Out to Review | Original | A | 12/4/2002 | JOHNJ | JOHNJ | ERIC BARRY HAS | | Out to Review | 176809 |
Construction | Original | A | 12/4/2002 | SEAN | SEAN | | | Construction | 176798 |
Fire | Original | N | 12/3/2002 | KEN | KEN | 12-02-02 SMC - no fire final required | | Fire | 176805 |
Construction | Original | D | 11/26/2002 | TIMC | TIMC | Is stairway used only for access to building eqipment? If not then stairs must be 1003.3.3.6 and guardrail per 509. Per first review: Specify mezz design parameters. Specify soil bearing pressure used in design. Label location of trusses on roof framing plan. No walk-thru | | Construction | 176801 |
Construction | Original | / | 11/26/2002 | TIMC | TIMC | | | Construction | 176797 |
Construction | Original | D | 11/4/2002 | SEAN | SEAN | still need trusses and stair detail. 1hr construction OK. walk thru OK. | | Construction | 176800 |
Zoning/Planning | Original | A | 11/4/2002 | CSZONING | CSZONING | PER AR CM3 01-439. PRIOR TO INSTALLING THE ANTENNAE AND PUTTING THE FACILITY ON AIR, THE ANTENNAE SCREEN SHALL BE COMPLETELY CONSTRUCTED. | | Zoning/Planning | 176810 |
Out to Review | Original | A | 10/30/2002 | TERESA | TERESA | Mark Zamora-Charles Taylor Communications | | Out to Review | 176808 |
Electrical | Original | A | 5/22/2002 | RED | RED | | | Electrical | 176803 |
Construction | Original | D | 5/22/2002 | TIMC | TIMC | Provide details and UL#'s for walls and ceilings to show 1-hr buiding requirement is being met. Provide copy of all premanufactured trusses and label location on roof framing plan. Specify design parameters for mezz floor. Specify soil bearing pressure used in foundation deasign and provide copy of soils report. Provide section of stairway showing rise, run etc. No walk-thru. | | Construction | 176799 |
Zoning/Planning | Original | D | 5/14/2002 | ANGELA | ANGELA | dmt5-13-02 | | Zoning/Planning | 176812 |
Zoning/Planning | Original | D | 5/13/2002 | CSZONING | CSZONING | ATTACH APPROVED AR CM3 01-439. PRIOR TO INSTALLING THE ANTENNAE AND PUTTING THE FACILITY ON AIR, THE ANTENNAE SCREEN SHALL BE COMPLETELY CONSTRUCTED. | | Zoning/Planning | 176811 |
Health Dept. | Original | A | 5/7/2002 | ANGELA | ANGELA | l scanlon 5-6-02 | | Health Dept. | 176807 |
Electric Div. | Original | A | 5/7/2002 | ANGELA | ANGELA | lp 5-6-02 | | Electric Div. | 176802 |
Floodplain | Original | A | 5/3/2002 | JEANNINE | JEANNINE | | | Floodplain | 176806 |
Enumeration | Original | A | 5/3/2002 | KAREN | KAREN | | | Enumeration | 176804 |