Hazmat/High Pil | Original | N | 1/3/2007 | SHELLEY | SHELLEY | 1/3/07 - vlc | | Hazmat/High Pil | 265475 |
Fire | Original | A | 1/3/2007 | CSFIRE | CSFIRE | 1/3/07 - vlc | | Fire | 265472 |
Out to Review | Original | A | 1/3/2007 | SHELLEY | SHELLEY | mike reiman, 303-710-9179 | | Out to Review | 265484 |
Fire | Original | D | 12/22/2006 | CSFIRE | CSFIRE | 12/21/06 VC | | Fire | 265474 |
Finished Bin | Original | / | 12/22/2006 | | MINDY | Location = Finished Bin by MINDY | | Finished Bin | 265471 |
Health Dept. | Original | A | 12/14/2006 | HEALTHDEPT | HEALTHDEPT | Approved as corrected in plan review dated 12/14/06. +Please contact LPirog at (719) 578-3132 with questions/comments. | | Health Dept. | 265476 |
Water Division | Original | A | 12/14/2006 | JEREMY | JEREMY | JMB 12-12-06 | | Water Division | 265491 |
Waste Water Div | Original | A | 12/14/2006 | JEREMY | JEREMY | JMB 12-12-06 | | Waste Water Div | 265489 |
Construction | Original | A | 11/27/2006 | TIMC | TIMC | | | Construction | 265463 |
Mechanical | Original | A | 11/27/2006 | DALEH | DALEH | | | Mechanical | 265479 |
Out to Review | Original | A | 11/27/2006 | JAN | JAN | Brian Ostler 303-477-2770 | | Out to Review | 265483 |
Finished Bin | Original | / | 11/8/2006 | | SHELLEY | Location = Finished Bin by SHELLEY | | Finished Bin | 265470 |
Plumbing | Original | A | 11/8/2006 | LARRY | LARRY | Approved as noted | | Plumbing | 265487 |
Enumeration | Original | A | 11/8/2006 | SHELLEY | SHELLEY | Given to LARRY by SHELLEY | | Enumeration | 265469 |
Plumbing | Original | / | 11/8/2006 | | SHELLEY | Location = Plumbing by SHELLEY | | Plumbing | 265486 |
Construction | Original | D | 11/8/2006 | TIMC | TIMC | Need to revise Pf design parameters. All old sheets must be removed from bound sets. Walk-thru ok. | | Construction | 265465 |
Construction | Original | / | 11/8/2006 | TIMC | TIMC | | | Construction | 265462 |
Enumeration | Original | A | 11/7/2006 | SHELLEY | SHELLEY | Given to TIMC by SHELLEY | | Enumeration | 265468 |
Construction | Original | / | 11/1/2006 | | JEREMY | Location = Construction by JEREMY | | Construction | 265461 |
Mechanical | Original | D | 11/1/2006 | DALEH | DALEH | need fire rated shaft or wrap for grease duct maintain 1500 fpm on grease duct size cut sheets for hood | | Mechanical | 265481 |
Plumbing | Original | / | 11/1/2006 | MINDY | MINDY | | | Plumbing | 265485 |
Mechanical | Original | / | 11/1/2006 | MINDY | MINDY | | | Mechanical | 265478 |
Out to Review | Original | A | 10/23/2006 | JAN | JAN | Bryan Ostler w/ mitchel plus 303-477-2770 | | Out to Review | 265482 |
Fire | Original | D | 10/20/2006 | CSFIRE | CSFIRE | 10/20/06 VC | | Fire | 265473 |
Electrical | Original | A | 10/11/2006 | SHELBY | SHELBY | KITCHEN OUTLETS TO COMPLY WITH NEC 210.8(B)(2) | | Electrical | 265466 |
Plumbing | Original | D | 10/6/2006 | LARRY | LARRY | It appears some trap arms exceed limits set in Tabel 10-1 2000 UPC Please identify combo waste and vent system Ant-1 is not a listed fixture trap. See plans for addtional comments | | Plumbing | 265488 |
Mechanical | Original | D | 9/21/2006 | RUSSELL | RUSSELL | Toilet exhaust duct shall be sleeved or without joints when routed in plenum, verify S.A. register as indicated on plans, Pharmacy area required minimum 480 cfm and also serving booth, storage & waiting areas, CO2 sensor to be set at 800 ppm, not 850 as indicated on drawings, see additional comments on sheet H2.1 | | Mechanical | 265480 |
Construction | Original | D | 9/20/2006 | TIMC | TIMC | Please revise allowable area calculations, per RBD records this building is of VB construction and is using sprinklers for unlimited area. Structural Engineer of record needs to cloud and initial all design roof load clarifications made to sheet S1.0. Structrural calculations need to be revised. No walk-thru. | | Construction | 265464 |
Health Dept. | Original | D | 8/22/2006 | JEREMY | JEREMY | CN 8-21-06 SEE PLANS STAMP | | Health Dept. | 265477 |
Water Division | Original | D | 8/21/2006 | WATERSVC | WATERSVC | BLZ +08-21-06; CS Fire Department approval of the RBD plans set is required prior to Water RBD approval by Utilities Development Services. | | Water Division | 265492 |
Waste Water Div | Original | D | 8/21/2006 | CSUREVIEW | CSUREVIEW | BLZ +08-21-06; Wastewater civil construction plans must be approved by Utilities Development Services and included in the RBD plan set. +Please call 719.668.8259 to schedule appointments or for general information.
Wastewater line will require a grease interceptor, please size and contact Development Services at 668-8259 for approval. | | Waste Water Div | 265490 |
Zoning/Planning | Original | A | 8/17/2006 | JEREMY | JEREMY | DMT 8-16-06 | | Zoning/Planning | 265493 |
Enumeration | Original | A | 8/16/2006 | MARLENE | MARLENE | | | Enumeration | 265467 |