330533 |
| Submittal 2 | Original | / | 7/2/2026 | NICOLASV | NICOLASV | Submittal #2 | | Submittal 2 | 2330105 |
| CO Springs Fire | Original | D | 6/26/2026 | CSFIRE | CSFIRE | You must have a ACA account in order to view your disapproval comments. You can find the link to the ACA website and a tutorial video on how to set up an account at: https://coloradosprings.gov/fire-code-resources . If you do not have an ACA account at time of CSFD review you will need to reach out to the CSFD Construction Service staff to link the review to your account. | phil.valdez | CO Springs Fire | 2327674 |
| CO Springs DRE | Original | D | 6/26/2026 | CHUDSPETH | CHUDSPETH | Minor Modification to DEPN-26-0071 is still under review. Until complete, plans are disapproved. Once approved please upload the approval letter and stamped plans. | | CO Springs DRE | 2327662 |
| Energy | Original | D | 6/26/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2327660 |
| CO Springs Hazmat | Original | D | 6/26/2026 | CSFIRE | CSFIRE | To allow contractor to upload documents for review. | smitty91 | CO Springs Hazmat | 2327206 |
| CO Springs DRE | Original | A | 6/18/2026 | CHUDSPETH | CHUDSPETH | No CDI fees due as Light Industry Use Teir 4 is below = too the existing Office / Warehouse value. | | CO Springs DRE | 2323803 |
| CO Springs DRE | Original | D | 6/17/2026 | SSADLER | SSADLER | There may be impact fees owed for use change. Contact Charla at charla.hudspeth@coloradosprings.gov
Plans are approved once fees have been collected. Approved for a commercial interior remodel. No changes to existing footprint, parking, or landscaping. | | CO Springs DRE | 2322999 |
| CSU Water | Original | N | 6/17/2026 | CSUREVIEW | CSUREVIEW | No new water service outside of building. mjg | mgackle | CSU Water | 2322936 |
| CSU Waste Water | Original | N | 6/17/2026 | CSUREVIEW | CSUREVIEW | No new wastewater service outside of building. mjg | mgackle | CSU Waste Water | 2322934 |
| Electrical | Original | A | 6/17/2026 | DANIELG | DANIELG | | | Electrical | 2322923 |
| Electronic Plan | Original | / | 6/17/2026 | DANIELG | DANIELG | In Current Review by DANIELG | | Electronic Plan | 2322913 |
| Zoning/Planning | Original | / | 6/17/2026 | SSADLER | SSADLER | In Current Review by SSADLER | | Zoning/Planning | 2322900 |
| Plumbing | Original | A | 6/17/2026 | SHANEN | SHANEN | | | Plumbing | 2322752 |
| Construction | Original | D | 6/17/2026 | DOUGC | DOUGC | CSF // IECC // Code Cycle // Path Of Egress * Please see either the "Progress Set" or the "Review Set" for complete list of this department's corrections. Plans cannot be re-submitted until all required departments have completed their review. * | | Construction | 2322749 |
| Electronic Plan | Original | / | 6/17/2026 | DOUGC | DOUGC | In Current Review by DOUGC | | Electronic Plan | 2322685 |
| Enumeration | Original | N | 6/2/2026 | BECKYA | BECKYA | | | Enumeration | 2315277 |
| Plumbing | Original | / | 6/2/2026 | BECKYA | BECKYA | Overtime approved for Plumbing by per Kier | | Plumbing | 2315267 |
| Mechanical | Original | / | 6/2/2026 | BECKYA | BECKYA | Overtime approved for Mechanical by per Kier | | Mechanical | 2315266 |
| Electrical | Original | / | 6/2/2026 | BECKYA | BECKYA | Overtime approved for Electrical by per Kier | | Electrical | 2315265 |
| Construction | Original | / | 6/2/2026 | BECKYA | BECKYA | Overtime approved for Construction by per Kier | | Construction | 2315263 |
| Electronic Plan | Original | / | 6/2/2026 | BECKYA | BECKYA | In Current Review by BECKYA | | Electronic Plan | 2315260 |
| | Original | / | 6/2/2026 | SYSTEM | SYSTEM | Plan Review fees paid 06/02/2026 for plan submitted 06/02/2026. Submit Date updated to now. Plan now open for review. | | | 2315134 |
| Energy | Original | / | 6/2/2026 | SYSTEM | SYSTEM | Energy Department review for 2023 PPRBC is based on status of Construction, Electrical, Mechanical and Plumbing reviews | | Energy | 2315007 |
| Floodplain | Original | N | 6/2/2026 | RBD GIS | RBD GIS | Autogenerated Review: Outside 100 Year Floodplain. (Parcel: 6425005019) | | Floodplain | 2315006 |